The opinion of the. court was delivered by
It seems that the plaintiff, under certain written contracts with the Atlantic, Greenville, and Western Railway Company, had graded two sections of said railway, which contracts, amongst other things, specified the amount per cubic yard, which the plaintiff should be entitled to receive for such work, varying according to the nature of the materials handled; so much for each cubic yard of earth, so much for each cubic yard of loose or soft rock, and so much for each cubic yard of solid rock. These contracts also provided that the work was to be done under the supervision of the chief engineer of the company, and to be paid for according to his estimates. The chief engineer made his final estimates, ascertaining the total amount due plaintiff by the company under these contracts, upon which sundry payments were made by the company, leaving a
The plaintiff claiming that the amount due him by the railway company, which had thus been assumed by the defendants, had been fixed by the final estimates of the chief engineer of the company, and the defendants questioning the correctness of such estimates, and refusing to be bound thereby, with a view to settle this difference the parties, on January 28, 1887, entered into an agreement under seal, a copy of which is set out in the “Case,” whereby the plaintiff, in consideration of the sum of eight thousand dollars then paid to him by the defendants, agreed “to await the payment of the balance due” him for the work done on the railroad “until the said work shall be measured, and the value thereof computed by two competent civil engineers,” one to be selected by plaintiff and the other by defendants, with an umpire, “said work to be measured and computed as soon as may be practicable, and in accordance with the specifications of the contracts” with the railway company under which the work was done ; and the plaintiff bound himself “to accept and receive the balance which is shown to be due'me by said report of said engineers in full discharge of all claims against said Susong & Co. and against said railway company.”
On the same day both parties — plaintiff and defendants— signed a paper, not under seal, which reads as follows : “In pursuance of the foregoing agreement we, the undersigned, do hereby
In pursuance of such appointment, Ramseur and Harrison began the examination and measurement of one section of the work on February 8, 1887., and finished on the 19th of that month; the other section they began on the 12th and finished on March 18, 1887. They then made their report, fixing the value of the work at a sum much less than that fixed by the final estimates of the chief engineer of the railway company. It seems, however, that in making their estimate they calculated the whole amount of cubic yards at the rate fixed by the original contracts with the railway company for each cubic yard of earth, without taking into account the higher rates fixed by those contracts for loose rock and for solid rock. In the meantime, however, the plaintiff, claiming that he had a right to substitute another engineer in place of Cox, on March 14, 1887, addressed a letter to the defendants,- naming T. B. Lee for that purpose, which letter urns delivered on the 15th, the next day; but no notice was taken of it, and Lee never assumed to act.
The plaintiff, declining to recognize the report of the engineers, Ramseur and Harrison, brought this action to recover the balance due on the final estimates of the chief engineer of the
If, as stated by the Circuit Judge in his decree, the contract of December 21, 1886, whereby the defendants assumed the payment of the debts of the railway company, contained a provision that the work out of which the plaintiff’s claim arose should be measured and valued, we do not see how the plaintiff could maintain an action against these defendants until that provision ivas complied with. They were not parties to the contracts between the plaintiff and the railway company under which the work was done, for which he is now seeking compensation. They Avere under no liability Avhatever to the plaintiff originally, and if they have assumed such liability upon terms, it seems to us clear that in order to fix their liability such terms must be complied with. It is manifest that the defendants were unAvilling to assume liability for the amount due to plaintiff, as ascertained by the final estimates of the chief engineer of the railway company, and refused to accept such estimates as a proper ascertaiment of the amount of work done by the plaintiff. This being so, the parties
It may be that the plaintiff acted incautiously and unwisely in binding himself to await payment of his claim until the work should be remeasured, but he was probably induced to take such action by the present advantage of receiving a cash payment to a large amount; and il seems to us that he cannot fall back upon ■ his original rights without surrendering such advantage, which it does not appear that he has ever done or offered to do. There can be no doubt that the defendants were induced to make this large payment for the purpose of obtaining a remeasurement of the work, and if the agreement of January 28, 1887, has failed from no fault of either of the parties, but from the inability of one of the engineers originally selected to act, as both the special master and Circuit Judge seem to have found, then -we think it clear that the plaintiff would not'be entitled to maintain an action against the defendants until he had refunded the eight thousand
It only remains for us to consider whether there is any such error in the conclusion reached by the Circuit Judge prejudicial to the appellant as requires us to reverse it. The special master held that after the parties had made their selection of engineers, under the agreement of January 28, 1887, neither party could supply the place of Cox, who was unable to act, their power of selection being exhausted by its first exercise. He therefore held that the parol evidence offered to show the alleged clerical error or mistake, in designating the names of, the persons selected by each of the parties, was irrelevant, being wholly immaterial; and upon this and other grounds stated in his report he ruled out the testimony. The Circuit Judge does not seem to have made any distinct ruling upon this point. But from the fact that he says in his decree that the testimony conclusively showed that there was such clerical error or mistake, we infer that he regarded the testimony as admissible. He held, however, that the estimate made by Ramseur (who had been substituted by the defendants in place of Cox) and Harrison was not made in accordance with the specifications of the plaintiff’s contracts with the railway company, as required by the agreement of January 28, 1887, and thei'efore that such estimate was properly rejected by the special master; and in this we agree with his honor. It seems to us, therefore, that the question as to the admissibility of parol evidence to show a mistake in the designation of the engineers becomes wholly immaterial and need not be considered.
The Circuit Judge further held : “That after the failure of St. John Cox to serve as one of the engineers chosen for the new meas
In the case of Milnes v. Gery (14 Ves., 400), cited by appellant in support of his view, the application was that the court should appoint a person or persons, in place of the two selected by the parties to value the estate, who had failed to agree. There the proposition was to take away from the parties the right to make the selection and give it to the court, while here the order still left it to the parties to make the selection, and it was only in case of their refusal to do what they had agreed to do, that'the selection is to be made by the court. We do not think, therefore, that the ease is applicable. The other case relied on by appellant, Blundell v. Brettargh (17 Ves., 232), does not seem to be in point. In that case the agreement was for the sale of an estate at a price to be fixed by arbitrators, whose award should be made within a prescribed time. Before the time limited had expired, and before the award was actually made, one of the parties died, and the question was whether specific performance of the award thus made could be required. We do not understand that there was any question in that case as to the power of the court to require the parties to make another selection of persons to value the estate after the first had failed.
The plaintiff, in one of his grounds of appeal, raises the question whether he was not entitled to interest on his demand. Both
The judgment of this court is, that the judgment of the Circuit Court be affirmed.