SUPERIOR COURT
OF THE
STATE OF DELAWARE
Sussex County Courthouse
ROBERT H. ROBINSON, JR. 1 The Circle, Suite 2
JUDGE Georgetown, DE 19947
Telephone: (302) 856-5264
Submitted: May 25, 2022
Decided: August 25, 2022
Edward Seglias, Esquire Brian D. Tome, Esquire
William R. Firth, III, Esquire Walter J. O’Brien, Esquire
Emily A. Letcher, Esquire Reilly, McDevitt & Henrich, P.C.
Cohen, Seglias, Pallas, Greenhall & Delle Donne Corporate Center
Furman, P.C. 1013 Centre Road, Suite 210
500 Delaware Avenue, Suite 730 Wilmington, Delaware 19805
Wilmington, Delaware 19801 Attorneys for Defendant
Attorneys for Plaintiffs
Re: CB Lewes, LLC and Coastal Tide Partners, LLC v. Brightfields, Inc.,
C.A. No. S20-C-06-001 RHR
Dear Counsel:
Before the Court is Plaintiff CB Lewes, LLC’s (“CB Lewes”) and Plaintiff
Coastal Tide Partners, LLC’s (“Coastal Tide”) (collectively, “Plaintiffs”) Motion for
Leave to File an Amended Complaint (“Motion to Amend”) against Defendant,
Brightfields, Inc. (“Brightfields” or “Defendant”).
I. Background
Plaintiffs brought this suit seeking damages from work performed by
Defendant on the redevelopment of a brownfield in Lewes, Delaware. The original
complaint alleged: (1) negligence; (2) professional negligence; (3) negligent
provision of information; and (4) breach of contract.1
Defendant moved to dismiss the tort claims and answered the breach of
contract claim. Defendant argued that the economic loss doctrine—which “is a
judicially created doctrine that prohibits recovery in tort where a product has only
damaged itself (i.e., has not caused personal injury or damage to other property) and,
the only losses suffered are economic in nature”2—barred Plaintiffs’ tort claims.
Defendant maintained that the “information supplier” exception to the economic loss
doctrine did not apply. Plaintiffs did not ask for leave to amend in lieu of dismissal.
After examining all well-pleaded allegations in the complaint, this Court
agreed with Defendant, finding that Plaintiffs’ tort claims were barred by the
economic loss doctrine. This Court found that Defendant provided information in
connection with the remediation services it provided to Plaintiffs, but it concluded
that Defendant was not an “information supplier.” Rather, this Court found
Defendant’s activities to be analogous to those of the defendants in Riverbend
Community, LLC v. Green Stone Engineering,3 and Millsboro Fire Company v.
Construction Management Services.4 In those cases, although the defendants
1
Compl., D.I. 1.
2
Brasby v. Morris, 2007 WL 949485, at *6 (Del. Super. Ct. Mar. 29, 2007) (quoting Marcucilli v.
Boardwalk Builders, Inc., 1999 WL 1568612, at *4 (Del. Super. Ct. Dec. 22, 1999) (citation
omitted)).
3
2012 WL 1409013 (Del. Super. Ct. Apr. 4, 2012), aff'd, 55 A.3d 330 (Del. 2012).
4
2006 WL 1867705 (Del. Super. Ct. June 7, 2006).
2
provided information in connection with services rendered, they were not found to
be “information suppliers” because construction/renovation was the “end and aim”
product of the defendants’ work, not the providing of information.5 This Court
reasoned that Defendant’s actions—providing reports and plans in connection to
redevelopment—is similar to those of engineers and architects who provide plans in
connection with construction projects. Therefore, this Court ruled that the tort claims
were barred by the economic loss doctrine and dismissed them. The order granting
dismissal did not explicitly indicate whether these claims were dismissed with or
without prejudice.6
II. The Present Motion
Plaintiffs now seek to amend their complaint to add additional facts and revive
the dismissed tort claims. The Proposed Amended Complaint alleges five tort
counts: (1) negligence (CB Lewes v. Brightfields), (2) negligence (Coastal Tide v.
