This action was brought by appellee to recover a balance alleged to be due to him for certain contract work and certain extra work done by him in and about the erection of a building for appellant. Appellee did not obtain a final certificate from the architect under whose supervision the work was, by the terms of the contract to be performed, and by whom it was_ to be accepted when completed, but appellee claimed and alleged that said certificate was unjustly and fraudulently refused by the architect. There is considerable conflict in the evidence as to certain changes alleged to have been made in the work contracted for, and as to extra work done and the value thereof, and as to the manner in which portions of it whs done and accepted by the architect or appellant, from time to time, as said portions of the work were completed. Numerous exceptions were taken by appellants upon the trial to the admission and rejection of evidence by the court, and to the giving, refusing or modifying of instructions. We are of opinion, after a careful examination of the record that, save as to the giving of two instructions hereafter to be noticed, there is no material error in the record and that appellant’s points against the ruling of the court, except as to said two instructions, are not well taken.
The court gave to the jury two instructions at the request oi appellee, both of which are palpably erroneous, and one al least of which could not be other than prejudicial to the appellant. Sec, 9 of the written contract under which the work waa done and which was declared on, in the action, provides: c‘ Thai all payments made on the work during its progress on acconnl of this contract or for any extra work shall in no case be construed as an acceptance of the work executed; but the contractor shall be liable to all the conditions of the contract until the work is finished and a final certificate given by the superintendent.”
Instruction hTo. 11, given by the court for the plaintiff, was as follows: “ The court further instructs the jury that the certificates given by the architect to the plaintiff for payment by defendant, is conclusive evidence as against the defendant and in favor'of the plaintiff, that so much of the material furnished and work done under the contract as originally made, covered and paid for by said certificates, were so furnished and done pursuant to the terms of the contract.” This instruction directly contravenes the terms of the contract, which, as between the parties, is the law on the point on which the instruction was given. It needs no argument to demonstrate that the instruction as given was prejudicial error.
The twelfth instruction was: “ The court instructs the jury that if they believe that any witness testifying in this cause has wilfully sworn falsely as to a material matter in the case, they will disregard the testimony of such witness or witnesses, except in so far as corroborated by other credible testimony offered in the case.’1 2**5
The court erred in directing the jury to disregard the testimony of such witness. The rule is that the jury are at liberty to do so if they see fit and the correct instruction is that the jury may do so.
For the errors indicated the judgment must be reversed and the case remanded.
Heversed cmd remanded.