If this opinion indicates that it is “FOR PUBLICATION,” it is subject to
revision until final publication in the Michigan Appeals Reports.
STATE OF MICHIGAN
COURT OF APPEALS
SHAREEF EL-JAMALY, UNPUBLISHED
September 1, 2022
Plaintiff-Appellee,
v No. 355402
Wayne Circuit Court
KIRCO MANIX CONSTRUCTION, LLC, and LC No. 18-011226-NO
KIRCO DEVELOPMENT, LLC,
Defendants-Appellees,
and
KIRCO-OM PLYMOUTH, LLC, OERLIKON
METCO (US), INC., GHAFARI ASSOCIATES,
LLC, GHAFARI, INC., NATIONAL SAFETY
RESOURCE CENTER, LLC, CHRISTOPHER
STREB, and DTE ENERGY COMPANY,
Defendants,
and
DTE ELECTRIC COMPANY,
Defendant-Appellant.
-1-
SHAREEF EL-JAMALY,
Plaintiff-Appellee,
v No. 355703
Wayne Circuit Court
KIRCO MANIX CONSTRUCTION, LLC, and LC No. 18-011226-NO
KIRCO DEVELOPMENT, LLC,
Defendants-Appellees,
and
KIRCO-OM PLYMOUTH, LLC, GHAFARI
ASSOCIATES, LLC, GHAFARI, INC.,
NATIONAL SAFETY RESOURCE CENTER, LLC,
CHRISTOPHER STREB, DTE ENERGY
COMPANY, and DTE ELECTRIC COMPANY,
Defendants,
and
OERLIKON METCO (US), INC.,
Defendant-Appellant.
-2-
SHAREEF EL-JAMALY,
Plaintiff-Appellee,
v No. 355932
Wayne Circuit Court
KIRCO MANIX CONSTRUCTION, LLC, and LC No. 18-011226-NO
KIRCO DEVELOPMENT, LLC,
Defendants-Appellants,
and
KIRCO-OM PLYMOUTH, LLC, OERLIKON
METCO (US), INC., GHAFARI ASSOCIATES,
LLC, GHAFARI, INC., NATIONAL SAFETY
RESOURCE CENTER, LLC, CHRISTOPHER
STREB, DTE ENERGY COMPANY, and DTE
ELECTRIC COMPANY,
Defendants.
-3-
SHAREEF EL-JAMALY,
Plaintiff-Appellee,
v No. 356542
Wayne Circuit Court
KIRCO MANIX CONSTRUCTION, LLC, and LC No. 18-011226-NO
KIRCO DEVELOPMENT, LLC,
Defendants-Appellees,
and
KIRCO-OM PLYMOUTH, LLC, OERLIKON
METCO (US), INC., GHAFARI ASSOCIATES,
LLC, GHAFARI, INC., DTE ENERGY
COMPANY, and DTE ELECTRIC COMPANY,
Defendants,
and
NATIONAL SAFETY RESOURCE CENTER, LLC,
and CHRISTOPHER STREB,
Defendants-Appellants.
Before: GADOLA, P.J., and CAVANAGH and K. F. KELLY, JJ.
PER CURIAM.
In these consolidated1 appeals, defendants-appellants appeal by leave granted the orders of
the trial court denying their respective motions for summary disposition under MCR 2.116(C)(10)
of plaintiff’s claims relating to injuries he sustained while working at a construction site. In each
of the consolidated appeals, we reverse the decision of the trial court and remand for entry of
summary disposition in favor of the respective defendants.
1
El-Jamaly v Kirco Manix Constr, LLC, unpublished order of the Court of Appeals, entered May
6, 2021 (Docket No. 356542).
-4-
I. FACTS
On November 13, 2017, plaintiff was seriously injured while working at a construction site
in Plymouth Township, Michigan. Plaintiff was employed by Merlo Construction Company, Inc.
(Merlo), a subcontractor performing concrete work as part of the construction project. On that
day, Merlo was pouring concrete for a driveway approach at the site, and plaintiff was working at
the construction site as a general laborer. Plaintiff was carrying a long-handled concrete-
smoothing tool called a “bull float” vertically from the worksite to the Merlo truck when the tool
either touched the overhead power line or came close enough to the power line that plaintiff was
electrocuted. Plaintiff sustained severe electrical injuries that resulted in the amputation of his
right arm above the elbow and the amputation of his left leg below the knee; he also suffered a
traumatic brain injury when he fell after being electrocuted.
The power line involved was 24 feet and 4 inches above the ground, which was higher than
the required vertical clearance height of 18 feet and 7 inches. During his deposition, plaintiff
testified that he knew that there were power lines at the construction site, but did not recall seeing
any warning signs regarding the overhead wires. He further testified that he did not know whether
he touched the overhead wire with the bull float.
The bull float consisted of four interlocking six-foot segments that were clipped together
through spring-push buttons that connected the component parts into an approximately 23½-foot
tool. The bull float had a conductive aluminum handle, rather than a nonconductive fiberglass
handle. The Merlo project foreman testified that Merlo instructed its workers to carry long-
handled tools such as bull floats horizontally; Merlo workers also testified that a bull float should
be carried horizontally rather than vertically, or that alternatively the bull float should be
disassembled before being carried.
