Griefen v. Hubbard

Mr. Presiding Justice Freeman

delivered the opinion of the court.

It is contended by appellant’s attorney that the contract is binding on appellee, Joseph B. Hubbard, having been executed and delivered by him, even though not binding on Janet W. Hubbard, his wife; and that, therefore, appellant was entitled to a judgment for at least nominal damages. The argument is that although the legal title to a part of the property to be conveyed as provided by the agreement, was in Janet W. Hubbard and it would have been necessary nr order to convey her dower and homestead rights for her to join in any deed made by appellee, it was yet within the range of possibilities for appellee, when he signed the contract, to acquire the title or obtain the necessary deeds from his said wife; and that his subsequent inability to do so, cannot relieve him from liability for damages caused by his failure to perform for himself and his wife. If appellee by said agreement had obligated himself personally as vendor of the property independently of his wife, he might have been bound by the obligations he assumed. But the contract in this case was one containing mutual covenants which were on each side the consideration of those of the other. To be valid, it required to be executed by all, as it was intended to be. It could not be performed by appellee only and it was not by its terms intended to be. Appellee did not make the agreement for himself alone, and was to receive no part of the consideration. Hot only did __ Janet W. Hubbard hold the legal title to at least part of the realty to be conveyed, but she would have been required by the agreement to execute her note for $7,500 payable within three years and to secure it upon the real estate to be conveyed to her. She was, moreover, the principal of the parties of the first part, to whom the entire consideration was to pass from appellant, as the second party to the agreement. It is certain that appellee could not under the terms of the proposed contract have required appellant, contrary to his agreement, to perform on his part, lacking an obligation to perform by Janet W. Hubbard. By reason of her failure or refusal to execute the contract, all the other parties alike, appellee as well as appellant, were relieved from the obligation which they had signed in the expectation that it was to be binding on all the parties named therein. “ Covenants founded on mutuality of obligation and liability must be mutually binding upon the parties, to them. If, therefore, one of several parties to a deed inter partes founded on mutual covenants neglects to execute the deed, the contract is not binding on the others who have executed it.” Addison on Contracts, vol. 1, p. 192-3. Such is the contract in the case before us. See also Short v. Keiffer, 43 Ill. App. 515, 523; Tewksbury v. O’Connell, 21 Cal. 60-70 (8th Ed.) 192; 3rd Reed on Statute of Frauds, end of section 1064; Fish v. Johnson, 16 La. Annual 29; Mattoon v. Barnes, 112 Mass. 463-466.

The contract not having become binding on any of the p irties named therein, appellant w.as not entitled to recover. The judgment of the Superior Court is therefore affirmed.

Affirmed.