Harrington Bros. v. City of New York

WOOLSEY, District Judge.

I give the plaintiff a decree herein with a reference to a master to compute the damages, if the parties cannot agree thereon.

I. This ease, which was before me once previously on a motion by a judgment creditor of the plaintiff to intervene, Harrington Brothers, Inc., v. City of New York, 35 B. (2d) 1009, is now before me on trial.

There are two questions now involved herein:

(1) The validity of the mechanic’s lien, on which the jurisdiction of this court in equity herein depends.

(2) The right of the complainant to a recovery against John J. Kelly, Inc., on the facts shown.

II. I hold that the lien was valid.

The notice of lien which was served under section 12 of the Lien Law of New York, at the department of finance of New York City, on the assistant deputy comptroller, on June 14, 1929, at 2:20 p. m., and entered on the audit lien docket of said department at 2:41 p. m. on said date, reads as follows:

“Notice under Mechanic’s Lien Law
“Comptroller of the City of New York, and to all others whom it may concern:
“Please take notice, and the undersigned hereby states:
“That Harrington Bros., Inc., is a corporation organized under the laws of the State of New Jersey, residing at and with business address and principal place of business at 590 Montgomery Street, Jersey City, New Jersey, and with its principal place of business within the State of New York at 1211 Wyatt Avenue, Borough of Bronx, New York City.
“That it has and claims a lien for the principal and interest of the value and price of the labor and materials hereinafter mentioned upon the moneys in the control of the .City of New York and upon the moneys of such municipal corporation applicable to the construction of the public improvement hereinafter mentioned, to the extent of the amount due or to become due under and on the contract with said municipal corporation hereinafter described, and hereby, further states:
“1. The name of the sub-contractor for whom the labor was performed is John J. Kelly, Inc. and Slattery Daino Co., Ine. is the contractor with the City of New York.
“2. The amount due the lienor is $9,-151.50, and the date when due is the 31st day of March, 1929.
“3. A description of the public improvement upon which the labor was performed is as follows: Section 4, Route 106, Municipal Rapid Transit under-ground railroad excavation and construction extending along the Grand Boulevard and Concourse, between 175th and 183rd Streets in the Borough of Bronx, City of New York.
“4. The kind of labor performed is as follows: furnishing trucks and labor for removal of excavated material.
“5. A general description of the contract pursuant to which such public improvement was constructed is as follows: Contract with Slattery Daino C'o., Ine. as contractor, dated December 3, 1928, covering Route 106, Section 4, known as the Concourse Route of the Municipal Rapid Transit Railroad subway.
“6. The time when the first item of work was performed was March 1, 1929, and the time when the last item of work was performed was March 31, 1929.
“7. This notice is filed pursuant to the Mechanic’s Lien Law of the State of New York, and all acts of the legislature of the State of New York amending or extending the same, or providing for filing mechanic’s liens on account of public improvements. The labor aforesaid was performed for the construction of said public improvement pursuant to said contract with said municipal corporation.
“8. Thirty days have not elapsed since the completion and acceptance of the construction of said public improvement.
“Dated, June 13, 1929.
“Harrington Brothers, Ine.
“By James Vincent Harrington, Treas.”

This lien was duly bonded and discharged on June 20, 1929, on filing with the comptroller of an undertaking given by defendant Continental Casualty Company, duly» approved by an order of the Supreme Court of New York.

It developed on the trial herein that, payment for the work done each month was made according to the informal arrangement *505existing between tbe complainant and Kelly on the 10th of tbe month following; consequently tbe defendants claim that tbe notice of tbe date when tbe amount claimed was due is subject to a fatal variance and tbe notice of lien is thereby made invalid.

But it is quite clear that tbe inaccuracy as to this date was not intentional and consequently must be deemed a venial mistake.

Notice under tbe Lien Law is supposed to be given by laymen, and its purpose is to make bis pay secure to tbe workman. In view of section 23 of tbe Lien Law, which requires, in order to accomplish this result, a liberal construction of the notice and provides that “a substantial compliance with its several provisions shall be sufficient for tbe validity of a lien and to give jurisdiction to tbe courts to enforce tbe same,” it seems to me that to bold tbe notice of lien in this case invalid for this minor and immaterial inaccuracy would be to defeat, in this case, tbe purpose of tbe Lien Law, without any real reason for so doing.