The construction site property was owned by defendant Kirco-OM Plymouth, LLC (Kirco-
OM). Defendant Kirco Manix Construction, LLC (Kirco Manix) was the general contractor and
construction manager of the construction project, and defendant Kirco Development, LLC (Kirco
Development) was the project planner and developer. A commercial building was being
constructed on the site for defendant Oerlikon Metco (US), Inc (Oerlikon), which had a long-term
lease agreement with Kirco-OM for the building, but the term of the lease had not begun and
Oerlikon was not in possession of the building that was under construction on the day of the
accident. Defendant National Safety Resource Center, LLC (NSRC) and its principal, defendant
Christopher Streb, were safety consultants for plaintiff’s employer, Merlo. Defendant DTE
Electric Company (DTE) is the utility company that owned, controlled, and maintained the
overhead power lines on the property. Plaintiff initiated this negligence action, asserting various
theories of liability against defendants. DTE, Oerlikon, Kirco Manix, Kirco Development, NSRC,
and Streb moved for summary disposition of plaintiff’s claims. The trial court denied defendants’
motions, and these appeals followed.2
2
The other defendants were dismissed by the trial court and are not involved in these appeals.
-5-
II. DISCUSSION
A. STANDARD OF REVIEW
We review de novo a trial court’s decision to grant or deny a motion for summary
disposition. Meemic Ins Co v Fortson, 506 Mich 287, 296; 954 NW2d 115 (2020). We also review
de novo as a question of law whether a defendant owed the plaintiff a duty of care, Powell-Murphy
v Revitalizing Auto Communities Environmental Response Trust, 333 Mich App 234, 243; 964
NW2d 50 (2020), and the applicability of a legal doctrine, such as the common work area doctrine.
See James v Alberts, 464 Mich 12, 14; 626 NW2d 158 (2001).
A motion for summary disposition under MCR 2.116(C)(10) tests the factual sufficiency
of a claim, and is properly granted when there is no genuine issue as to any material fact and the
moving party is entitled to judgment as a matter of law. El-Khalil v Oakwood Healthcare, Inc,
504 Mich 152, 160; 934 NW2d 665 (2019). When reviewing the trial court’s decision to grant or
deny summary disposition under MCR 2.116(C)(10), we consider the documentary evidence
submitted by the parties in the light most favorable to the nonmoving party. Id. A genuine issue
of material fact exists when the record leaves open an issue upon which reasonable minds might
disagree. Johnson v Vanderkooi, 502 Mich 751, 761; 918 NW2d 785 (2018). To defeat a motion
for summary disposition, the plaintiff “must do more than present evidence that the defendant’s
conduct possibly caused the injury,” but rather must present “substantial evidence from which a
jury may conclude that more likely than not, but for the defendant’s conduct, the plaintiff’s injuries
would not have occurred.” McMaster v DTE Energy Co, ___ Mich ___, ___; ___ NW2d ___
(2022) (Docket No. 162076); slip op at 11 (quotation marks and citation omitted).
B. DOCKET NO. 355402
In Docket No. 355402, DTE contends that the trial court erred by denying its motion for
summary disposition because DTE did not owe a legal duty to plaintiff, and therefore plaintiff’s
claim of negligence against DTE must fail. We agree.
In his second amended complaint, plaintiff alleges that DTE was negligent because DTE
knew about the construction project and denied a request to cover the power lines or to take other
actions to protect against the dangers posed by the power lines. Plaintiff alleges that DTE was
negligent because it failed to initiate, convene, competently conduct, and follow up on meetings
regarding the construction project, failed to protect workers, including plaintiff, from unreasonable
risks of harm posed by the power lines, and failed to bury, raise, relocate, de-energize, cover, or
warn about the power lines.
To set forth a prima facie case of negligence, a plaintiff must prove that the defendant owed
a legal duty to the plaintiff, the defendant breached the legal duty by failing to exercise ordinary
care in performing that duty, and the plaintiff suffered damages proximately caused by the
defendant’s breach. McMaster, ___ Mich at ___; slip op at 5. The threshold question in a
negligence action is whether the defendant owed a legal duty to the plaintiff, Fultz v Union-
Commerce Assoc, 470 Mich 460, 463; 683 NW2d 587 (2004), which is a question of law to be
decided by the court. Hill v Sears, Roebuck & Co, 492 Mich 651, 659; 822 NW2d 190 (2012). If
-6-
the defendant does not owe a legal duty to the plaintiff there can be no breach and no causation,
and thus no liability in negligence, entitling the defendant to summary disposition. See id. at 660.
“Duty is the legal obligation to conform one’s conduct to a particular standard to avoid
subjecting others to an unreasonable risk of harm.” Composto v Albrecht, 328 Mich App 496, 499;
938 NW2d 755 (2019). Generally, there is no duty that requires one person to protect or aid
another person. Williams v Cunningham Drug Stores, Inc, 429 Mich 495, 499; 418 NW2d 381
(1988). However, every person performing an undertaking has a duty to use due care not to
endanger other persons and their property. McMaster, ___ Mich at ___; slip op at 6. “This rule
of the common law arises out of the concept that every person is under the general duty to so act,
or to use that which he controls, as not to injure another.” Id., quoting Clark v Dalman, 379 Mich
251, 261; 150 NW2d 755 (1967). However, our Supreme Court in In re Certified Question from
Fourteenth Dist Court of Appeals of Texas, 479 Mich 498; 740 NW2d 206 (2007), explained that
although Clark makes statements suggesting a broad general duty,
[T]hese statements immediately follow the statement that “[a]ctionable negligence
presupposes the existence of a legal relationship between parties by which the
injured party is owed a duty by the other, and such duty must be imposed by law.”
