Wabash Railroad v. Jackson

Myers, J.

Appellees filed a petition in the Wabash Circuit Court, under the act of 1907 (Acts .1907 p. 508, §6140 et seq. Burns 1908), asking that certain lands in that county be drained by a public drain. Over the remonstrance of appellant, said drain was established so that it crossed appellant’s right of way. By their report the commissioners of drainage found for the construction of the drain, and the costs and expenses were fixed at $788.52. Benefits and damages were assessed, in which appellant was reported as benefited $60, and the assessment against it fixed at $50, but in their report, the commissioners recommended that appellant, at its own cost and expense construct a bridge twelve feet high and twenty-four feet wide. Various lands, lots and a public highway would be affected by the construction of the proposed drain, and all were reported as benefited in amounts in excess of the assessments for construction.

Upon remonstrance by appellant, a special finding of facts was made and conclusions of law stated. The findings are quite lengthy, but they show that the railway was constructed in 1854 with a fill; that where the proposed drain crosses the right of way the fill was twenty-two feet high, fourteen feet wide on top, and eighty feet wide at its base, at which point, in 1881, appellant constructed a stone culvert four feet and one inch wide at the bottom, and the same width to the height of three feet, and for the next two feet, eleven and a half inches wider, the total height being five feet, one inch. This culvert is called No. 440. At a point about eight hundred feet southwest is culvert No. 441, constructed when the railroad was built. A natural stream approaches the railroad from the northwest, called Jackson *489creek. When the railway was constructed that stream crossed in a state of nature about three hundred feet southwest of culvert No. 441, and the stream was diverted through that culvert, which was of stone, eight feet wide at the bottom and four feet high. This culvert was replaced in 1902 by a cast-iron pipe five feet in diameter. The natural stream lias its source in hills some two and a half miles northwest of the railway crossing. Soon after the construction of culvert No. 440, which was at a point where there was no waterway prior thereto, one Jackson, father of some of the appellees, constructed a ditch southeast of Jackson creek to and through culvert No. 440. It is found that culvert No. 440, on the line of the proposed drain, will not in times of high water be sufficient to conduct the water which will flow in the proposed drain, which is partly in the channel of the old creek, but diverges from it at its greatest distance four hundred feet, and will be of the average width of four feet in the bottom, twelve feet at the top, and of the average depth of four feet, and runs over a portion of the ditch constructed by James Jackson, connecting with culvert No. 440. After the construction of said ditch, Jackson ploughed and filled up Jackson creek proper from a point 238 feet north of culvert No. 441, and caused the water of Jackson Creek to flow through culvert No. 440.

It is found that since the construction of the railway grade the culverts have not been sufficient to carry off the waters of Jackson, creek, and in times of heavy rains the water backs up at the railway embankment, and runs southeasterly over a public highway, and into the houses of residents of the town of Rich Valley, and covers the highway and remains in the houses five or six hours at a time.

All necessary facts authorizing the establishment of the drain are found, but the court found that a culvert seventeen feet long and eight feet high will be sufficient to carry off the water.

As conclusions of law the court established the ditch and *490required the construction of the culvert by appellant at its own expense, which it is found will be $8,000, as against $10,000, the cost of a culvert recommended by the commissioners of drainage.

1. It is urged by appellant that the cost of the culvert, added to the cost of construction, would largely exceed the benefits assessed, and that the proceeding should have been dismissed. The case, therefore, turns upon the question whether the cost of the culvert is to be included in the cost of constructing the drain, or whether the cost of the culvert should be wholly borne by appellant. That question has been determined adversely to appellant. Chicago, etc., R. Co. v. Luddington (1910), 175 Ind. 35.

2. It is urged, however, that this case is to be distinguished from the one just cited, because in that case “it may be inferred from the proceedings that a large amount of land was assessed benefits, largely in excess of the damages sustained by the company, it appearing that the damages sustained by the company in that case were only about $3,200.” In this case the total benefits assessed are $927.97, and the cost, exclusive of the bridge, $788.52. If, as was held in the case cited, railroad companies as a matter of law, are required to construct at their own expense such culverts as are required, so as not to interfere with the free use of public drains, whether constructed prior to or after the construction of the railway, and in such manner as not unnecessarily to impair its usefulness, the cost of such culvert is not the subject of damages, within the contemplation of the statute, which is specifically referred to in that case, and to which we adhere. It cannot reasonably be contended that the construction of a drain, and whether or not it is of public utility and beneficial to highways, can be made to depend alone upon the number of acres of land immediately drained, or the amount of travel over or the length of highways benefited, or the cost of restoring or opening a waterway for the passage of water.

*491It is shown by the findings that the stream rises in the hills two and a half miles away, and empties the water in a large volume upon these lower lands, and that it is impeded by the railway embankment, and the insufficiency of the waterways through it, and seriously affects the residents of a village, the lands north of and adjoining the railway, and the highway.

3. It is also contended that certain assessments are so defective as to description of the property assessed that they cannot be enforced. Some descriptions are not very accurate, but they can be made certain, and that is sufficient. Upon an application to foreclose the lien, the correct description could be supplied.

4. It is to be noted that under §6144, supra, a sale of land for ditch assessments can be made by county treasurers only in the manner that other taxes are collected, and it has been held, under a similar statute, that collection can be made only in that method. Storms v. Stevens (1885), 104 Ind. 46; Lockwood v. Ferguson (1886), 105 Ind. 380.

But it is also held, under the same statute, that under a proceeding to foreclose, after sale, the lien may be enforced against the land intended to be assessed, by its true description. Ager v. State, ex rel. (1904), 162 Ind. 538; Luzadder v. State, ex rel. (1892), 131 Ind. 598; Cullen v. Strauz (1890), 124 Ind. 340; Brosemer v. Kelsey (1886), 106 Ind. 504; Baker v. Clem (1885), 102 Ind. 109.

1. The apparent hardship of a case where appellant is put to an expense of $8,000 to produce a benefit of $927.97 cannot be invoked as against a public enterprise. If this were so, it will readily be seen that many much-needed improvements for the public benefit, and in the interest of public health, would be prohibited, unless assessments should be made which would amount to confiscation of the property of those who, except for the creation of conditions such as are here presented, would not need the *492improvement. Appellant received and exercises its franchise subject to both the common law and the statutory-power to require it to perform the duty imposed upon it by this proceeding.

No error is made to appear, and the judgment is affirmed.