O'Brien v. Sexton

Mr. Chief Justice Magruder

delivered the opinion of the ■Court:

This is ah action of assumpsit begun on April 20, 1888, by the appellant for the use of Bich and Stone against the appellee. Judgment in the trial court was in favor of the defendant below, the appellee here, and this judgment has been affirmed by the Appellate Court, whence the cause is brought before us by appeal.

The declaration contains the common counts only, to which the defendant filed the plea of the general issue. The record shows a written stipulation, signed by the attorneys of both parties, by which it is agreed “that either of the parties may introduce evidence under the pleadings as they stand, the ■same as if an appropriate special count or special plea had been filed in the case, and the said defendant may introduce-any evidence which would be a defense under the statute of limitations, or by way of set-off, or recoupment, which would be admissible if the subject matter were properly pleaded.”

On December 31, 1882, appellant, O’Brien, and appellee, Sexton, entered into a written contract under seal, by which O’Brien agreed, that he would provide all labor, workmanship and materials and execute to completion all the plastering work required in the erection of a block of niné buildings, containing 36 flats, known as Hotel St. Benedict, and located at the corner of Chicago Avenue and Gass Street in Chicago, in accordance with the plans and specifications prepared by J. J. Egan, architect, and annexed to the contract, the work and materials to be subject to the direction and acceptance of Egan and of Sexton, who was to act as superintendent; and' by which Sexton agreed to pay O’Brien $9990.00 as follows: $3000.00 when the work is lathed and browned; $2000.00 'when the work is second coated;, balance, less 15 per cent, 'when completed; the 15 per cent reserved to be paid when work is accepted. Under the specifications, O’Brien was to do lathing, plastering, calcimining, patching, repairing, finishing, •cleaning and drying, and to commence the plastering within •six days after one house was roofed and enclosed, and to continue the work so as to have the entire block plastered within six weeks from the commencement of the plastering. The ■owner, Sexton, was to have the building suitably enclosed with temporary doors and window sashes, etc.

O’Brien or the men under him worked at the lathing and ■plastering until the close of Saturday, April 21,1883, or until sometime in the forenoon of Monday, April 23, 1883, at which time the work, which O’Brien was to do under the contract, liad not yet been finished. After April 23, 1883, O’Brien did no more work. Before that day Sexton had paid him $6225.00 ■upon the contract, and thereafter paid some of his workmen $943.00, making $7168.00 in all, and leaving $2822.00 unpaid. Appellant claims that the cost of completing the contract should not have been more than about $400.00, and that there is due to him the difference between $2822.00 and $400.00, ¡tówit: $2422.00, besides interest and the value of certain materials and utensils alleged to have been appropriated by appellee. On the other hand, appellee claims that he was-obliged to pay out more than $5000.00, in addition to said1 sum of $'7168.00, in order to complete the work left unfinished' by the appellant, and that, in addition to all this, he lost more-than $5000.00 in rents by reason of the delay in the completion of the work.

The pivotal fact in the case is the cause of the failure of appellant to do anything more towards the fulfillment of the; contract after April 21 or April 23. The testimony is clear,1 that O’Brien’s men worked until the close of April 21. The-; testimony is not clear as to whether any work was done on; April 23, though appellant claims that some work was done-, on the morning of that day. Was the failure of O’Brien to. finish the work due to his fault, or to the fault of appellee Did appellant abandon the work and neglect and refuse to pro- - ceed with it, or did appellee refuse to allow the appellant to-, proceed and prevent him from fulfilling his contract ? These, were questions for the jury to decide. Appellee claimed, that appellant abandoned the work without good cause; and there-, was testimony tending to support this view. Appellant claimed,, that appellee refused to furnish him with money to pay the-workmen what was due to them on the evening of April 21,, and forcibly prevented him from entering the building, and employed outside parties to complete the contract without the-, consent of the appellant and without notice to him. There-| was evidence tending to support this contention.

No instructions were given for the plaintiff below, and none-seem to have been asked on his behalf. The court gave some-fourteen instructions for the defendant, and, among others,, the following:

“Tenth—If the jury believe, from the evidence, that there was a written contract between O’Brien and Sexton for the; ‘doing of the plastering in question, and that O’Brien failed and refused to perform his part of said contract, and abandoned said plastering work in an unfinished state, and that Sexton did not release O’Brien from said contract, nor waive the performance of it by him, nor prevent O’Brien from completing his contract, then the jury are instructed, as matter of law, that O’Brien cannot recover anything under said written contract. And even though the jury may believe, from the evidence and under the instructions of the court, that O’Brien is entitled to recover-under an implied contract for some plastering done by him, yet the jury are instructed, as matter of ■ ' law, that he cannot, under such implied contract, recover for any work done or materials furnished before April 20, A. D. 1883, but only for work done and materials furnished on or after April 20, A. D. 1883, if done and finished under a contract not in writing, or an implied contract.

“Eleventh—If the jury believe, from the evidence and under the instructions of the court, that O’Brien is not entitled to ■recover under a written contract for the plastering in question, ; but is entitled to recover under an implied verbal contract for plastering done by him, then the jury are instructed that the' Statute of Limitations precludes a recovery by O’Brien for! any plastering done by him more than five years before the. commencement of this suit. This suit was commenced April ' 20, A. D. 1888.”