[Clark, 379 Mich ] at 260-261. . . . Therefore, contrary to plaintiffs’. . . suggestion,
Clark does not stand for the proposition that everybody owes a duty to everybody
else. [In re Certified Question, 479 Mich at 509 n 10.]
A duty of care may arise by statute, by a contractual relationship, or under the common
law. Hill, 492 Mich at 660-661. Special relationships that may give rise to a duty include owners
and occupiers of land and their invitees, Bailey v Schaaf, 494 Mich 595, 604; 835 NW2d 413
(2013), employers and employees, common carriers and passengers, and innkeepers and guests.
Williams, 429 Mich at 499. “These special relationships are predicated on an imbalance of control,
where one person entrusts himself to the control and protection of another, with a consequent loss
of control to protect himself.” Bailey, 494 Mich at 604 (emphasis, quotation marks, and citation
omitted). The special relationship “must be sufficiently strong to require the defendant to take
action to benefit the injured party.” Murdock v Higgins, 454 Mich 46, 54; 559 NW2d 639 (1997).
When no relationship exists between the parties, no duty can be imposed. In re Certified Question,
479 Mich at 507.
“Factors relevant to the determination whether a legal duty exits include the relationship
of the parties, the foreseeability of the harm, the burden on the defendant, and the nature of the
risk presented.” Hill, 492 Mich at 661 (quotation marks and citation omitted). The most important
considerations in determining whether a duty exists are the relationship of the parties and the
foreseeability of the harm; if either of those two factors is lacking, then it is unnecessary to consider
the remaining factors. Id. “In other words, before a duty can be imposed, there must be a
relationship between the parties and the harm must have been foreseeable.” Id. (Quotation marks
and citation omitted).
Our Supreme Court has decided several cases addressing the extent of the legal duty owed
by an electric utility, an examination of which is useful here. In Schultz v Consumers Power Co,
443 Mich 445, 449; 506 NW2d 175 (1993), the plaintiff’s decedent was fatally electrocuted while
painting the exterior of a house. The plaintiff’s decedent was using a 27-foot aluminum extension
-7-
ladder when electricity allegedly arced from an uninsulated wire located near the house,
electrocuting the decedent. Id. at 448. The plaintiff sued the power company, alleging that the
power company was negligent in maintaining the wire. Id. at 448-449. A jury found the power
company negligent and awarded the plaintiff $750,000. Id. at 449. This Court reversed,
determining that the power company did not owe a duty to the decedent. Id. Our Supreme Court
reversed this Court’s decision, holding that the relationship between the power company and the
decedent was sufficient to impose a duty under those circumstances, and stating that “a power
company has an obligation to reasonably inspect and repair wires and other instrumentalities in
order to discover and remedy hazards and defects.” Id. at 451. Regarding foreseeability, the Court
stated that “a reasonable person could certainly anticipate that a painter could be electrocuted if
his aluminum ladder came close to, or touched, a pitted, corroded and frayed electric wire,” and
“a reasonable person could confidently conclude that this event would cause serious injury or death
to the painter.” Id. at 452. The Court reasoned:
Those engaged in transmitting electricity are bound to anticipate ordinary
use of the area surrounding the lines and to appropriately safeguard the attendant
risks. The test to determine whether a duty was owed is not whether the company
should have anticipated the particular act from which the injury resulted, but
whether it should have foreseen the probability that injury might result from any
reasonable activity done on the premises for business, work, or pleasure. Here,
Consumers Power should have realized that homeowners generally maintain their
homes. This may include washing windows, cleaning troughs, repairing the roof,
cleaning gutters, and, certainly, painting. Considering the proximity of the
uninsulated primary wire to the house (roughly fifteen horizontal feet and twenty-
four vertical feet from the ground), it was foreseeable that someone making repairs
could be injured by a dilapidated wire. [Id. at 452-453.]
This duty, however, does not include warning or guarding against all possible contacts with
elevated power lines. In Groncki v Detroit Edison Co, 453 Mich 644, 649; 557 NW2d 289 (1996)
(opinion by BRICKLEY, C.J.), our Supreme Court rejected negligence claims in three incidents
when the plaintiffs came into contact with elevated power lines that were not alleged to be
defective. The Court held that in each incident the defendant power company could not have
foreseen that equipment could come into contact with its maintained elevated power lines.
In the first of the three cases, the plaintiff, Theodore Parcher, was electrocuted when the
29-foot high scaffold he was moving using a forklift at a construction site came into contact with
a power line. Id. at 650. The power lines were 65 feet from the building and 35 feet above the
ground. Id. Edison, which owned and operated the lines, knew about the ongoing construction.
Id. In the second of the three cases, the plaintiff, Gerald Groncki, was injured while moving a
ladder that contacted an uninsulated overhead power line that was 21 feet high and 14½ feet from
the building. Id. In the third case, the plaintiff’s decedent was unloading materials at a
construction site when the boom of his truck touched the overhead power lines, killing him. The
uninsulated power lines were 12 feet from the house and 26 feet high. Id. at 652-653. The power
company was aware of the construction, but refused to insulate or move the power lines unless the
cost of doing so was reimbursed. Id.
