Moore & Richter Lumber Co. v. Scheid

Hottel, J.

Appellant instituted this action to foreclose a mechanic’s lien on certain real estate in LaPorte county owned by appellee Adolph Scheid. *696The trial court made a special finding of the facts in issue, and stated its conclusions of law thereon to the effect that appellant is entitled to recover from Scheid the sum of $406.13 for materials furnished, but is not entitled to a foreclosure of its alleged lien. So far as material to the present inquiry the findings of fact show that on November 26,1913, appellant and appellee Scheid entered into a verbal contract, wherein appellant agreed to furnish lumber and building material for the completion of a dwelling 'house on real estate owned by Scheid; that thereafter, on various dates beginning with January 20, 1914, and ending with November 16, 1914, appellant did furnish , to said Scheid lumber and other material for use in the construction of said dwelling house, and all of such lumber and material was in fact used by Scheid in the construction of said building, except the material furnished on August 11, October 6, and November 16,1914, which are the last three dates on which any material was furnished; that the material furnished on these dates was used by Scheid in the construction of other buildings and oh real estate other than that described in appellant’s complaint, all without appellant’s knowledge or consent; that appellant, in furnishing and delivering material under dates of August 11, October 6, and November 16,c 1914, understood and believed that the same was to be used by Scheid in the construction of his dwelling house, in accordance with the contract of the parties, and delivered the same with that understanding; that on December 3, 1914, appellant .filed a proper notice of an intention to hold a mechanic’s lien on the real estate in question, and instituted this action within one year thereafter ; that on July 2, 1914, Adolph Scheid and Eose *697Seheid, his wife, executed to the State of Indiana and delivered to the auditor of LaPorte county a mortgage on said real estate for the use of the common school fund in the sum of $1,200, which is unpaid; that said mortgage was duly recorded in the School Fund Mortgage Record on July 3, 1914, and the $1,200 received from the school fund was applied on the payment of labor and materials used in the construction of Seheid’s said dwelling house.

1. In bringing this action, appellant has 'named as parties defendant, in addition to the owners of the real estate, the auditor and board of commissioners of LaPorte county, the county itself, and the trustees of the common school fund. The decision of the trial court does not directly inolve the issue of priority as between appellant’s alleged lien and the school fund mortgage, but in view of the-conclusion which we have reached, that issue will doubtless arise on a retrial of the case, we deem it proper, at this time, to call attention to the fact that the state is the real party in interest under a school fund mortgage. Snodgrass v. Morris (1890), 123 Ind. 425, 426, 24 N. E. 151; Crooks v. Kennett (1887), 111 Ind. 347, 350, 12 N. E. 715. In this connection, see Hogston v. Bell (1916), 185 Ind. 536, 548, 112 N. E. 883.

2. 3. *6984. *697In the present appeal no briefs have been filed on behalf of appellees, and we are justified, therefore, in relying on appellant’s statement that the decisión of the /trial court, in so far as it denies the right to a lien, rests on the fact that the material furnished to Seheid within the sixty days prior to December 3, 1914, did not actually go into the construction of the building for *698which it was furnished. The mechanic’s lien statute rests on the principle that one who furnishes labor or material for the improvement of property is entitled to look to that property for his compensation, and “a materialman claiming a lien must ordinarily show that his materials were furnished for and were actually used in the erection, alteration or repair of the building against which the lien is asserted. ’ ’ (Our italics.) Potter Mfg. Co. v. A. B. Meyer & Co. (1909), 171 Ind. 513, 519, 86 N. E. 837, 131 Am. St. 267, and cases cited. However, it is not always necessary to show that-the material furnished'actually went into the building, since the circumstances in a particular instance, especially where, as in the present case, the material was furnished to the owner of the building to be used herein, may be such as to estop such owner in a foreclosure suit from invoking the general rule. Totten & Hogg Iron, etc., Co. v. Muncie Nail Co. (1897), 148 Ind. 372, 47 N. E. 703; Smith v. Newbaur (1896), 144 Ind. 95, 105; 42 N. E. 40,1094, 33 L. R. A. 685; Scott v. Goldinghorst (1890), 123 Ind. 268, 270, 24 N. E. 333; Hill v. Braden (1876), 54 Ind. 72, 76; City of Crawfordsville v. Barr (1873), 45 Ind. 258, 261; Welch v. Sherer (1879), 93 Ill. 64, 67.

5. *6996. *698In this case the trial court has found specially that appellant furnished the material in question directly to the owner of the real estate, on his promise to use the same in the construction of his dwelling house, and on the security of that building and the real estate on which it was being erected. It further finds that Scheid diverted this material to other use without the knowledge or consent of appellant. These circumstances are sufficient to estop him from relying on the rule which has evidently *699guided the trial court in its decision and that decision must be reversed. Appellant asks that the circuit court be directed to restate its conclusions of law on the facts found and to render judgment accordingly, but, as the record discloses that the rights of other parties might thus be improperly affected, we believe that the ends of justice will be better served through the granting of a new trial. §702 Burns 1914, §660 R. S. 1881; Kitchell v. Schneider (1913), 180.Ind. 589, 594, 103 N. E. 647; McCoy v. Kohomo R., etc., Co. (1902), 158 Ind. 662, 667, 64 N. E. 92.

Judgment reversed, with instructions to grant a new trial, and for further proceedings not inconsistent herewith.

Note. — Reported in 121 N. E. 91. Mechanics’ liens: material furnished for structure, but not actually used therein, as basis of lien, showing necessary, 31 L. R. A. (N. S.) 746, L. R. A. 1918D 1041, 27 Cyc 46.