United States v. Colegrove

Mr. Justice Shepard

delivered the opinion of the Court:

The question raised by the demurrer turns upon the construction to be given the act of Congress of May 4, 1882 (22 Stat. U. S. 54).

That act was passed as a section' of the general appropriation bill to cure, as is claimed, certain defects in former laws applying to the relations between contractors and their subcontractors and carriers. The appropriation for inland transportation by “ star routes ” of $7,250,000, is followed by five general provisos or clauses under that designation. The. first three of these are unimportant in this connection, as they provide merely for the substitution of subcontractors for the contractors, under certain circumstances. The remaining provisos read as follows: “ And provided further, That if any pérson shall hereafter perform any service for any contractor or subcontractor in carrying the mail, he shall, upon filing in the Department his contract for such service and satisfactory evidence of its performance, there*258after have a lien on any money due' such contractor or subcontractor for such service to the amount of the same, and if such contractor or subcontractor shall fail- to pay the part)'- or parties who have performed service as aforesaid, the amount due for such service within two months after the expiration of the quarter in .which such service shall have been performed, the Postmaster-General may cause the amount due to be paid said party or parties and charged to the contractor: Provided, That such payment shall not in any case exceed the rate of pay per annum of the contractor or subcontractor.: And provided further, That where any person, corporation, or partnership shall have contracts for the performance of mail service upon more than one route, and any failure to perform the service according to contract on any one or more of such routes shall occur, no payment shall be made for service on any of the routes under contract with such person, corporation, or partnership until such failure has been removed and all penalties therefor fully satisfied.”

It appears from the defendants’ plea that Colegrove was a successful bidder, at the same letting, upon some other routes, and had entered into contracts therefor. But the Government is charged with, the breach of'the contract, as to the route in controversy, through withholding from the contractor money earned thereon, and paying the same out to subcontractors and carriers upon other routes that had been let to him. This was done by the order of the Postmaster-General, as admitted in the plea, “ in accordance with the construction uniformly given to the act of Congress of May 4, 1882, since the passage of said act, relating to claims against mail contractors, or subcontractors by carriers for carrying the mails.”

It does not seem necessary to pursue, to final determination, the question that has been ably argued on both sides, viz : Whether the terms of the fourth and fifth provisos give subcontractors and carriers a lien upon all money due the contractor upon all of his routes, or only upon that earned *259on the particular routes upon which their services shall have been performed. If it was necessary to decide that question we would be inclined to hold that the lien expressly provided for each carrier is confined to the sums due for carriage on his own route only. As it is not necessary in our view of the case we will not consume time with its discussion.

It seems also that, as between the claims of the carrier's themselves, this is the construction of the Postoffice Department, for it is said on its behalf: “In no case does the Postmaster-General withdraw money from one route to pay for service on another until all claims on file for service on the former have been met and paid.”

The substantial question of the case is this: Whether, taking the provisions quoted above, in connection with each other, the Postmaster-General was justified thereby in paying carriers, on another route, from the surplus accruing on this one?

The right to do so has been exercised under the uniform construction which, it is admitted, has been given the law since its passage. In case of doubt the construction of the Department, long adhered to, would have great weight; but independently thereof we think it the correct one. Conceding that the express lien of the carrier is limited to the money earned upon his own route and no other, does not exhaust the purposes of the first clause ; for, after giving the lien, it is provided that in case of failure to pay the same within two months after the expiration of the quarter in which the services shall have been performed, the Postmaster-General may cause the amount due to be paid said party or parties and charged to the contractor.” Although there follows a proviso, that such payment “ shall not in any case exceed the rate of pay per annum of the contractor or subcontractor,” there is no limitation confining the payment to the fund due the contractor on the particular route. If the amount to be paid the carrier could not be taken from money due the contractor on any other *260route, where was the necessity of the proviso that in no case should the payment exceed the rate of pay of the contractor, as well as the subcontractor, in case there should be one between the carrier and the contractor ?

That proviso would seem to have been added to the bill pending the final proviso, or in contemplation of it; because it is not only consistent with it, but also important to the protection of the Government under its operation, as we shall show later.

The object of the whole law was, primarily, to protect the Government, and, incidentally, the interests of carriers. The Government was given an advantage it had not enjoyed before, and of which experience had demonstrated the necessity, in the case of contractors for many separate routes. By keeping one general account with such a contractor, penalties could be assessed for. dereliction of one route contract, and for negligent performance of others, and all could be summarily collected, by retention, as long as any balance remained due the contractor on his. contract, as a whole, without resort to proceedings upon his several bonds. Thus, by the power given to re-let to a subcontractor on any one route, to retain for the actual carriage upon others, to deduct from money due on all contracts for penalties assessed, and by the limited power to pay therefrom also for actual services of carriage rendered, the protection of the Government was as ample as it could well be made. In this view the importance of the limitation, as intimated above, in the special proviso to the fourth clause, becomes manifest. It might occur that one general contractor would secure many good contracts and some bad ones. On particular routes he might be compelled to pay more than his contract price to secure performance. In such cases the lien of the carrier, as well as the right to retain for his payment, is limited to the sum due the contractor. Beyond that he must look to other remedies for his protection. To pay the excess out of other contracts might conflict with the special liens of the carriers thereon, as well as pro*261duce loss to the Government; hence the limitation, in the proviso.

No injury can be done thereby to the particular subcontractor or carrier. He undertakes the work with knowledge of the situation, and if he fails to secure himself by contract, beyond the lien given him by the law, it is his own fault.

In the case suggested, where the Government shall have paid the contractor on a route before notice of a carrier’s special lien, his equity is recognized and provided for, as far as practicable, in the power given to retain for his payment from the surplus funds due the contractor upon any or all of his contracts. Such being the object and effect of the several provisions of the law, they must be considered as read into the contract to secure the performance of which the bond was given. Hence the sureties are concluded thereby equally with the principal contractor.

’ It follows, therefore, that the contract has not been violated by the retention of the money due thereunder, as set forth in the plea, nor has the contingent liability, of the sureties been changed, or rendered more onerous.

The judgment must be reversed, with costs to the -appellants, and the cause remanded with direction to sustain the demurrer to the plea. It is so ordered.

A motion for a rehearing was made and overruled.