Automatic Refrigerating Co. v. New York Independent Meat Co.

SEABURY, J.

The complaint alleges, a cause of action for labor performed and materials furnished. Upon the trial it was proven that the plaintiff and defendant entered into a written contract, pursuant to which the plaintiff delivered to the defendant certain appliances and articles to be used in a refrigerating plant, which, under the terms of the contract, plaintiff agreed to install. The answer pleaded a general denial and two counterclaims. The first counterclaim was for damages which the defendant claims to have sustained by reason of the alleged spoiling of defendant’s meats for want of the refrigeration *479which the plaintiff contracted to supply. The second counterclaim^ is for money alleged to have been paid out by the defendant at the plaintiff’s request.

In the contract referred to plaintiff agreed “to furnish refrigeration on or about the 10th day of June, 1911,” and further agreed that, “in event we fail, we shall provide temporary means of refrigeration.” It is very plain that the plaintiff did not furnish refrigeration, or any temporary substitute therefor, or perform the terms of the contract in any substantial way. The effort of the plaintiff was directed to excusing its failure, not to proving its performance of the provisions of the contract. Although the plaintiff elected to sue upon the theory of a quantum meruit, the written contract was proven. The plaintiff could not avoid its obligations to perform the conditions of the contract by the simple process of ignoring the contract and designating its demand a cause of action upon the theory of a quantum meruit. The evidence, measured by the terms of the contract, shows a failure to perform on the part of the plaintiff, and that its failure was not waived or excused by the defendant.

•The charge of the court to the jury was very general in terms, and could not have served to convey to the jury any precise idea of the issues that were involved. An examination of the whole record shows that the jury, not having received proper guidance from the court, have rendered a verdict for the plaintiff in disregard of the contract and the evidence.

Judgment reversed, and new trial ordered, with costs to the appellant to abide the event. All concur.