Brightfields), (3) professional negligence (CB Lewes v. Brightfields), (4)
professional negligence (Coastal Tide v. Brightfields), (5) negligent provision of
information (CB Lewes and Coastal Tide v. Brightfields).7 The Proposed Amended
Complaint also clarifies that the breach of contract claim is brought by CB Lewes.
5
Riverbend, 2012 WL 1409013, at *6; Millsboro Fire Co., 2006 WL 1867705, at *3.
6
CB Lewes, LLC v. Brightfields Inc., 2020 WL 6364521 (Super. Ct. Oct. 29, 2020).
7
Proposed Am. Compl., D.I. 47.
3
Plaintiffs filed the Motion to Amend on May 28, 2021. Plaintiffs initially
argued that they had the right to amend because Defendant had not filed a responsive
pleading. I ruled that Defendant had filed a responsive pleading by filing the motion
to dismiss and an answer to the breach of contract claim.8 I directed the parties to
address whether Plaintiffs may amend their complaint with leave of the court.
A. The Parties’ Positions
Plaintiffs contend that leave should be granted because they meet the
requirements for Superior Court Civil Rule 15, leave should be freely given,
prejudice to the Defendant is minimal, and the amendment is not futile. Plaintiffs
alleged that they did not possess a copy of the contract between the parties (the
“Contract”) when they filed suit and that they did not have it when the motion to
dismiss was filed and considered by this Court.9 Plaintiffs received a copy of the
Contract when Defendant included it as part of its responses to interrogatories and
requests for production six months after this Court issued its decision on the motion
to dismiss.
Defendant contends that Plaintiffs are attempting an “end run around” this
Court’s order dismissing the tort claims and that it faces prejudice if the motion to
amend is granted. Defendant also argues that the amendment should be denied
8
Letter Order dated Jan. 27, 2022, D.I. 42.
9
Aff. of William R. Firth, III, Esq., D.I. 47, ¶ 9.
4
because the tort claims are still subject to dismissal based on, among other things,
the economic loss doctrine.
B. Discussion
The Proposed Amended Complaint cites newly discovered facts—provided
by the Contract—that Plaintiffs believe support their position that Defendant was an
information supplier. The facts relevant to the Motion to Amend include:
1) Defendant was “to perform the necessary exploratory test pit work and
other related services required by [Delaware Department of Natural
Resources (“DNREC”)]”.10
2) Defendant was to “establish existing environmental conditions, fill in
data gaps as required by DNREC, and evaluate what environmental
risks, if any, for future development of the property.”11
3) Defendant was to “among other things, review available information
and data about the environmental site conditions, create a map of that
data, complete the site investigation, provide a report to DNREC, and
identify remediations needed by CB Lewes as part of the re-
development.”12
4) Defendant was to “review and tabulate analytical information, collect
and analyze soil samples, and survey well locations and elevations and
calculate groundwater elevations at each well… all for the purpose of
being able to provide a report of such information to CB Lewes and
DNREC.”13
5) Defendant did not propose to do “any site remediation work, project
oversight or the creation of plans for any remediation work.14
6) The main product provided by Brightfields to CB Lewes was analytical,
mathematical, and data information, including supporting surveys. This
10
Proposed Am. Compl., D.I. 47 ¶17.
11
Id. at ¶ 18.
12
Id. at ¶ 22.
13
Id. at ¶ 23 (internal quotations omitted).
14
Id. at ¶ 24.