-8-
Chief Justice Brickley’s lead opinion in Groncki explained that “[t]he scope of the duty
owed by electrical companies to move, insulate or de-energize overhead power lines is a question
of foreseeability.” Id. at 654, citing Schultz, 443 Mich at 452. “Utility companies, particularly
electric companies are charged with a duty to protect against foreseeable harm.” Groncki, 453
Mich at 654 (opinion by BRICKLEY, C.J.), citing Schultz, 443 Mich at 452. With respect to the
allegations in two of the cases in Groncki that Edison owed a duty to warn of the presence of the
power lines, the lead opinion in Groncki stated that “there is no duty to warn someone of a risk of
which that person is aware. Specifically, there is no duty to warn of known overhead power lines.”
Groncki, 453 Mich at 656 (opinion by BRICKLEY, C.J.) (citation omitted). “The duty to warn only
arises when there is a foreseeable victim. Thus, this duty, like the duty to inspect and repair, does
not arise where it is not foreseeable to Edison that the plaintiff would come into harmful contact
with the wires.” Id. at 656-657.
The Court in Groncki also discussed the Court’s earlier decision in Koehler v Detroit
Edison Co, 383 Mich 224; 174 NW2d 827 (1970), in which the plaintiff was electrocuted when
the crane on which he was riding at a construction site came into contact with overhead power
lines. The Court in Koehler upheld the trial court’s determination that the electrical company owed
no duty to the plaintiff, reasoning that “[t]he mere fact that Detroit Edison knew a building was
under construction near its power line and that, from time to time, mobile cranes were being
brought upon the premises to be used in construction work, would not, standing alone, create a
duty upon Detroit Edison to remove the charge, insulate the line, or notify the parties of a
dangerous condition.” Groncki, 453 Mich at 655 (opinion by BRICKLEY, C.J.), quoting Koehler,
383 Mich at 231.
With respect to Parcher’s case, the lead opinion in Groncki stated that Edison owed no duty
to protect Parcher. Id. at 657. “As in Koehler, Edison knew that there was ongoing construction,
but had no reason to know that any high profile machinery would be used near its power lines”
and the case did not involve an allegation of inadequately maintained power lines. With respect
to Groncki’s case, the lead opinion concluded that Edison did not owe him a duty to inspect, repair,
insulate, move, or place safety barriers around the power lines. Id. at 658. The lead opinion found
Groncki’s case distinguishable from Schultz:
In Schultz, the probability of injury was based upon a frayed line that had been
placed next to a preexisting structure. Further, the plaintiff in Schultz was a
homeowner making repairs to his own home. In this case, there is no evidence
suggesting that the line was in poor condition or was not properly maintained.
Further, Mr. Groncki was not a homeowner unfamiliar with the dangers of electric
lines. Rather, he was an experienced workman who was fully aware of the presence
of the wires. Indeed, he warned a coworker to take exceptional care around the
power lines. Thus, it was not foreseeable that he would ignore his own warnings
and attempt to move the fully extended metal ladder himself, and Edison owes no
duty to Mr. Groncki. [Id. at 658-659.]
Similarly, regarding the third case in Groncki, the lead opinion determined that the
plaintiff’s injury was not foreseeable to Edison and that Edison thus owed no duty to move,
insulate, de-energize, or warn about the power lines. Id. at 659. “[I]t was not foreseeable to Edison
that an experienced, skilled workman would disregard clear instructions and operate his delivery
-9-
vehicle directly beneath power lines. Thus, no duty arose on the part of Edison to [Bohnert].” Id.
at 660.
In Valcaniant v Detroit Edison Co, 470 Mich 82, 84; 679 NW2d 689 (2004), the Court
determined that as in Groncki, the plaintiff’s injuries in Valcaniant were not foreseeable and that
Edison owed the plaintiff no legal duty. The plaintiff owned a gravel lot on which he operated a
used-car business. The plaintiff was injured when a dump truck on the lot severed a nearby
overhead power line owned by Edison. Id. at 84-85. Because the ground was wet, electricity
traveled through the truck and the ground to the plaintiff, who was standing nearby. Id. Edison’s
sensor automatically detected the severed line and momentarily stopped the flow of electricity, but
was designed to restart the flow of electrical current three times within a six-second period to
determine if a fault existed. The sensor operated as designed, and the plaintiff was injured by the
sensor completing its cycles. The plaintiff sued Edison, arguing that Edison owed him a legal duty
to deenergize the severed power line immediately. Id. The trial court denied Edison summary
disposition. This Court reversed, holding that Edison owed no legal duty to the plaintiff. Id. Our
Supreme Court affirmed this Court’s opinion and remanded to the trial court for entry of summary
disposition in favor of Edison. Id. at 84, 88. The Court stated:
Edison had no obligation to anticipate that the dump truck operated under
plaintiff’s direction would sever an overhead power line that was suspended more
than twenty-five feet above the ground, much less that plaintiff would be standing
on wet ground several feet away. As a result, Edison had no legal duty to anticipate
that plaintiff might be injured when the sensor device briefly re-energized the line,
as it was designed to do, or to take other steps to prevent plaintiff’s injury. [Id. at
87-88.]
In this case, as in Valcaniant and Groncki, plaintiff does not allege that the wire involved
in plaintiff’s accident was defective. Rather, plaintiff alleges that DTE had a duty to move, de-
energize, insulate, or warn about the power lines in light of ongoing construction near the power
lines. As in Valcaniant and Groncki, however, plaintiff’s accident was unforeseeable, and DTE
thus had no duty to take the actions plaintiff argues should have been taken.
