delivered the opinion of the Court.
Appellant employed appellee, an architect, to prepare plans, drawings and specifications for a business block which appellant was about to erect in the city of Joliet, and to superintend its construction. Appellee was to receive three per cent of the cost of the building except the cost of painting and plumbing. The building was erected, and the sum upon which commission was to be paid was $11,019.45, upon which sum the commission amounted to $330.57. Appellant paid $150 to apply on the commission, and appellee filed the bill in this case for a mechanic’s lien to enforce his claim for the balance of $180.50. Appellant answered and defended upon the ground that appellee failed to exercise the degree of skill and diligence contracted for in superintending the erection of the building, in consequence of which appellant had suffered damage exceeding the amount of commission claimed. Upon a hearing the court found in favor of appellee and that there was due him $180.50, and declared the claim to be a lien upon the premises, and directed a sale unless the same ivas paid within forty days from the date of the decree.
The particulars in which it was claimed that appellee had failed in his duty and entailed consequent damage upon appellant, were in not properly deadening the floors of the second story and in failing to have the roof of the porch sufficiently secured.
The first story of the block was divided into two store rooms, and the occupants could hear noises of walking and conversations, the operation of dental machinery, the groans of patients having teeth pulled, the falling of teeth and instruments on the floor and other noises connected with the occupation of the second story. These noises were not agreeable, and lessened the value of the building for renting purposes. It is claimed that appellee was responsible for the resulting damages. The evidence was that when the subject of deadening the floors was under discussion, appellee stated to appellant that they had a new thing for that purpose and that it was mineral wool. Appellee recommended it and it was adopted. He went to Chicago and took the plan with him, and the manufacturers figured out how much would be required. He made the specification accordingly for the mineral wool to be put in an inch and a half thick. Mineral avooI is made from the slag of blast furnaces by jets of superheated steam or compressed air blowing the melted slag into fibers. This material was put between the floor above and a false floor under it, made by nailing strips on the joists on which boards Avere placed. About the ordinary amount was used, and in the way shown to be proper by the testimony of a manufacturer of the material. The evidence showed that the mineral avooI was largely used and with reasonable success to deaden floors, but in this instance, for some reason the floors were not well deadened. The ceiling below was of corrugated iron, and there was a shaft between the joists for running dental machinery with treadles on top of the floor attached to the shafts Avhich turned partly around. There was also some evidence that some oE the wool was disturbed and not replaced properly. Whatever the cause may have been, appellee was not in fault in recommending the material, which Avas being largely and successfully used, and the evidence does not shoAV that an insufficient quantity was used, as claimed by appellant.
There was a porch at the back of the building running up to the roof and connected with each floor. The roof of the porch was blown off in a windstorm. There were posts supporting the roof, and the ends of the posts were mortised into the roof timbers, but Avere not fastened with spikes or pegs. The roof was only held in place by its own Aveight. There was no complaint that the plans and specifications were improper or did not provide for suitable fastenings, but the claim was that appellee should have seen that the contractor put in spikes or pegs. The exercise of ordinary care did not require appellee to stand by each workman at all times to see that each spike or peg was driven, and we are not prepared to say that his failure to detect the omission of the contractor in this instance amounted to negligence and a consequent failure of duty to appellant. The decree will be affirmed.