The plaintiffs and appellants claim of tho defendant the sum of $411, with interest. They allege, in substance, that in January, 1860, they had contracted to deliver to James Martin, at the Atlantic dry dock, at Algiers, a certain quantity of white oak (ship timber), from
The defendant answered by a general denial, but admitted the undertaking ; denied, at the same time, the neglect imputed to him; that the loss was caused by an unforeseen storm. He claims in reconvention $500, for which he prays judgment.
The District court dismissed plaintiffs’ demand, and gave judgment for defendant in reconvention, for $34 and costs.
We find in the record a bill of exceptions, taken by plain tiffs ; but, as a decision upon it would not change the conclusion we have come to, we have not thought necessary to pass upon it.
The testimony shows that the weather was fine in the commencement of the night; that the steamboat had two anchors out (one at each end), and a line ashore, tied to an old log; there was nothing else to tie it to. The flatboat was properly fastened. In the night a storm came on; everything got loose — steamboat, flatboat and timber. The timbers that were not put on the flatboat were lost.
It is true that steamboats are common carriers, and, as such, are hold to the most strict vigilance and responsibility. They must deliver what they have received, unless they prove that the loss has been occasioned by accidental and uncontrollable events. C. G. Art. 2725.
The loss of the timber is proven, as alleged; it was then incumbent on the defendant to show the accidental and uncontrollable event which had caused the loss. He has done so by proving a storm which put everything adrift in the river. But it is contended that he had been neglectful in not securing properly his steamboat, the flatboat andtlie timber. We have carefully examined the testimony, and we think, with the district judge, that the defendant is not responsible. We are of opinion that the judgment appealed from is erroneous in allowing the defendant thirty-four dollars in reconvention against the plaintiff. We believe that defendant has failed to make out his demand in reconvention.
It is therefore ordered and decreed, that the judgment of the District court be annulled and avoided ; it is further ordered and decreed, that there be judgment against plaintiff, and that there be also a judgment against the defendant on his rcconventional demand. It is further ordered and decreed, that plaintiff pay costs incurred in the District court, and that the defendant pay those of appeal.