These consolidated appeals, arising out of the decision of an administrative regulatory agency to adjust a public utility company’s rates because of a finding of imprudent sales of generating capacity, raise questions about the standard of judicial review and the substantiality of the evidence supporting the agency’s
I
The present proceedings have their origins in a 1985 application for approval of amended rate schedules for 1988 that CL&P filed with the DPUC pursuant to Gen
On August 7,1987, CL&P filed the present application for approval of amended rate schedules with the DPUC. A primary issue in the ensuing proceedings was the manner in which the large costs of the Millstone III nuclear power plant would be allocated between CL&P’s stockholders and customers. In addressing this issue, the DPUC for the first time applied § 16-19aa
The DPUC conducted two alternate forms of analysis with respect to CL&P’s excess capacity sales. In one analysis, conducted pursuant to § 16-19aa and Part III of the Settlement Agreements (the excess capacity analysis), the DPUC determined that CL&P had “excess capacity” of 254 megawatts on its system. The DPUC concluded that if it were to adjust CL&P’s rates accordingly, it would have excluded $12,741,220 in costs associated with the 254 megawatts of “excess capacity.” In its alternative analysis (the capacity sales analysis),6 the DPUC concluded that CL&P’s increased sales of short-term capacity were made “with the obvious intent of avoiding excess capacity adjustments to this rate application,” that CL&P had sold the capacity in question at prices that were “much less than was possible,” and that “choosing to sell only the cheapest units for short periods was not a reasonable and prudent decision.” Choosing the capacity sales analysis as
CL&P’s appeal to the trial court challenged both the excess capacity and capacity sales analyses. Following the DPUC’s denial of its petition for reconsideration of the excess capacity analysis, the OCC also appealed to the Superior Court, challenging only the excess capacity analysis. The trial court consolidated the appeals, and dismissed them both on the ground that the DPUC rate order was neither unjust nor unreasonable.
In its appeal to this court, CL&P contends that the trial court invoked too restrictive a standard of review, and that, on proper examination, the DPUC rate order cannot be sustained on either the excess capacity analysis or the capacity sales analysis. The OCC’s appeal challenges the former analysis only. We conclude that the judgment of the trial court on CL&P’s appeal must be sustained because the DPUC’s decision to exclude $17,542,000 from CL&P’s rates in accordance with its capacity sales analysis was supported by substantial evidence.8
II
The first issue raised by CL&P’s appeal is whether the trial court applied the correct standard of review in rejecting its challenge to the substantive merits of the decision of the DPUC. Pursuant to General Statutes § 16-35, the provisions of General Statutes § 4-183 of the Uniform Administrative Procedure Act determine the scope of judicial review for administrative appeals
The issue before the Supreme Court of the United States in Hope was the interpretation of § 4 (a) of the federal Natural Gas Act of 1938, 52 Stat. 821,15 U.S.C. § 717, which provides that gas rates “shall be just and
CL&P argues that because it has not raised a constitutional confiscation claim in this case, the trial court erred in applying the Hope test.11 CL&P correctly notes that, in Woodbury, this court applied the Hope test solely to a party’s claim that the rates in question were confiscatory. In response, the DPUC and the OCC maintain that General Statutes § 16-19e (a) (4)12 embod
It is true that § 16-19e (a) (4), in identifying the various factors that the DPUC must consider when it establishes rates for public service companies, uses language that tracks, almost verbatim, the language that the United States Supreme Court used in Hope when it interpreted the “just and reasonable” requirement under the Natural Gas Act and the federal constitution. Indeed, the legislative history of § 16-19e (a) (4) reveals that its drafters perceived the Hope decision as controlling with respect to the federal constitutional validity of rate orders. Conn. Joint Standing Committee Hearings, Regulated Activities, Pt. 2, 1975 Sess., p. 724. Neither the language of § 16-19e (a) (4) itself, nor its legislative history, however, indicates that the section was intended to establish an independent standard, apart from § 4-183 (g), for judicial review of DPUC rate orders. To the contrary, General Statutes
We conclude, therefore, that § 16-19e (a) (4) does not permit a court to sustain a rate order solely on the basis of a determination that the rate is “just and reasonable” and generally supported by record evidence. Similarly, § 16-19e (a) (4) does not express the sole standard for a reviewing court’s determination of whether a regulated company’s “substantial rights” have been prejudiced. Under the appropriate standard set out in § 4-183 (g), courts must undertake a case-by-case analysis to determine the merits of the challenged rate order and the prejudice, if any, to the regulated company. See, e.g., Connecticut Natural Gas Corporation v. Public Utilities Control Authority, supra, 139-40 (reliance on extra-record evidence for important facts demonstrates substantial prejudice); Madow v. Muzio, 176 Conn. 374, 382, 407 A.2d 997 (1978) (no substantial prejudice when, even after erroneously admitted evidence stricken from record, sufficient evidence remains to support agency conclusion); accord Lawrence v. Kozlowski, 171 Conn. 705, 714-15, 372 A.2d 110 (1976), cert. denied, 431 U.S. 969, 97 S. Ct. 2930, 53 L. Ed. 2d 1066 (1977).