Plaintiff was employed by Merlo, which was performing concrete work for a driveway
from the street to the parking lot, and the section of power line in question was near the street.
Although concerns about the power lines had been brought to DTE’s attention several months
earlier, those concerns related to sections of the power lines near the building.3 There is no
indication that any concerns expressed to DTE were focused on the specific area where plaintiff
was injured or that concerns were raised specifically about the performance of concrete work under
the power lines in that area. On the date of the accident, the power line involved in plaintiff’s
3
The so-called “Carnwath incident” occurred in April 2017 when a high-reaching excavating
machine operated by Carnwath Excavating severed a power line near the building site. The
incident occurred in an area distant from the location of plaintiff’s accident, and no injuries
occurred. That incident did not provide notice to DTE of an increased likelihood that a person
carrying a handheld tool near the street was likely to contact a power line.
-10-
electrocution was 24 feet and 4 inches high, in excess of the required vertical clearance of 18 feet
and 7 inches.
Critical to the lack of foreseeability of plaintiff’s accident is that he chose to raise a fully
extended 23½-foot aluminum bull float vertically underneath the power lines. Plaintiff’s job duties
required him to transport the bull float back to the Merlo truck after the tool had been used by other
Merlo workers. Performing this task did not require plaintiff to raise the tool vertically. Rather,
other Merlo employees testified that a bull float should not be carried vertically, but should be
carried horizontally or taken apart into its four segments before moving it. Plaintiff testified that
he was familiar with disassembling the bull float and also was generally aware of the power lines
at the construction site. There is also evidence indicating that he had been warned about the power
lines by Kirco Manix during a safety-orientation meeting.4
Further, DTE had no reason to know that Merlo would equip its employees with
conductive-handled bull floats for use in proximity to overhead power lines, in contravention of a
MIOSHA regulation.5 See Mich Admin Code, R 408.42520(3). Because DTE reasonably could
not have foreseen that a worker would raise a 23½-foot fully extended aluminum bull float
vertically into the air underneath the power lines, no duty arose on the part of DTE to protect
plaintiff by moving, insulating, de-energizing, or erecting safety barricades around the power lines.
See Hill, 492 Mich at 661 (if the harm is not foreseeable, then no duty can be imposed). Nor did
DTE owe a duty to warn plaintiff about the power lines, given that the incident was not foreseeable
to DTE and that plaintiff knew of the power lines. Groncki, 453 Mich at 656-658 (opinion by
BRICKLEY, C.J.); see also Hill, 492 Mich at 669 (noting that there is no duty to warn someone of a
risk of which that person is aware).
A review of the record suggests that the trial court conflated the element of duty with the
distinct element of breach of duty, suggesting that the determination of duty was a question of fact
for the jury. As noted, the existence of a legal duty is a question of law for the court to decide.
Valcaniant, 470 Mich at 86. By contrast, the element of breach of duty is generally for the trier of
fact to determine. Riddle v McLouth Steel Prod Corp, 440 Mich 85, 96; 485 NW2d 676 (1992).
4
But this evidence regarding the safety-orientation meeting is not critical to the analysis in DTE’s
appeal. Plaintiff’s admitted awareness of the power lines would preclude a conclusion that DTE
owed a duty to warn him about the power lines. See Groncki, 453 Mich at 656 (opinion by
BRICKLEY, C.J.) (“[T]here is no duty to warn someone of a risk of which that person is aware.
Specifically, there is no duty to warn of known overhead power lines.”) (Citation omitted). Also,
the lack of foreseeability of the incident to DTE is itself dispositive of the duty analysis.
5
After the accident, Merlo was cited and fined by the Department of Licensing and Regulatory
Affairs for two regulatory violations under the Michigan Occupational Safety and Health Act
(MIOSHA), MCL 408.1001 et seq., for allowing plaintiff to work with a metal-handled bull float
too close to the power lines and for the use of uninsulated bull floats underneath the power lines.
Kirco Manix was cited and fined for two violations for allowing plaintiff to work with a metal-
handled bull float close to the power lines and for failing to reinstall a blown-over “danger” sign
that had been installed to alert workers of the hazard of the overhead power lines.
-11-
Similarly, the record suggests that the trial court conflated the question of the standard of care with
the distinct question whether a duty exists. See also Valcaniant, 470 Mich at 86 n 4 (“Duty
concerns whether a defendant is under any legal obligation to act for the benefit of the plaintiff.
This concept should be distinguished from the standard of care, which, in negligence cases, always
requires reasonable conduct.”) (Citation and emphasis omitted).
In this case, plaintiff’s accident was not foreseeable to DTE, and thus, no duty arose on the
part of DTE to move, de-energize, insulate, or erect barricades around the power lines. Given the
lack of foreseeability as well as plaintiff’s knowledge of the power lines, no duty arose on the part
of DTE to warn plaintiff about the power lines. Absent a duty, DTE was entitled to summary
disposition.
C. DOCKET NO. 355703
In Docket No. 355703, Oerlikon contends that the trial court erred by denying its motion
for summary disposition6 of plaintiff’s claim of ordinary negligence because Oerlikon did not owe
a legal duty to plaintiff. Oerlikon also contends that the trial court erred by denying its motion for
summary disposition of plaintiff’s claim of premises liability. We agree.
