Fine Airlines, Inc. v. Federal Aviation Administration

                       United States Court of Appeals,

                                  Eleventh Circuit.

                                    No. 94-5314.

                      FINE AIRLINES, INC., Petitioner,

                                          v.

             FEDERAL AVIATION ADMINISTRATION, Respondent.

                                    May 10, 1995.

Review of a Final Order of the FAA Denying Waiver from Interim
Compliance with Noise Level Standards of the Airport Noise and
Capacity Act of 1990 (Florida Case).

Before ANDERSON and BIRCH, Circuit Judges, and JOHNSON, Senior
Circuit Judge.

     PER CURIAM:

     The issue on this appeal is whether the Federal Aviation

Administration        ("FAA")     acted   arbitrarily      and    capriciously    in

denying the application of Fine Airlines, Inc. for a waiver of the

December 31, 1994, interim compliance date established by 14 C.F.R.

§ 91.867 pursuant to the Airport Noise and Capacity Act of 1990

("ANCA"), 49 U.S.C. §§ 47521, et seq.               Aircraft are categorized by

the noise level ranging from a stage 1, the noisiest, to stage 3,

the quietest.         The ANCA provided for the phasing out of stage 2

aircraft in favor of stage 3 aircraft by the year 2000, and

delegated    to       the   FAA     authority       to   promulgate      regulations

establishing a schedule of phased-in compliance, including interim

compliance    dates.        Air    carriers     could    comply   with    the   noise

requirements by purchasing stage 3 aircraft or, through hushkit,

adapting their stage 1 or 2 aircraft to stage 3 noise levels.

Pursuant    to    §   91.867(a)(2),       a   new   entrant   United     States   air
carrier, like Fine Airlines, must by the initial compliance date of

December 31, 1994, have at least 25% of its fleet in compliance

with stage 3 noise levels.       However, 14 C.F.R. § 91.871 permits a

waiver   of   the   interim   compliance   requirements   under   certain

specified circumstances.

     In 1992, Fine Airlines began its cargo service operations

between the United States and numerous Central American, South

American and Caribbean countries.      By the end of 1992, it had four

stage 2 aircraft.      It added five stage 2 aircraft in 1993.        By

September 1, 1994, it had added another stage 2 aircraft, and in

the instant petition for a waiver filed September 1, 1994, it

indicated an intention to acquire two more stage 2 aircraft before

the end of 1994.     In May, 1992, Fine Airlines began working with a

manufacturer to develop a hushkit which could convert its stage 2

aircraft in order to meet the stage 3 noise levels.

     On September 1, 1994, Fine Airlines petitioned the FAA for a

waiver of the December 31, 1994, interim compliance date, pursuant

to 14 C.F.R. § 91.871.        The FAA denied the waiver on December 8,

1994.    On December 16, 1994, Fine Airlines filed a petition for

reconsideration, which was denied by the FAA on December 20, 1994.

        The regulation governing the instant application for waiver

provides in relevant part as follows:

     Section 91.871 Waivers from interim compliance requirements.

     (a) Any U.S. operator ... subject to the requirements of ...
     [section] 91.867 of this subpart may request a waiver from any
     individual compliance requirement.

     (b) Applications must be filed with the Secretary of
     Transportation at least 120 days prior to the compliance date
     from which the waiver is requested.
     (c) Applicants must show that a grant of waiver would be in
     the public interest, and must include in its application its
     plans and activities for modifying its fleet, including
     evidence of good faith efforts to comply with the requirements
     of ... § 91.867....

     (d) Waivers will be granted only upon a showing by the
     applicant that compliance with the requirements of ...
     [section] 91.867 at a particular interim compliance date is
     financially onerous, physically impossible, or technologically
     infeasible, or that it would have an adverse effect on
     competition or on service to small communities.

14 C.F.R. § 91.871.    The regulation clearly requires a showing of

good faith efforts to comply with the interim compliance dates of

§ 91.867, including the December 31, 1994, interim compliance

date.1   The issue in this case is whether the FAA acted arbitrarily

and capriciously in finding that Fine Airlines did not satisfy the

good faith criterion.

     The crux of the FAA decision denying the waiver was that Fine

Airlines had failed to demonstrate that it had "established a

timely, achievable plan for compliance and made reasonable efforts

to keep that plan current and follow it."   Thus, the FAA concluded

that the actions of Fine Airlines did not constitute a good faith

effort to comply with the interim compliance requirements.     Fine

Airlines, Inc., FAA Docket No. 27898 (Dec. 8, 1994), at 5.      The

agency opinion pointed out that Fine Airlines began operations in

1992, and that its 1992 report to the FAA indicated that it would

be in compliance.     Fine Airlines' 1993 report indicated that it

would not meet the first compliance deadline, December 31, 1994,

that the expected date of certification for its hushkit project was

     1
      We find no merit in Fine Airlines' argument that its
demonstration of technological infeasibility as of the December
31, 1994, compliance date was sufficient in and of itself without
any showing of good faith.
in early 1995, and that it intended to apply for a waiver of the

December 31, 1994 deadline.         The agency opinion also noted:

      It is important to note that this does not appear to be a case
      in which an operator had a plan to hushkit its aircraft before
      the compliance date and at some late hour, was unable to
      follow through with that plan and needs extra time. None of
      the materials submitted by Fine Air indicates, nor does the
      petitioner argue, that it thought the hushkit would be ready
      in time to meet the first compliance date.

Id.   at    7.       Fine   Airlines     filed    a   petition   for    emergency

reconsideration on December 16, 1994.                 Among other things, that

petition purported to explain the delays causing its failure to

meet the December 31, 1994, compliance date, proffering additional

evidence for that purpose.               The FAA denied reconsideration on

December 20, 1994.

