As wo have reached "the conclusion that we must sustain appellee’s motion to dismiss this appeal on-
In March, 1909, the city entered into a contract with the defendants Lehmann & Bradley, who will hereafter be spoken of as the contractors, for the improvement by paving and curbing of a short street. Among the specifications of the contract -were the provisions that the curbing should be of sandstone, and the paving of brick having an absorption test of not more than 2 per cent and a rattler test of not to exceed 16 per cent. This contract was let to these contractors in accordance with competitive bidding in which said contractors were the lowest bidders; plaintiff being an unsuccessful bidder. The cost was to be paid by assessment upon abutting property, save the expense of paving one street intersection and the alley intersections, which was to be paid out of the improvement fund. Before the work was commenced, some agreement was made between the officers of the city and the contractors by which the width of the street was to be reduced and a cement curb and gutter substituted for the sandstone curbing, and this agreement was on the petition of the abutting property owners. When the work had been partially performed under the modified agreement, objection was made by the city engineer that the brick used was not in accordance with the specifications, in that the absorption test showed a 5 per cent., instead of a 2 per cent., absorption. Thereupon the property owners petitioned the city council that the work be allowed to continue to completion with the same kind of material as that which had already been used, and it was thus completed without objection on the part of the property owners. Such owners afterward and before the commence
1. Appeal: injunction: settlement of controversy: dismissal of appeal. The contentions of plaintiff as a taxpayer were that the. modifications in the contract made by the city council were without authority, that the contract as performed was ™ accordance with the proposals for bids, an<^ that the °ity could not in accepting .the work completed in accordance with the modified contract become obligated to make payment for the expense of street and alley intersections. On these contentions the decision of the court was against the plaintiff, the preliminary injunction was dissolved, a permanent injunction was denied, and plaintiff’s petition was dismissed. Thereupon, as is made to appear in this court by affidavits in support of the motion to dismiss this appeal subsequently taken, it was made to appear that, before the taking of such appeal, the officers of the city and the contractors settled the case, and the city paid to the contractor all sums due under the contract. From further affidavits submitted by appellant we infer that such settlement and payment were effected by the delivery to a bank of city bonds as authorized by Code, section 910, and we are justified in assuming that the city council had in accordance with the provisions of Code, section 830, levied for the cost of street and alley intersections a special tax payable into the improvement fund of ten annual installments to be used when collected in the ex-tinguishment of the bonds so issued. It appears, therefore, that the city had, between the entering of the decree dismissing plaintiff’s petition and dissolving the temporary injunction and the appeal by plaintiff from such decree, fully performed all the obligations which it had assumed or attempted to assume under the contract for the street improvement.
It is suggested in appellant’s resistance to the motion to dismiss, supported by some attempted showing by affidavits, that a civil suit is now pending in which Lehmann & Bradley seek to recover damages from this plaintiff for the wrongful
A motion is submitted with the case to strike a portion of appellee’s argument on the merits, but, as it relates to the subject-matter which has been brought before us by the motion to dismiss, we see no reason for sustaining it. Such motion is therefore overruled.
The motion to dismiss the appeal is Sustained.
SUPPLEMENTAL OPINION.
2 same: right of appeal. Counsel do not contest the position taken by us on the former hearing so far as it pertains to the main controversy, but insist that, as the trial court vacated the temporary injunction and thereby rendered plaintiff liable prima facie upon the injunction bond, he ought to have the decree reviewed, so far as that question is concerned, to determine (if such be the case) that the order of vacation was improperly entered and thereby .relieve him from such liability. No precedent for this practice is pointed out in our cases, and we think none can be found. On the contrary, this court has inferentially, if not directly, held that, when jurisdiction of the main ease
3. Same: temporary injunction : dismissal : review. Moreover, a temporary injunction can exist only as an incident to some case pending in court, and when the case is dismissed or is otherwise disposed of the injunction falls with it; nothing is left to be heard or determined. This was distinctly held in Railroad Co. v. Dey, 76 Iowa, 278. There, the trial court having refused to dissolve a temporary injunction, the defendant appealed from the ruling. Pending the appeal plaintiff went into.the district court and dismissed its main action. Thereafter on a showing of these facts this court dismissed the appeal, declining to consider the error assigned upon the trial court’s refusal to vacate the injunction. Discussing the matter we there said:
But the case, as we have seen, is ended. The injunction proceedings must end with the ease. The injunction is a remedy sought in the action; it is an incident or a proceeding in the action. This incident — this proceeding — must fall when there ceases to be a case. . . . This court will notPage 657determine questions unless there be pending cases in which the questions arise. If remedies be sought and rights claimed in actions, the withdrawal, settlement, or abandonment of claims for such remedies or rights leaves nothing for us to determine in relation thereto. There must be real, present questions, involving actual interests or rights of the parties, to authorize us to consider the ease in which they arise. We will not settle questions involved in rights now no longer existing; and when, in a case pending in this court, rights cease to exist, the appeal will be dismissed.
The case of People v. Clark, 70 N. Y. 518, is quite in point upon the question. There a citizen brought an action to restrain proceedings for the incorporation of a village. A temporary injunction was granted and afterwards dissolved and the corporation was completed. The Court of Appeals refused to review the ruling upon the injunction, saying: “We do not deem it necessary to determine whether the action was maintainable as originally commenced. As it appeared upon the trial and is presented to us upon appeal, no effectual judgment can be rendered in it.” The principle is also affirmed in Dinsmore v. Express Co., 183 U. S. 115. (22 Sup. Ct. 45, 46 L. Ed. 1111).
4. Same, laches. It is further' to be said that, if plaintiff has been deprived of an opportunity for a review of the error which he assigns, the loss is chargeable to his own laches. When judgment was entered below he knew that unless case wag removed to this court by prompt appeal and further proceedings suspended or stayed by supersedeas, or if supersedeas was unavailing, then by a stay procured from this court the city and the contractors were at liberty to treat the controversy as having been adjudicated and proceed to a settlement on that basis. The judgment was entered on December 30, 1909] and notice of appeal was not served until January 19, 1910, after the city and its 'contractors had fully settled the paving claims, and there was nothing left from which an appeal would lie..