As discussed, to establish a prima facie case of negligence a plaintiff must establish that
the defendant owed a legal duty to the plaintiff, the defendant breached that duty, and the plaintiff
suffered damages proximately caused by the defendant’s breach of its duty. McMaster, ___ Mich
at ___; slip op at 5. The threshold question is whether the defendant owed a legal duty to the
plaintiff. Fultz, 470 Mich at 463, which is a question of law to be decided by the court. Hill, 492
Mich at 659. If the defendant does not owe a legal duty to the defendant there can be no breach
and no causation, and thus no liability in negligence, entitling the defendant to summary
disposition.
In this case, plaintiff did not establish that Oerlikon owed a legal duty to plaintiff. There
was no relationship—special or otherwise—between plaintiff and Oerlikon. At the time of
plaintiff’s accident, Oerlikon was merely the future tenant of the building that was under
construction. Oerlikon did not own the property, nor did Oerlikon manage the construction site or
supervise safety at the site. The parties do not dispute that Kirco Manix was the general contractor
and construction manager, and that plaintiff was an employee of Merlo, a subcontractor. Although
Oerlikon used a trailer on the construction site and its representative was regularly present at the
construction site, the record suggests that his role was merely monitoring the construction progress.
Because there was no relationship between plaintiff and Oerlikon, Oerlikon did not owe a duty to
plaintiff and Oerlikon was entitled to summary disposition on plaintiff’s ordinary negligence
claim. See Hill, 492 Mich at 660-661. In addition, plaintiff failed to establish that the accident
6
Oerlikon moved for summary disposition under MCR 2.116(C)(8) and (10), but its motion was
based in part on evidence outside the pleadings and the record suggests that the trial court
considered evidence outside the pleadings when ruling on the motion. We therefore review the
trial court’s ruling as one under MCR 2.116(C)(10). See Cuddington v United Health Servs, Inc,
298 Mich App 264, 270; 826 NW2d 519 (2012).
-12-
was foreseeable to Oerlikon; Oerlikon could not foresee the actions of Merlo and plaintiff that led
to plaintiff’s electrocution. Accordingly, Oerlikon was entitled to summary disposition.
Oerlikon also was entitled to summary disposition of plaintiff’s claim of premises liability
because Oerlikon did not possess or control the premises at the time of plaintiff’s accident. When
a plaintiff alleges injuries arising from a dangerous condition on the land, the claim is one of
premises liability rather than ordinary negligence. Buhalis v Trinity Continuing Care Servs, 296
Mich App 685, 692; 822 NW2d 254 (2012). In a premises liability action, as in any negligence
action, the plaintiff must establish the elements of negligence. Goodwin v Northwest Michigan
Fair Ass’n, 325 Mich App 129, 157; 923 NW2d 894 (2018). Unlike ordinary negligence, however,
premises liability arises from the defendant’s possession and control of the land. See Finazzo v
Fire Equip Co, 323 Mich App 620, 632-633; 918 NW2d 200 (2018).
The initial inquiry when analyzing a claim of premises liability is the duty owed by the
possessor of the premises to a person entering the premises. Hoffner v Lanctoe, 492 Mich 450,
460; 821 NW2d 88 (2012). Here, the parties do not dispute that plaintiff was an invitee. The
possessor of land owes an invitee the duty to use reasonable care to protect the invitee from an
unreasonable risk of harm posed by a dangerous condition on the premises. Estate of Livings v
Sage’s Investment Group, LLC, 507 Mich 328, 337; 968 NW2d 397 (2021). The possessor of the
premises breaches that duty of care when he or she knows or should know of a dangerous condition
on the premises of which the invitee is unaware, and fails to fix, guard against, or warn the invitee
of the defect. Lowrey v LMPS & LMPJ, Inc, 500 Mich 1, 8; 890 NW2d 344 (2016).
If a defendant did not possess and control the premises, premises liability cannot be
asserted. Finazzo, 323 Mich App at 632-633. A possessor of premises has been defined as (1) a
person who occupies land with intent to control it, or (2) a person previously occupying land with
intent to control it when no one subsequently occupies the land with intent to control it, or (3) a
person entitled to immediate occupation of the land if no other person possesses the land under (1)
or (2). Merritt v Nickelson, 407 Mich 544, 552; 287 NW2d 178 (1980). “[P]ossession for purposes
of premises liability does not turn on a theoretical or impending right of possession, but instead
depends on the actual exercise of dominion and control over the property.” Kubczak v Chemical
Bank & Trust Co, 456 Mich 653, 661; 575 NW2d 745 (1998).
In this case, Oerlikon did not possess or control the premises at the time of plaintiff’s
accident. Oerlikon was to be a future tenant of the building that was under construction; Oerlikon
had signed a lease agreement with the owner, Kirco-OM, but the term of the lease did not begin
until April 2018, more than four months after plaintiff’s accident. Oerlikon’s project manager was
regularly at the construction site to monitor the progress of the project, but used a trailer provided
by Kirco Manix, the general contractor and construction manager. The project manager for Kirco
Manix agreed that Oerlikon had no role or responsibility with respect to supervising or training
workers. A party’s mere presence or performance of limited activities on a parcel of land does not
by itself establish possession and control. See, e.g., Morelli v Madison Heights, 315 Mich App
699, 704; 890 NW2d 878 (2016) (although the defendant regularly mowed the grass on a berm
located in a public right-of-way, he lacked possession of the berm for purposes of premises
liability). In the present case, although Oerlikon had a regular presence at the construction site,
there is no evidence that it possessed and controlled the property during the construction project.
