Appellee recovered judgment against appellant in an action which alleges the breach of a contract to furnish the kind of mortar that had been specified by an architect for use in the construction of a building which appellee built under an agreement with Thomas Watts, the owner. The architect’s specifications called for mortar containing one part of cement to two and a half parts of clean sharp sand, and gave permission that “the mortar, as above specified, may be made by the Blue Diamond process.” It is undisputed that the mortar originally used contained one part of cement to six parts of sand, and therefore did not comply with the'specifications but was of an inferior quality. Upon completion of the building, there developed through the mortar joints of the outside walls leaks which appellee repaired and stopped up, in compliance with the architect’s requirements and its agreement with the owner. The judgment was for the amount expended in pointing up the mortar and making the necessary repairs, together with interest.
The architect testified that appellant’s method of mixing mortar was merely a mechanical one, that it regularly made its mixture according to his specifications, but whether they had been complied with could
The real question in the case is whether the parties entered into the contract alleged in appellee’s petition; and its solution depends upon the legal effect of what was said in a conversation that was held between Charles T. Allen and W. H. Brooks. The former was appellee’s secretary and general manager, and the latter was appellant’s president; and there was no question as to the authority of either to act for the corporation he represented. Allen’s testimony may be stated in condensed form as follows: It was appellee’s duty to buy material for the Watts Building. Brooks came to see me and solicited an order for the mortar. I explained that we were doing this work under the supervision of an architect, and would be governed by his decision; and that he would have to comply with the architect’s specifications. He then told me “that he had already done that,” and that the architect “had incorporated” appellant’s mortar “in the specifications.” “On that assurance, I told him that we would use the mortar.” We agreed on the price, which was either $6.75 or $7.25 per yard. “At the time I made the contract with Mr. Brooks to use Blue Diamond mortar, we had intended to do the masonry work ourselves, and, with that in view, I had bought the brick, terra cotta and the mortar. The Lewis Building Company * * * made us a proposition that was so advantageous that we decided to let them do it under a sub-contract. So I entered into a contract with them, explaining to them that we had obligated ourselves to use Blue Diamond mortar, and that we would expect them to use the stuff that we had bought. * * * The mortar was furnished to the sub-contractor, Lewis Building Company, and it paid for-the mortar. The price that the sub-contractor bid for the work was based on the price that we had received for the mortar. My understanding was that the mortar was furnished to the Lewis Building Company under the contract that we made with Mr. Brooks.” In giving his version of the conversation, Brooks testified that, after learning that Allen had secured the contract for the construction of the Watts Building, he went to him and asked him if he was going to do the brick work himself or sublet it. “Mr. Allen told me he did not know, but he might sub-let the brick work on that building. I do not remember having any other talk with Mr. Allen in regard to furnishing mortar for the Watts Building. I was waiting to see whether he would do the brick work or sub-let it. When I discovered that Mr. Allen was not going to do the brick work on the building himself, I solicited the brick work from the Lewis Building Company, the sub-contractor.” He further testified that before he went to see Allen he had already interviewed the architect, but was not familiar with the building specifications, although he knew that Blue Diamond mortar could be used; and admitted that he told Allen it had been approved for the Watts Building. It was appellant’s practice to sell its material through dealers; and in this instance the order was handled through the Standard Building Material Company, but appellant itself delivered the mortar to the Watts Building in its own trucks. At the dose of the evidence appellant moved for a directed verdict in its favor on the ground that the contract alleged had not been proven. The trial court denied this motion, and instead charged the jury that the contract sued on had been established, if they believed Allen’s testimony to be true, but if they did not so believe, in view of Brooks’ testimony, that they must find that there was no contract between the parties and return a verdict for appellant. A motion for a new trial was made on the ground, among others, of newly discovered evidence based upon the affidavit of J. D. McEaddy, member of the firm of the Lewis Building Company, subcontractor, to the effect that he represented this firm in the negotiations with Allen which resulted in the subcontract; that Allen- did not represent to the subcontractor that he had the contract with appellant, but merely requested, “everything being equal,” that its mortar be used. In a supporting affidavit Brooks stated he was unaware that appellee would present evidence on the trial to prove a contract between 'the parties- to the suit whereby appellant agreed to furnish mortar, and that his first knowledge of the claim of the existence of such a contract was when Allen gave his testimony; and that after Allen testified McEaddy could not be located and produced as a witness at the trial.
There are a number of assignments of error based upon rulings during the course of the trial, but they all relate to the single point whether Allen’s testimony was sufficient to prove the contract sued on. Of course, according to Brooks his conversation with Allen did not reach beyond the stage of negotiations, and the only contract made was with the subcontractor. But this theory disappears along with the rejection by the jury of
Denial of the motion for a new trial is also assigned as error, .but clearly no abuse of the trial court’s discretion is shown. Appellant must have known that appellee would undertake to prove the existence of the contract alleged, and by the exercise of reasonable diligence could have ascertained as well before as after the trial what it is now claimed a member of the firm of subcontractors would testify.
The judgment is affirmed.