Smith v. Wilcox

Mr. Justice AVolverton,

after stating the facts in the foregoing terms, delivered the opinion of the court.

*3251. Appellants’ counsel first insist that a subcontractor is not within the. purview of the mechanic’s lien statute, and hence he cannot claim its benefits. The question is wholly one of construction. “Every mechanic, artisan, machinist, builder, contractor, lumber merchant, laborer, teamster, drayman, and other person performing labor upon or furnishing material, or transporting or hauling any material of any kind, to be used in the construction, alteration, or repair, either in whole or in part, of any building, wharf, * * or any structure or superstructure, shall have a lien upon the same for the work or labor done or transportation or material furnished at the instance of the owner of the building or other improvement or his agent; and every contractor, subcontractor, architect, builder, or other person having charge of the construction, alteration, or repair, in whole or in any part, of any building or other improvement as aforesaid, shall be held to be the agent of the-owner for the purposes of this act”: B. & C. Comp. § 5640. “A subcontractor is one who has entered into a contract, express or implied, for the performance of an act with the person who has already contracted for its performance”: Phillips, Mech. Liens, (3 ed.) § 44. A subcontract is defined to be “a contract by one who has contracted for the performance of labor or service with a third party for the whole or part performance of that labor or service”: Bouvier, Law. Diet. The term “subcontractor” therefore is not inappropriate to designate one who has contracted with the principal contractor to perform the whole as well as a part of the service which the latter has undertaken to perform. The statute was certainly intended to be, and is by its tefms, very comprehensive in its scope and bearing, as it concerns persons performing labor and furnishing materials, one or both, in the construction or repair of the structures or superstructures designated. A subcontractor is not *326specially designated by name, as are others in the statute, as entitled to its benefits; but, if the term “ contractor ” is to be treated as used in its generic sense, he certainly falls within the category. He is assuredly a person who performs labor or furnishes materials, one or both, as the case may be ; and in the case at bar he has not only done both, hut he has erected and completed the entire structure. And would it not seem strange that a contractor, who did the same work, and workmen and materialmen who are employed and furnish materials at his instance and request, should have the benefit of the statute, and yet that the subcontractor should be eliminated ? True, there is no contractual privity between him and the owner. Neither is there between the laborer or the materialman and the owner, where employed by the contractor, but he stands in identically the same relation to the owner as the latter.

2. To facilitate the acquirement of the lien, however, the statute has made the original contractor an agent of the owner while in charge of the construction. Necessarily, he is given the primary control thereof. He may authorize some other person to superintend or take the management of the work, or the parties may agree that an architect or a special builder shall be in charge, but unless there is some such provision to shift the supervision he is necessarily intrusted with it. Being in entire charge, therefore, of the construction, he may subject the building to a lien by the employment of any person to perform labor or furnish materials therefor. A subcontractor, as we have seen, is within the range of such employment, so that he is manifestly within both the letter and spirit of the statute. The principle upon which mechanic’s liens are upheld, where they are given to persons other than those contracting directly with the owner, is that the contractor becomes, for the purpose of the statute, an agent of the owner, and thus do all such persons indirectly con*327tract with the owner: Osborn v. Logus, 28 Or. 302 (37 Pac. 456, 38 Pac. 190, 42 Pac. 997). Some authorities base the right to a lien exclusively upon the circumstance that the labor and materials have been employed and used in the structure and have thereby inured to the benefit of the owner. In all cases supporting the doctrine, however, it is to be observed that there existed either an express or implied contract between the owner and the principal contractor for the construction of the improvement, which is not inconsistent with the view that the reason that such subcontractors and materialmen are entitled to impose a-burden on the parties, depriving the owner of his property, is that the latter has impliedly, through the agency of the principal contractor, contracted for such material and labor: 20 Am. & Eng. Enc. Law, (2 ed.) 350, 351, and note to latter page.