-13-
Therefore, plaintiff may not recover against Oerlikon for premises liability, and Oerlikon therefore
was entitled to summary disposition.
D. DOCKET NO. 355932
In Docket No. 355932, Kirco Manix and Kirco Development contend that the trial court
erred by denying Kirco Manix summary disposition of plaintiff’s claims under the common work
area doctrine and erred by denying Kirco Development summary disposition7 of plaintiff’s claim
of negligence. We agree.
1. KIRCO MANIX
At common law, a general contractor generally could not be held liable for the negligence
of independent subcontractors and their employees. Ormsby v Capital Welding, Inc, 471 Mich 45,
48; 684 NW2d 320 (2004). Our Supreme Court created an exception to this general rule, however,
known as the common work area doctrine. Id. Under the common work area doctrine, a general
contractor can be held liable for the negligence of a subcontractor if the plaintiff proves that (1)
the defendant general contractor failed to take reasonable steps within its supervisory and
coordinating authority, (2) to guard against readily observable and avoidable dangers, (3) thereby
creating a high degree of risk to a significant number of workers, (4) in a common work area. Id.
at 54. Failure to establish any one of the elements of the common work area doctrine is fatal to a
plaintiff’s claim under the doctrine. Id.
In considering the elements of the common work area doctrine, it is necessary to identify
the danger that allegedly created the high degree of risk that the general contractor allegedly had
responsibility to take reasonable steps to guard against. See Latham v Barton Malow Co, 480
Mich 105, 113-114; 746 NW2d 868 (2008). In this case, plaintiff seeks to define the relevant
danger broadly as the mere presence of the overhead power lines at the construction site. However,
the presence of power lines is a common condition. See Groncki, 453 Mich at 661 (opinion by
BRICKLEY, C.J.). And here, the power line involved in plaintiff’s accident was at a proper height
and in good repair. The danger arose only when plaintiff raised a high-reaching conductive tool
under the power lines. Thus, the pertinent danger for the purpose of the common work area
doctrine is not the power line itself but the risk of electrocution from use near the power line of
high-reaching conductive tools or equipment capable of reaching the power lines. See Alderman
v JC Dev Communities, LLC, 486 Mich 906, 906 (2010) (defining the relevant danger as “the risk
of electrocution from a subcontractor’s crane coming into contact with power lines above the
construction site”).
Having identified the alleged danger, we conclude that plaintiff failed to establish a genuine
issue of material fact regarding the third element, i.e., that the danger created a high degree of risk
7
Although Kirco Manix and Kirco Development moved for summary disposition under MCR
2.116(C)(8) and (10), the motion was based in part on evidence outside the pleadings, and the
record suggests that the trial court considered evidence outside the pleadings when ruling on the
motion. We therefore review the trial court’s ruling as one under MCR 2.116(C)(10). See
Cuddington, 298 Mich App at 270.
-14-
to a significant number of workers. There is no evidence that anyone other than plaintiff raised a
bull float into the air under the power lines. But even assuming that another Merlo employee could
have faced the same danger as plaintiff, there is no evidence that any employees of any
subcontractors other than Merlo were using high-reaching conductive tools or equipment capable
of reaching the overhead power lines. The Carnwath incident occurred seven months earlier under
a different span of power lines on a different part of the property, the worker was not injured, and
there is no evidence that conductive tools or equipment were used by Carnwath. Overall, there is
no evidence that any workers other than plaintiff and perhaps another Merlo employee were
exposed to the risk of electrocution from the use of high-reaching conductive tools or equipment
capable of reaching the power lines. The evidence thus fails to show a high degree of risk to a
significant number of workers. See Alderman, 486 Mich at 906. Because plaintiff cannot
demonstrate a genuine issue of material fact regarding the third element, his claim under the
common work area doctrine fails, and it is unnecessary to consider the other elements.
We observe, however, that plaintiff also failed to establish a genuine issue of material fact
regarding the fourth element, i.e., that the dangerous condition was in a common work area. The
common work area doctrine is meant “to distinguish between a situation where employees of a
subcontractor were working on a unique project in isolation from other workers and a situation
where employees of a number of subcontractors were all subject to the same risk or hazard.”
Ormsby, 471 Mich at 57 n 9 (quotation marks and citation omitted). The relevant danger here was
the risk of electrocution arising from the use of long conductive tools or equipment capable of
reaching the overhead power lines near the street. Plaintiff has presented no evidence that any
subcontractor other than Merlo was using such tools or equipment, nor is there evidence that any
subcontractors other than Merlo were working in the area of the driveway during the period that
Merlo was working there. Merlo was pouring and smoothing concrete for the driveway approach;
this appears to have been a unique project performed by Merlo employees in isolation from other
workers, at some distance from the building under construction. Because plaintiff did not establish
that employees of a number of subcontractors were subject to the same risk or hazard, he failed to
establish that the alleged danger existed in a common work area.