These were the only instructions given which related to the statute of limitations, and we think that, under the facts of this case, they were erroneous and calculated to mislead the jury.

Under the stipulation of the parties the declaration is to be .regarded as containing not only the common counts, but a .special" count founded upon a breach of the contract. If the defendant, Sexton, forced the plaintiff, O’Brien, to abandon ,the work at the close of Saturday, April 21, he was guilty of-.a breach of the contract at that time, and, if the plaintiff was entitled to recover by reason of such breach, the cause of action accrued at that time. This suit, having been begun on April 20, 1888, was commenced one day less than five years after the plaintiff did the last work upon the defendant’s building.

If the action be regarded as a suit upon the express contract in writing brought to recover damages for a breach thereof, the cause of action was not barred on April 20,1888.

The jury had a right to consider the evidence tending to show, that the defendant prevented the plaintiff from completing his contract, as well as that which tended to show, that plaintiff abandoned his contract without excuse. If they had found from the evidence, that the plaintiff had been improperly prevented by the defendant from completing the contract, or, in other words, that the plaintiff had been improperly discharged from the performance of the work before its completion, he was certainly entitled to'recover under the common counts what was due to him for the work which he had actually performed under the contract. In Catholic Bishop of Chicago v. Bauer, 62 Ill. 188, we said: “Where there has been only part performance, and the remainder has been waived ■or prevented, and the work performed has been accepted, then, * * * recovery may be had for the contract price of the ■service performed under an indebitatus assumpsit.”

The above instructions contemplate, that the jury might be ¡instructed in favor of a right of recovery upon an implied ,agreement^ “When a servant is discharged without sufficient legal excuse before the expiration of his term, * * * he ¡may elect to treat the contract as rescinded and at once bring ,-an action for the value of the services rendered.” (Wood’s Law of Mas. and Serv. (2d ed.) see. 127.)

Whether the measure of the recovery in this case depended upon the contract price of the work actually done under the contract, or upon an implied agreement to pay so much as the Tabor and materials were reasonably worth, it was wrong to instruct the jury that there could be no recovery for work done or materials furnished before April 20, 1883, for the reason that the work to be done, or the service to be performed, by appellant for appellee, was an entirety. What appellant agreed to do was to plaster the whole building; and the lathing, and caleimining, and drying, and all the other items named in the specifications, were merely incidental to, and parts of, the work of plastering./ Undoubtedly the general rule is that,' where there is no special contract, the law will imply an agreement to pay for the materials as delivered, and the work as done. But where one continuous piece of work, consisting of a number of parts or items, is to be performed, the statute of .limitations does not begin to run upon the completion of each ■ separate part or item, but upon the completion of the whole. ■ If the several items are merely parts of one transaction, the i statute begins to run from the date of the last item, and all the others are saved from the bar. “Bach item is not to be regarded as a separate cause of action, but the whole rather i as a continuous dealing.” (Frankoviz v. Smith, 34 Minn. 403, and cases there cited). In Hall v. Wood, 9 Gray, 60, the action was on the common counts with a bill of particulars, containing some items which bore date more than six years before the beginning of the suit; and it was held that recovery could ' be had for the full amount, notwithstanding the statute of limitations, as the whole work was done under an entire contract.

In Walker v. Goodrich, 16 Ill. 341, we held that the statute of limitations could not commence to run against an attorney until the legal services contracted for had been performed by a termination of the suit, or a release from the contract, and it was there said: “Did the statute of limitations commence .running at the termination of each day as to the services ren dered on that day ? Were the solicitors obliged to pause in their defense, within each period of five years, to commence , a suit against their clients for the services already performed, or forfeit them ? The very statement of the proposition shows how embarrassing, inappropriate and indeed impracticable such a rule would be ?”

We do not think, that the case of Schillo v. McEwen, 90 Ill. 77, can be construed as holding a contrary view to that here expressed. In that case, the evidence showed, that the last-item was of goods delivered before the period of five years-began to run, and none were delivered within five years before-the commencement of the suit. The doctrine was there recognized, that, in case of a running account, if some of the items are of goods delivered within the statutory period, other items' of goods delivered before the commencement of such period will be withdrawn from the operation of the statute of limitations.

In the case at bar, it is conceded that a part of the labor of plastering the building was done on April 21, within the period of five years before the commencement of the suit. The labor so performed was a part of the performance of one continuous piece of work, and was a part of the execution of an entire contract. As the plastering done on that day was within the period limited by the statute, the balance of the plastering theretofore done, and of which the labors of that day were a mere continuation, was withdrawn from the operation of the statute. But the instructions were calculated to-make the impression upon the minds of the jury, that plaintiff’s right of recovery was barred except for the work done on April 20 or 21, 1883. The plastering which appellant’s men did on those days, was so inconsiderable, that the jury may have regarded the right to recover its price or value as can-celled by the smallest and most insignificant items of set-off which defendant’s evidence tended to sustain, while the right to a larger recovery may have led to a more careful eonsideration of such items of set-off. We are unable to say that the plaintiff was not injured by the error committed in the giving of these instructions.

The judgments of the Appellate and Circuit Courts are reversed and the cause is remanded to the Circuit Court.

Judgment reversed.