5
information provided by Brightfields was not incidental to any other
product provided by Brightfields; the information was the product.15
Superior Court Civil Rule 15 governs the amendment of pleadings.16 After a
responsive pleading has been filed, a party may amend a pleading only with leave of
the court or by written consent of the adverse party, and “leave shall be freely given
when justice so requires.”17 Generally, Delaware courts liberally grant leave to
amend unless the opposing party would be seriously prejudiced.18 If there is
“evidence of undue delay, bad faith, or dilatory motive on the part of the movant,
repeated failure to cure deficiencies, prejudice, futility, or the like,” leave should not
be granted.19 Delaware courts permit amendment of a complaint after dismissal to
allow the party to correct “the defect that led to the dismissal, ‘or to correct
technicalities in their claims in situations where the amendment arises out of the
exact same set of facts.’”20 “[L]eave to file an amended complaint should not
15
Id. at ¶ 26.
16
Super. Ct. Civ. R. 15 (“A party may amend the party's pleading once as a matter of course at
any time before a responsive pleading is served or, if the pleading is one to which no responsive
pleading is permitted and the action has not been placed upon the trial calendar, the party may so
amend it at any time within 20 days after it is served. Otherwise, a party may amend the party's
pleading only by leave of court or by written consent of the adverse party; and leave shall be freely
given when justice so requires. A party shall plead in response to an amended pleading within the
time remaining for response to the original pleading or within 10 days after service of the amended
pleading, whichever period may be the longer, unless the Court otherwise orders”).
17
Id.
18
Dunfee v. Blue Rock Van & Storage, Inc., 266 A.2d 187 (Del. Super. Ct. 1970).
19
Hess v. Carmine, 396 A.2d 173 (Del. Super. Ct. 1978).
20
Rich Realty, Inc. v. Potter Anderson & Corroon LLP, 2011 WL 1632338, at *2 (Del. Super. Ct.
Apr. 26, 2011) (quoting Playtex Family Prods., Inc. v. St. Paul Surplus Lines Ins. Co., 1990 WL
35299, at *4 (Del. Super. Ct. Mar. 27, 1990)).
6
properly be granted unless new facts are made to appear which would remedy the
defects contained in the previous complaint.”21
Here, Plaintiffs face the hurdle that a motion to dismiss was granted for the
three tort claims that they hope to revive on the basis that the claims were barred by
the economic loss doctrine. If an amendment would not survive a motion to dismiss
under Rule 12(b)(6), it must be denied as being futile.22 The question is, what, if
anything, has changed since this Court’s order dismissing the tort claims that would
now allow these claims to withstand a motion to dismiss. The answer is simple:
Plaintiffs now have the Contract and are able to identify the parties to the Contract
and the scope of work covered by the Contract. The Proposed Amended Complaint
specifies the narrow scope of the work for which Defendant was responsible and on
which Plaintiffs base their claims.
This Court, in granting dismissal of the tort claims, identified two elements to
the information supplier exception to the economic loss doctrine, and found that
Plaintiffs failed to plead those elements. In order to fall within the exception, a
defendant must (1) be in the business of supplying information and (2) have supplied
the information to the plaintiff for use in business transactions with third parties.23
21
Playtex Family Prods., Inc. v. St. Paul Surplus Lines Ins. Co., 1990 WL 35299, at *4 (Del.
Super. Ct. Mar. 27, 1990) (citing Kirsch v. Barnes, 157 F. Supp. 671, 672 (N.D. Cal. 1957), aff'd,
263 F.2d 692 (9th Cir. 1959)).
22
Marshall v. Priceline.com, Inc., 2008 WL 4153740, at *1 (Del Super. Ct. Aug. 28, 2008).
23
CB Lewes, 2020 WL 6364521, at *4.
7
A defendant will not be considered an information provider “where the information
supplied is merely ancillary to the sale of a product or service in connection with the
sale.”24 In Millsboro Fire Co., the Superior Court described the exception as
narrowly tailored and stated that “only surveyors, and those expressly in the business
of supplying information such as accountants, financial advisors, and title searchers,
can be liable in tort for purely economic losses.”25 However, the court also
recognized that the point where one crosses the line into the business of “supplying
information” has not been definitively resolved by Delaware courts.26 Engineers may
fall on either side of the line, depending on the nature of the service provided.27 For
example, engineers who provide calculations, specifications, or reports for a project
are considered information providers.28 But when an engineer “produces designs or
plans as a component of a construction project, any information supplied is ancillary
to the finished product,” the engineer is not an information supplier.29
Although I have concerns about the legal sufficiency of Plaintiffs’ proposed
amendment, accepting all allegations in the proposed amendment as true, I cannot
24
Christiana Marine Serv. Corp. v. Texaco Fuel & Marine Mktg., 2002 WL 1335360, at *7 (Del.