Finally, we conclude that plaintiff failed to establish a genuine issue of material fact
regarding the first element, i.e., that Kirco Manix failed to take reasonable steps within its
supervisory and coordinating authority to guard against the risk or hazard. The evidence reflects
that Kirco Manix took numerous reasonable steps to protect against the danger, including asking
DTE to insulate the lines, holding mandatory safety-orientation meetings with every employee of
every subcontractor during which the overhead power lines were discussed, placing posters on the
Kirco Manix trailer where the safety-orientation meetings were held, providing notice of the power
lines and the MIOSHA requirement to maintain a 10-foot distance from the lines, placing multiple
warning signs on the site regarding the power lines, and providing a Kirco Manix safety handbook
and pamphlet to every employee of every subcontractor.
Plaintiff does not dispute that Kirco Manix took steps to address the danger, but argues that
Kirco Manix should have been done more, including an additional meeting between Kirco Manix
and Merlo and replacing the warning sign that had blown over near the site of plaintiff’s accident.
However, Kirco Manix would have been required to take reasonable steps to address the danger;
the fact that more could have been done when viewed in hindsight does not alter the fact that Kirco
-15-
Manix took reasonable steps. Kirco Manix is thus entitled to summary disposition of plaintiff’s
claim under the common work area doctrine.8
2. KIRCO DEVELOPMENT
Kirco Manix and Kirco Development also contend that the trial court erred by denying
Kirco Development summary disposition of plaintiff’s claim of negligence. We agree. Plaintiff
alleged no basis to conclude that Kirco Development owed a legal duty to plaintiff. Plaintiff relies
on events occurring remote in time from his accident. For example, plaintiff asserts that Kirco
Development was the original purchaser of the property, but offers no explanation regarding the
relevance of this point to the question of duty. It is undisputed that Kirco-OM, which ultimately
was dismissed by stipulation of the parties, was the owner of the property at the time of the
construction project. Although plaintiff asserts that Kirco Development participated in
preconstruction design decisions, there is no evidence that Kirco Development played a direct role
in the construction project or possessed authority to make decisions with respect to construction-
site safety.
Further, there is no basis to conclude that plaintiff’s accident was foreseeable to Kirco
Development. As discussed regarding DTE and Oerlikon, Kirco Development likewise had no
reason to anticipate that Merlo would supply its employees with conductive-handled bull floats to
use in proximity to overhead power lines, in violation of a MIOSHA regulation, or that plaintiff
would unnecessarily raise a 23½-foot conductive-handled bull float vertically into the air under
the overhead power lines of which he was admittedly aware. Kirco Development thus owed no
legal duty to plaintiff, and therefore is entitled to summary disposition on plaintiff’s negligence
claim. See Hill, 492 Mich at 660-661.
E. DOCKET NO. 356542
In Docket No. 356542, NSRC and Streb argue that the trial court erred by denying their
motion for summary disposition of plaintiff’s claim of negligence. We agree. At the time of
plaintiff’s accident, NSRC had contracted to act as a safety consultant for Merlo. Christopher
Streb is the principle of NSRC. The extent of NSRC and Streb’s undertaking was limited to certain
specific safety-consulting services that Merlo could request and use as it wished. The parties do
not dispute that Merlo did not inform NSRC and Streb of the Oerlikon site or request safety-
consulting services specific to that site. Streb testified that Merlo did not inform him about its
contract with Kirco Manix or about Merlo’s work on the Oerlikon construction project until after
plaintiff was injured. Merlo did not contact Streb about conducting a site-specific safety audit of
8
Plaintiff contends that his second amended complaint included a claim of active negligence
against Kirco Manix. Our review of the second amended complaint reveals no claim of active
negligence against Kirco Manix, and our review of the record reveals no evidence that would
support that claim. Plaintiff’s theory of negligence pertains to Kirco Manix’s broad supervisory
role as general contractor for the construction project, not to any specific tasks performed by Kirco
Manix as part of the project and that would give rise to a duty of due care.
-16-
the Oerlikon construction site, and NSRC thus did not inspect the Oerlikon site before plaintiff’s
accident. Plaintiff’s accident therefore was not foreseeable to NSRC and Streb, and NSRC and
Streb did not owe a legal duty to plaintiff in connection with his accident. Plaintiff suggests that
NSRC and Streb should have ensured that Merlo supply its employees with nonconductive-
handled bull floats to use in proximity to overhead power lines. However, NSRC and Streb lacked
the ability to advise Merlo about the appropriate tools to use at a worksite that they did not know
existed. Given these circumstances, NSRC and Streb could not reasonably have foreseen
plaintiff’s accident.
Plaintiff further argues he had a special relationship with NSRC and Streb and that they
thus owed a duty to protect him, but cites no authority establishing that a special relationship exists
between a safety-consulting company and an employee of the company’s client. Plaintiff did not
entrust himself to the control and protection of NSRC, nor did Merlo entrust its workforce at the
Oerlikon worksite to NSRC. See Bailey, 494 Mich at 604. Merlo did not tell NSRC about the
Oerlikon worksite or ask for site-specific safety services for the Oerlikon worksite. NSRC thus
had no ability to advise Merlo about the hazards specific to that site or the appropriate tools to use
in light of those hazards. Because NSRC and Streb did not owe a legal duty to plaintiff, they are
entitled to summary disposition of plaintiff’s negligence claim. See Hill, 492 Mich at 660.
In each consolidated case, we reverse the trial court’s order denying the respective
defendants summary disposition and remand to the trial court for entry of summary disposition for
the respective defendants. We do not retain jurisdiction.
/s/ Michael F. Gadola
/s/ Mark J. Cavanagh
/s/ Kirsten Frank Kelly
-17-