My decision that this lien is valid notwithstanding tbe mistake as to- tbe due date of tbe payment is supported by tbe principles of construction laid down for such notices in Goldberger v. 74 Second Avenue, 252 N. Y. 336, 342, 343, 169 N. E. 405; Ringle v. Wallis Iron Works, 149 N. Y. 439, 442, 443, 446, 44 N. E. 175.

In tbe last-mentioned ease, O’Brien, J., ■dealt with tbe bind of criticism of tbe notice which I have beard in this ease, as follows, at page 446 of 149 N. Y., 44 N. E. 175, 177: “Tbe statement was not, in fact, strictly correct; but it by no means follows that it was false in a legal sense. When we bear in mind that such contracts are often executed by agents and employees, and that they are not always expressed in terms so clear and explicit as to be free from doubt or ambiguity, it must be an exceptional ■ ease where an appellate court will be warranted in assuming that an incorrect statement in the notice that tbe contract has been performed, or that tbe contract price is due, is a false statement, within tbe meaning of tbe rule. In this ease tbe view of tbe court at special term that it was tbe result of an honest error is tbe more reasonable and just conclusion.” Cf., also, Schwartz & Co., Inc., v. Aimwell Company, 204 App. Div. 769, 772, 773, 198 N. Y. S. 838, and Barrett v. Schaefer, Jr. & Co., 162 App. Div. 52, 55, 57, 146 N. Y. S. 1056.

Intentional or willful misstatements are, of course, held to vitiate a notice of lien. Aeschlimann v. Presbyterian Hospital, 165 N. Y. 296, 302, 303, 59 N. E. 148, 80 Am. St. Rep. 723.

Here there is not tbe scintilla of a suggestion that the mistake in tbe due date was willful or intentional.

It would be a curious result on this vague record if this lien, which is tbe only really fixed and clear bit of evidence in it, should go by the board.

III. Tbe arrangement between Harrington, tbe complainant, and Kelly, was oral and of tbe most informal kind.

In my opinion, it was a promise, but not a binding contract, by Kelly to use Harrington’s trucks as be needed them to take excavated materials away from tbe scene of the Slattery-Daino Company’s operations on tbe subway.

There was not even a promise to use a fixed number of trucks.

Indeed, at tbe commencement of the operation tbe charge for each truck load was not fixed until after tbe trucks bad begun working.

Tbe result is that the arrangement here comes within tbe well-known category of so-called “requirement contracts,” in which, if tbe requirement is not based on a fixed or a priori reasonably ascertainable requirement but depends on the wish, will, or whim of one of tbe parties, tbe so-called contract is not binding on either party as to future performance, although for material or services actually furnished an action is maintainable. Cf. American Cotton Oil Co. v. Kirk et al., 68 F. 791 (C. C. A. 7); Crane et al. v. C. Crane & Co., 105 F. 869, 873 (C. C. A. 7); Cold Blast Transp. Co. v. Kansas City Bolt & Nut Co., 114 F. 77, 81, 82, 57 L. R. A. 696 (C. C. A. 8).

So here, under the principle laid down in those eases, for tbe trucks furnished by Harrington to Kelly during March, 1929, Harrington is entitled to recover. This is so, notwithstanding Harrington’s failure to continue tbe work after March 29th, for tbe legal result of tbe arrangement between Harrington and Kelly was that Harrington was not bound so to continue it.

IV. The first four counterclaims were not pressed at tbe trial, and no proofs put in to support them. They are therefore dismissed.

Tbe fifth counterclaim for storage was admitted by tbe plaintiff, although tbe precise amount due was left open, as I understand tbe stipulation.

*506V. An order- may be entered providing that this memorandum shall stand as the findings of fact and conclusions of law herein. Briggs v. United States, 45 F.(2d) 479, 480 (C. C. A. 6); Lewys v. O’Neill (D. C.) 49 F.(2d) 603, 618; and cf. The El Sol and The Sac City (D. C.) 45 F.(2d) 852, 856, 857.

VI. If the parties cannot agree as to the amount to be allowed to the plaintiff hereunder, the suit will be referred to a special master to fix the damages. Settle orders on two days’ notice.