Super. Ct. June 13, 2002).
25
Millsboro Fire Co., 2006 WL 1867705, at *3 (Del. Super. Ct. Sept. 24, 2018).
26
Id.
27
Riverbend Cmty., LLC, 2012 WL 1409013, at *4 (citing Delaware Art Museum v. Ann Beha
Architects, Inc., 2007 WL 2601472, at *3 (D. Del. Sept. 11, 2007)). The Proposed Amended
Complaint alleges that Defendant represented that it possessed all engineering qualifications
necessary to assess the site.
28
Id.
29
Id.
8
say that Plaintiffs cannot recover under any reasonably conceivable set of
circumstances. I believe I must grant the motion and allow for reasonable discovery
to proceed. The newly discovered and alleged facts in the Proposed Amended
Complaint nudge Defendant closer to falling within the information supplier
exception. Therefore, I find the proposed amendment is not futile.
Next, I address the additional considerations regarding a motion to amend,
including evidence of undue delay, bad faith, or dilatory motive on the part of
Plaintiffs, repeated failure to cure deficiencies, prejudice, or the like. Defendant
makes no argument that the amendment is the result of bad faith or dilatory motive
on the part of the movant and there is no evidence of such. Instead, Defendant argues
that there was undue delay, repeated failure to cure deficiencies, and prejudice.
Plaintiffs filed the Motion to Amend less than sixty days after receiving the
Contract that provided Plaintiffs with the basis for the proposed amendment.30
Although Plaintiffs do not offer many (if any) reasons for this sixty-day delay, I find
it to be reasonable and not an undue delay justifying the denial of the Motion to
Amend. The claims are of the same nature of the initial complaint and the scope of
discovery will not change significantly. Prejudice to Defendant is also minimal.
Defendant also argues that res judicata should prevent the amendment. As
noted previously, a party may be permitted to amend the complaint after dismissal
30
Aff. of William R. Firth, III, Esq., D.I. 47, ¶ 9.
9
for the purpose of correcting the defect that led to the dismissal, “or to correct
technicalities in their claims in situations where the amendment arises out of the
exact same set of facts.” Notably, the Delaware Supreme Court noted that “res
judicata does not operate to bar claims based on facts that were not, and could not
have been, known to the plaintiff in the second action at the time of the first action.”31
This case is distinguishable from Rich Realty Incorporated v. Potter Anderson &
Carroon,32 cited by Defendant. In denying the motion to amend, the Rich Realty
court specifically found that new proposed language was not based on newly
discovered evidence and—more importantly—that all the facts had been well-
known to the plaintiffs for years.33 Here, the proposed language is based upon newly
discovered evidence so leave to amend is appropriate.
III. Conclusion
Superior Court Civil Rule 15 provides for the amendment of a complaint to
correct the defects that led to dismissal. Here, Plaintiffs’ Proposed Amended
Complaint remedies the defects of the original complaint, and the motion is not
futile. Therefore, Plaintiffs’ Motion for Leave to File an Amended Complaint is
GRANTED.
31
LaPoint v. AmerisourceBergen Corp., 970 A.2d 185, 193 (Del. 2009) (citing Ambase Corp. v.
City Investing Co. Liquidating Trust, 326 F.3d 63 (2d Cir.2003).
32
Rich Realty, Inc., 2011 WL 1632338.
33
Id. at *4.
10
IT IS SO ORDERED.
Sincerely,
/s/Robert H. Robinson, Jr.
Judge
11