          We cannot conclude that the FAA decision in this case was

arbitrary or capricious.        After oral argument and a careful review

of the briefs and record in this case, we are satisfied that Fine

Airlines has failed to demonstrate that its plan to comply through

the vehicle of its hushkit project was a timely and achievable plan

for compliance.        As the agency opinion so clearly articulates:

"None of the material submitted by Fine Air indicates, nor does the

petitioner argue, that it thought the hushkit would be ready in

time to meet the first compliance date."                Id. at 7.      The agency

also pointed out that Fine Airlines' 1992 report indicated a plan

to comply, but provided no facts to support its expectation of

compliance.           The    1993      report     acknowledged     a      lack   of

compliance—i.e., that the expected date of certification for its

hushkit was not until early 1995—and indicated an intent to apply

for   a    waiver.      Although    it    began   working   with    the    hushkit
manufacturer in May, 1992, a contract with the manufacturer was not

entered until May, 1993.       Significantly, the contract contained no

date for delivery.       In an attempt to pinpoint the source of its

evidence of good faith, Fine Airlines at oral argument pointed to

the May 1994 report of its manufacturer.             However, nothing in that

report demonstrates that the hushkit project was a timely and

achievable plan for compliance.            Indeed, the report contemplated

delivery dates only in 1995.          The report contained little or no

explanation relating to the reasonableness of the hushkit plan or

the reasons for delay.

          Fine   Airlines'   petition      for   agency   reconsideration    was

apparently an attempt to rectify the obvious deficiency in its

prior submissions, i.e. its failure to demonstrate that its hushkit

project was a reasonable plan for compliance within the interim

compliance dates.        For this purpose, Fine Airlines submitted

additional information2 with its petition for reconsideration, in

the   form   a   December    16,   1994,    update   from    the   manufacturer,

updating its previously-submitted May, 1994, report.                The December

16, 1994, update purported to explain production delays. We are in

full agreement with FAA that the additional information falls far

short of satisfying the deficiency in Fine Airlines' showing.               The

four delays described in that document are woefully vague, and

provide very little assistance to the factfinder with respect to

its   determination      whether      Fine       Airlines'    hushkit   project


      2
      Fine Airlines' argument that the FAA had a duty to ask for
additional information is frivolous. The burden was on Fine
Airlines to present evidence in support of its waiver
application.
constituted a reasonable plan of compliance. For example, there is

no indication at all of chronology, i.e., the timing of the delay

or the effect of the delay on compliance with the compliance

deadline dates.       Moreover, the update document undermines Fine

Airlines' position in that it indicates that delays have been

experienced only with respect to one major component and that the

delays being encountered are relatively minor and minimal in

comparison with those that have been encountered in previous

hushkit programs.     Rather than supporting Fine Airlines' position,
the update document suggests that there have been fewer delays than

usual,   and   thus   that   the   hushkit   project   was   never   a   plan

reasonably calculated to permit compliance.

     We readily conclude that Fine Airlines failed to demonstrate

that its hushkit project constituted a "good faith effort[ ] to

comply with the requirements of ... § 91.867."                14 C.F.R. §

91.871(c).3    Accordingly, the order of the FAA denying the instant

     3
      We decline to address Fine Airlines' argument that the FAA
acted arbitrarily and capriciously in departing from the
standards previously applied in evaluating good faith compliance
efforts. The prior standards to which Fine Airlines points
relate to the phase-out of stage 1 airplanes in 1985. In
particular Fine Airlines points to the guidance provided in In
Re: Lineas Aereas del Caribe, S.A., 50 Fed.Reg. 19,102 (May 6,
1985). We decline to address this argument for two reasons.
First, Fine Airlines' argument is, with one exception mentioned
below, a mere repetition of the bald statement that a different
standard was applied. We decline to address such a vague
argument.

          Second, the only specific assertion by Fine Airlines is
     that the FAA failed to recognize that the Caribe guideline,
     id., suggested that a good faith effort would include a firm
     contract with the earliest possible delivery date. Assuming
     arguendo, but expressly not deciding, that good faith would
     be satisfied by a firm contract with the earliest possible
     delivery date, it is clear in this case that Fine Airlines
     has not satisfied that standard. Its contract contains no
waiver is

    AFFIRMED.




    delivery date at all. Moreover, Fine Airlines has made no
    showing at all that the instant circumstances relevant to
    good faith compliance are sufficiently similar to the
    circumstances addressed in Caribe, id., to require
    application of the same criteria. We note that the Caribe
    guidelines set forth on May 6, 1985, followed a period of
    inconsistent application of the standards by the FAA. See
    Airmark Corp. v. FAA, 758 F.2d 685 (D.C.Cir.1985). We note
    that the Caribe guidelines required that the firm contract
    referred to therein be entered as of a particular date,
    which would obviously have no relevance to the instant
    circumstances. We note further that the instant
    circumstances derive from subsequent legislation, i.e., the
    1990 Airport Noise and Capacity Act, that the regulations
    pursuant to that Act were published in final form on
    September 25, 1991, and thus that Fine Airlines has been on
    notice of these regulations since at least September 25,
    1991. As noted in the text of this opinion, Fine Airlines
    has failed to adduce evidence to demonstrate its entitlement
    to a waiver under the clear language of those 1991
    regulations. In light of the foregoing, we cannot conclude
    that the instant circumstances are obviously similar to
    those extant in 1985, and in the absence of a showing on the
    part of Fine Airlines that the instant circumstances are in
    fact similar to those addressed in the 1985 Caribe
    guidelines, we decline to address the issue.