There is room for incorporation of § 16-19e (a) (4) criteria within the frame of reference for judicial review established by § 4-183 (g). The latter section specifically
In this appeal, CL&P asserts that the rate order excluding $17.5 million from its rates pursuant to the DPUC’s capacity sales analysis deprived it of its operating expenses under § 16-19e (a) (4). In elaborating upon this claim, however, CL&P argues that the exclusion can only be sustained if the DPUC was correct, as a legal and factual matter, in its finding that CL&P’s capacity sales decision was not prudent. The gravamen, then, of CL&P’s complaint is not that the DPUC’s decision violates § 16-19e (a) (4), but rather that it reflects the application of an incorrect legal standard for deter
We would normally remand a case such as this one to the court with instructions to conduct a new review pursuant to the proper standard. Nonetheless, because the administrative record before us on appeal is identical to that which was before the trial court, the interests of judicial economy would not be served by a remand in this case. We therefore review CL&P’s claims directly. We consider the substantial evidence issue first, and then examine the prudence standard issue.
Ill
A
Judicial review of an administrative agency decision requires a court to determine whether there is substantial evidence in the administrative record to support the agency’s findings of basic fact and whether the conclusions drawn from those facts are reasonable. Campisi v. Liquor Control Commission, 175 Conn. 295, 296, 397 A.2d 1365 (1978); Almada v. Administrator, 137 Conn. 380, 391-92, 77 A.2d 765 (1951). “Substantial evidence” exists if the administrative record affords “ ‘ “a substantial basis of fact from which the fact in
To support its conclusion that CL&P had engaged in imprudent sales of generating capacity, the DPUC made three crucial determinations: that a market existed for more expensive intermediate and baseload capacity; that CL&P should have sold such capacity instead of the short-term, peaking capacity that it actually sold; and that CL&P’s sales evidenced a lack of good faith. Our review of the administrative record discloses substantial evidence to support these administrative findings.16
The evidence also establishes that a market for capacity sales existed. Regional utilities such as Boston Edison, Central Maine Power, Commonwealth Electric, Public Service of New Hampshire and others needed to purchase capacity in order to satisfy their capability responsibility requirements. Boston Edison alone
The evidence farther establishes that during the years 1978 through 1986, CL&P had sold, on average, 125 MW of short-term capacity per year. In 1987, these sales increased dramatically. CL&P executed three capacity sales contracts on March 1, 1987, three on May 1, 1987, and six on November 1, 1987. As of March, 1987, CL&P had projected short-term sales of 625 MW for the summer of 1988. In July, 1987, CL&P revised this figure to 635 MW. As of November, 1987, CL&P had again revised that figure to 1173 MW. These capacity sales were made for an average price of $44/kw-year.
The DPUC concluded that CL&P had greatly increased its capacity sales in an effort to avoid an excess capacity charge of nearly $150/kw-year under § 16-19aa. CL&P does not contest the finding that its short-term sales greatly increased in 1987. It asserts, simply, that the coming on-line of Millstone III in 1986 “freed up” other capacity for sale. The DPUC counters, however, that while Millstone III may explain the existence of greater capacity, it does not explain, or justify, CL&P’s decision to sell the amount and type of capacity that it actually sold. CL&P’s large reserve margin of 45 to 50 percent, coupled with other utilities’ need to purchase capacity to meet their reserve requirements, meant that CL&P had significant leverage to control the amount and type of capacity it could sell and the price it could receive for its capacity sales.
CL&P proffers three arguments to rebut the conclusion reached by the DPUC. It maintains that NEPOOL regulations, the Federal Energy Regulatory Commission (FERC) and managerial prudence dictated the nature of its capacity sales. We are unpersuaded by these arguments.
CL&P argues, first, that NEPOOL regulations created a “cap” upon the price that could be obtained for capacity and that it could not, therefore, have sold capacity at prices greater than it actually did. CL&P bases this argument in part on testimony given in 1989, nearly two years after the close of the administrative proceedings that led to this appeal and, therefore, not before the DPUC at the time it rendered its decision. CL&P also relies on the testimony of its own expert witness, which the DPUC was free to disregard. See Huck v. Inland Wetlands & Watercourses Agency, supra, 540-41.
CL&P’s second argument invokes rules laid down by the FERC, which has jurisdiction over interstate capacity sales, that purportedly limit the price of such sales to the utility company’s embedded cost, i.e., original cost less depreciation, or “net book cost,” of the capacity sold. This limit, according to CL&P, prevented it from charging a greater price for the short-term, peaking capacity that it had sold. As the DPUC correctly observes, however, even if the FERC would have limited the price CL&P could have received for its capacity sales to the embedded cost of capacity sold, CL&P could have elected to sell Millstone III capacity, which has high embedded costs.
