Submitted on brief February 6, modified March 6, 1917.
On the Merits.
(163 Pac. 435.)
Consolidated suits to foreclose mechanics’ liens by Martin Johnson and others against Josephine Paul-son and others. From a decree for plaintiffs, defendants Josephine Paulson and W. J. Clemens, trustee, appeal. Decree entered in accordance with opinion.
In Banc. Statement by
Mr. Justice Benson.Suits were begun by the several plaintiffs to foreclose mechanics’ liens. It appears that the defendant Josephine Paulson was the owner of the property and the plaintiff A. S. Paulson, her husband, was the contractor engaged in building a dwelling-house for her. After the issues were joined these suits were united and tried as one. From a decree for the plaintiffs the defendants Josephine Paulson and W. J. Clemens, trustee, appeal.
Submitted on brief without argument under the proviso of Supreme Court Rule 18: 56 Or. 622 (117 Pac. xi). Modified and Decree Rendered.
For appellants there was a brief by Messrs. Staple-ton <& Conley.
*244• For respondents Martin Johnson, Oscar Carlson, B. E. Remaley, Hansen & Holding and Park McDonald, there was a brief by Messrs. Hall & Lepper.
For respondent A. S. Paulson, there was a brief by Messrs. Schmidt & Schmidt.
For respondent J. B. Winstanley & Co., there was a brief by Messrs. Angel & Fisher.
For respondent Oregon Door Company, there was a brief by Messrs. Asher & Johnstone.
Mr. Justice Bensondelivered the opinion of the court.
5. Taking up the several claims in their order we shall first consider that of Martin Johnson, a carpenter, whose notice of lien was for an unpaid balance of $191.40, and to whom the trial court awarded $159.12. Defendants contend that plaintiff is not entitled to a decree since his complaint alleges an express contract while his proofs disclose an implied contract only, and that the judgment of the court is erroneously based upon quantum meruit. The complaint alleges an express agreement to pay $3.50 a day and the affirmative answer alleges an express contract for the payment of $3 a day. Hence the nature of the agreement was not an issue in the case and need not be discussed further.
6, - 7. The second assignment of error urges that the plaintiff ought not to prevail because he knowingly filed his claim for a greater sum than was due. The difference in amount between that claimed in the notice and that allowed by the court arises out of the dispute as to whether plaintiff is entitled to $3.50 or $3 a day. The testimony offered by the plaintiff is to the effect that about three weeks before he began to work upon *245defendants’ house he was employed by the same contractor, A. S. Paulson, to work upon another building; that when the job was completed Paulson paid him at the rate of $3 a day and when he protested that he was entitled to $3.50 a day Paulson silenced him by saying:
“Well I took this job cheap and I can’t afford to pay any more on this job, but I will pay more on the next job.”
When Johnson began work on the building involved in this controversy he understood that he was working for $3.50 a day under the promise above quoted. Paul-son testifies with equal positiveness that there was an express understanding that Johnson was to have $3 a day. It is the settled law of this State that a willful overstatement in the lien notice of the amount due will render the lien void: Nicolai v. Van Fridagh, 23 Or. 149 (31 Pac. 288); but in the same opinion we find the following language:
“The authorities are generally agreed that where in the hen filed there is an honest mistake in the amount or price of labor, or the quantity or value of material furnished, about which there might be a difference of opinion requiring evidence to ascertain the true facts, it will not defeat the hen.”
As we read the evidence before us, such is the situation in the present case and the trial court did not err in finding that plaintiff was entitled to $3 a day.
The second claim is that of Oscar Carlson, also a carpenter, with reference to which all that has been said in regard to Johnson’s claim applies with equal force and with the same result.
8, 9. The third claim is that of B. E. Bemaley, a carpenter, who filed a hen claim for $194.52 upon which the decree of the trial court allowed him $167.52. The assignments of error as to this case are identical with *246the ones already considered. The complaint alleges an'express contract for $3.50 a day and the affirmative answer pleads an express agreement for $2.50 a day. As already suggested this leaves no issue as to the nature of the contract and we turn to the evidence to discover the terms of the agreement. Plaintiff testifies that he was employed to take the place of one Park McDonald who had received an injury which had disabled him and, thinking such employment would be brief, said nothing about wages when he began work; but, about a week later at the request of McDonald, he took some papers to Paulson to be signed which related to proof of injury and his right to relief under the workmen’s compensation act; that Paulson signed a paper stating that McDonald was working for $3.50 a day and plaintiff upon observing this said to Paul-son: “That is the wages you are paying?” and the latter said, “Yes.” The witness further says: “And he promised me under those conditions three and a half a day and that is the reason I filed my lien in that way.” The contractor testifying for defendants says that there never was any agreement as to wages but that he told McDonald that he would pay Remaley “whatever he is worth.” In referring to signing the paper which stated that McDonald was receiving $3.50 a day Paulson explains the conversation with Remaley thus:
“He asked me if that was what I was paying him and I said yes, meaning McDonald, which I was. He says, ‘Is that what you are paying him?’ and I said ‘Yes.’ Q. Was there anything said about what you would pay anybody else on the job? A. No, never, I never told my business to anybody else.”
This constitutes all the evidence as to the terms of Remaley’s employment. We think that the evidence *247justifies a finding in accordance with plaintiff’s testimony but since he has not appealed, the judgment for $3 a day should be affirmed.