3. The next question is one arising under the evidence, and is whether the plaintiff entered into one or two contracts with Dammeier Company for the construction of the Wilcox and Turple dwellings. The plaintiff testifies that Dammeier told him that he had some buildings he wanted him to figure on, and gave him the plans and specifications for the two; that witness looked them over, but did not want to carry the whole business, and took the specifications for one of them (the Wilcox dwelling) home with him, made the estimate, and told Dammeier that it figured up to $1,335, but that, if the water was in front of the house, he would do the work for $1,325 ; that on investigation it was found that the water was not in front of the house, and it was finally agreed that Dammeier Company would allow $40 for bringing it in, one pipe being all that was needed for both houses, and that witness then agreed to build the house for $1,345; that Dammeier thought there was a little difference in the other plans, and wanted witness to figure on them also, in *328order to see if lie could not do the work for less; that witness then looked them over again, and said that he would not spend any further time in figuring upon them, but that, if Dammeier wanted to let him have both houses at the same figure, namely, $1,345, he would take them, and that Dammeier agreed to it. George H. Dammeier testifies that he let plaintiff have the contract to build the two houses for Wilcox and Turple, and was to give him $1,345 for building each house, that amount being specified and agreed upon; that the contract for the two houses was made at the same time, at the same interview, but was not reduced to writing; that the witness had a contract with Wilcox to build him a house on his premises, also one with Turple to build a house on his premises, and that his contract with plaintiff was for building the two houses for $2,690; that they made up the price for the two houses by doubling his estimate for the one. It is a little difficult to determine from this testimony, which is, in substance, all that was offered upon the subject, whether the parties entered into separate contracts for the construction of each house, or a single one for the construction of both. The work of construction was carried forward upon both dwellings concurrently, the plaintiff letting subcontracts for doing portions of the work on both jointly, and it might be said that he treated them, so far as the employment of his workmen was concerned, as one undertaking. This is a circumstance of some weight, perhaps, in determining the character in which he contracted with Dammeier Company for their construction, whether for each separately or for both as an entire undertaking, but it is not conclusive. We think, however, the feature of controlling importance is that Dammeier Company had separate contracts with Wilcox and Turple for the construction of these buildings, and it was its purpose in dealing with plaintiff to have the structures erected in accord with its under*329taking with them. After plaintiff had made his estimate on the Wilcox house, Dammeier tried to get him to contract the Turple house for less, but he would not assent to it, and so they agreed upon $1,345 for each house. Having kept' the estimates separate, perhaps for Dammeier Company’s convenience and benefit, the most natural thing would be to carry on the negotiations to the end upon the separate basis. This is what plaintiff says they did, and is what we are warranted in concluding that they in fact did. The plaintiff was justified, therefore, in filing separate claims or liens: Beach v. Stamper, 44 Or. 4 (74 Pac. 208).

4. The evidence shows that Dammeier Company and its agent have made payments to plaintiff and his subcontractors and employés indiscriminately, without any reference to the idea of separate contracts, and it is insisted that it is impossible to say how much has been paid upon the Wilcox building and how much upon the Turple building, and that for this reason the liens are void. The payments were made without directions by the debtor as to how they should be applied, so the creditor, the plaintiff herein, had the right to make the application; and having admittedly made it upon an altogether equitable basis, the defendants cannot be heard to complain. He is at fault that he did not protect himself against the defalcation of the original contractor in allowing claims to be preferred against the building by exacting sufficient surety to insure a faithful compliance with the contract to construct.

5. But it is further ui’ged that the subcontractor has made a profit, and that it is contrary to the spirit of the statute to allow him to do so and claim a lien for it; that the plain principle of the statute is, not to make the owner responsible for the performance of such contracts, but to require him to pay the reasonable worth of the labor or materials when they have added to the value of liis prop*330erty. We have seen that the principle upon which the lien is given is that the subcontractor, artisan, laborer, or materialmen have by implication a contract with the owner, and, so long as they do not pass beyond the terms and scope of the original contract, which is the foundation of their privity with the owner for the purpose of the statute, they are entitled to claim a lien. In the present case the plaintiff is not only within the principle, but the work done must be considered to have been reasonable, for it was done at a price less bjr $165 on each building than that which the defendants contracted to pay Dammeier Company therefor.

These considerations affirm the-decree of the trial court, and such will be the order of this court. Affirmed.