10, 11. The next claim is that of Hansen & Holding, plasterers. Their notice of lien claims a total of $96.22, which was allowed in full by the trial court. The complaint alleges that this was the agreed price for the work and the answer avers that the stipulated sum was $72,34, and that one of plaintiffs’ employees, a lather, had filed a lien for his labor which, with costs, defendants had been obliged to pay in the sum of $54, leaving but $18.34 due to plaintiffs at the time they filed their notice which fact was then known to them. The complaint and the notice of lien both segregate the claim into two classes: (1) Plastering 1,247 yards at 6 cents a yard, $74.82; and (2) “extra work” consisting of plastering outside gables, outside brick work and lining two fireplaces with fire brick for a total of $21.40. There is much conflict in the testimony but we think a preponderance of the evidence establishes the facts that the laborer who did the lathing was not in the employ of plaintiffs and that the “extra work” was not a part of the express contract,but was to be done and paid for as a per diem job with no agreement as to what the daily wage should be. It appears to be a well-established doctrine that if a plaintiff alleges in his pleading an express contract, he cannot recover upon proof of a quantum meruit: Schade v. Muller, 75 Or. 225 (146 Pac. 144); 9 Cyc. 749; Craft v. Dalles City, 21 Or. 53 (27 Pac. 163); and, therefore, plaintiffs cannot recover in this proceeding their claim for extra work. However, this does not invalidate their demand for work done under the terms of their express contract since it does not appear that their claim was filed in bad faith or that the *248charge for extra work was not due them. They fail as to that part of their claim through an error in pleading. It follows that the decree as to them must be modified by deducting from théir judgment the sum of $21.40.
12. We next consider the claim of J. B. Winstanley Company for $235.40, a balance alleged to be due upon account for building materials. Defendants answer by pleading payment; alleging that plaintiffs accepted the promissory note of Josephine Paulson and A. S. Paulson in payment of their demands. Plaintiffs deny this and allege that the note was accepted by them as collateral security and not otherwise. The evidence utterly fails to disclose any express agreement that the note in question was to be accepted as a payment of the debt. In Black v. Sippy, 15 Or. 574 (16 Pac. 418), Mr. Chief Justice Lord says:
“Nothing is better settled than that accepting a note is not payment of an account, nor is accepting one note in renewal of another payment of the old note, unless there is an agreement that the note should be accepted in payment. In The Kimball, 3 Wall. 45 [18 L. Ed. 54], Mr. Justice Field said: ‘By the general law as well of England as of the United States, a promissory note does not discharge the debt for which it was given, unless such be the express agreement of the parties. It only operates to extend until its maturity the period of the payment of the debt. The creditor may return the note when dishonored, and proceed upon the original debt. The acceptance of the note is considered as accompanied with the condition of its payment. Thus it was said, as long ago as the time of Lord Holt, that ‘a bill shall never go in dischargé of a precedent debt, except it be a part of the contract that it should be so.’ ”
This case has been repeatedly cited with approval by this court, the latest instance being French v. *249Columbia Life & Trust Co., 80 Or. 412 (156 Pac. 1042 and 1058). The decree as to these plaintiffs is therefore affirmed.
13. We next consider the claim of the plaintiff Oregon Door Company wherein a lien was filed for $721.70, upon which the trial court gave judgment for $673.10. The defendants object to this decree upon the grounds: (1) That the plaintiff has filed a claim for more than was due; and (2) that it had accepted a note for $200 secured by mortgage as part payment of its demand, prior to the date of filing the lien. It appears from the evidence that a representative of the Oregon Door Company called upon the contractor for the purpose of selling him certain doors, windows and other building materials; that after some consultation and deliberation the salesman prepared a list of such materials upon a printed form supplied by his company in which it was sought to itemize as. nearly as possible what would be required, and delivered a carbon copy thereof to Paulson. A few days later he again saw Paulson and after the prices had been extended and the necessary addition made fixing the total cost of the items, the following words were written at the bottom of the last page: “We agree to furnish material per this list for $542.00. Order OK. (signed) A. S. Paulson.” At the top of each sheet were printed these words: “Examine this estimate, as we propose to furnish only the quantities and sizes enumerated here.” Thereafter some slight changes were made and some parts of the order canceled for which the notice of lien concedes a credit of $24.95 and, thereafter, plaintiff delivered other additional material for which in the notice there is a charge of $204.65, making a total claim of $721.70. It is the contention of defendants that plaintiff made an absolute bid to *250furnish whatever was necessary to complete the building for the fixed sum of $542, and it is not entitled to make any demand for extras except, perhaps, for some insignificant items in connection with the garage which the contractor admits was an afterthought. It further appears from the evidence that there were some errors of bookkeeping arising apparently from making certain exchanges in doors, from one kind to another, and neglecting to make proper credits upon returning those not used whereby the claim of lien fixes the amount due at $48.60 more than it should have been. There is nothing in the record to indicate that this error was willfully made or anything more than an honest mistake and it should not be permitted to vitiate the entire lien: Cooper Mfg. Co. v. Delahunt, 36 Or. 402 (51 Pac. 649, 60 Pac. 1); Rowland v. Harmon, 24 Or. 529 (34 Pac. 357); Fitch v. Howitt, 32 Or. 409 (52 Pac. 192); Stewart v. Spalding, 71 Or. 310 (141 Pac. 1127).
14. As regards defendants’ contention that the plaintiffs’ contract was to furnish all the material necessary to complete the job for the fixed sum of $542, we think it is not sustained by the evidence.
Referring to the defense that plaintiff had accepted a secured note for $200 in part payment of his claim, we think that the evidence sustains plaintiffs’ contention that he agreed to accept a secured note for $200 of the debt upon prompt payment of the balance and, as such payment was not made, he returned the note and mortgage to Paulson by mail. It follows that the trial court did not err in its decree as to this claim. A decree will be entered here in accordance with this opinion. Modified. Decree Rendered.