Because the DPUC, in evaluating the evidence before it, brought to bear its expertise, technical competence and specialized knowledge; General Statutes § 4-178; Success Village Apartments, Inc. v. Local 376, 175 Conn. 165, 170, 397 A.2d 85 (1978); its interpretation of the evidence must be sustained unless its conclusions are unreasonable. Administrative conclusions are not unreasonable simply because the evidence admits of multiple, possibly inconsistent, conclusions. See National Labor Relations Board v. Nevada Consolidated Copper Corporation, 316 U.S. 105, 106, 62 S. Ct. 960, 86 L. Ed. 1305 (1942). Having examined the record and found substantial evidence to support the basic facts from which the DPUC in this case could have drawn its conclusions, we conclude that its determinations of fact and law pass the test of reasonableness.
B
General Statutes § 16-19e (a) (5)18 requires the DPUC to ensure “that the level and structure of rates charged
In the DPUC’s capacity sales analysis, pursuant to which it made the determination of CL&P managerial imprudence, the DPUC did not charge CL&P with imprudence in building excess capacity, or in its decision to sell per se. Instead, the focus of the DPUC was on the “timing, the quantity and the price of the sales of capacity in question.” The DPUC concluded that by its sudden increase in sales of inexpensive peaking capacity, CL&P sought to avoid the excess capacity adjustment under § 16-19aa and that, therefore, the sales decision was not made in good faith. Similarly, the DPUC concluded that a market for long-term, more expensive intermediate and baseload capacity existed at the time of CL&P’s capacity sales, that CL&P management could or should have known of the existence of that market, and that CL&P acted unreasonably in failing to sell capacity to that market. On these findings of lack of good faith and unreasonableness, the DPUC charged CL&P with managerial imprudence.
CL&P argues that the DPUC’s conclusion of imprudence cannot be sustained because the DPUC applied an incorrect standard when it determined that the capacity sales in question were imprudent. Since CL&P does not challenge the appropriateness of the prudence
C
In its capacity sales analysis, the DPUC adopted $89/kw, the replacement cost of peaking capacity,19 as the standard for determining the $17.5 million exclusion for the unreasonably low compensation that CL&P received for its capacity sales. The DPUC multiplied the volume of CL&P’s capacity sales during the relevant time period, less certain deductions, by the difference between the $89/kw standard and the average $44/kw that CL&P actually received for its sales of short-term, peaking capacity.
CL&P contests the $89/kw standard, arguing that it is unsupported by substantial evidence in the record. CL&P’s argument misconstrues the method by which the DPUC adopted that standard. The DPUC does not maintain that CL&P could, or should, have sold all of its capacity for $89/kw. Instead, the standard represents the DPUC’s attempt to establish a reasonable compensation standard for adjusting CL&P’s rates once it had determined that CL&P had acted imprudently. The DPUC defends the reasonableness of the $89/kw standard, arguing that peaking capacity is the
Viewing the administrative record in its entirety, we are not persuaded that, in this particular case, the adoption of an $89/kw standard is unreasonable. We therefore hold that the DPUC’s decision to exclude $17.5 million from CL&P’s rates must be sustained.
The judgments are affirmed.
In this opinion the other justices concurred.
1.
The plaintiff is an electric public service company, under General Statutes § 16-1 (a) (4), which defines “fpjublic service company” to include “electric . . . companies, owning, leasing, maintaining, operating, managing or controlling plants or parts of plants or equipment . . . .”
2.
General Statutes § 16-2a designates the office of consumer counsel as the “advocate for consumer interests in all matters which may affect Connecticut consumers with respect to public service companies.” Section 16-2a authorizes the OCC to “appear in and participate in any regulatory or judicial proceedings, federal or state, in which such interests of Connecticut consumers may be involved, or in which matters affecting utility services rendered or to be rendered in this state may be involved.” Accordingly, the DPUC had designated the OCC as a party to the CL&P rate increase hearings in this case.
3.
In addition to the OCC, the DPUC also designated its prosecutorial division, the Connecticut siting counsel and other state agencies as additional parties. Only CL&P, the OCC and the DPUC are parties to these appeals.
4.
General Statutes § 16-19aa provides in relevant part: “excess generating CAPACITY. EXCLUSION OF COSTS ASSOCIATED with, (a) During each proceeding on a rate amendment under section 16-19 proposed by an electric public service company, as defined in section 16-1, having more than seventy-five thousand customers, the department of public utility control shall (1) review the facilities utilized by the company for the generation and transmission of electricity, (2) determine the level of the company’s reserve capacity, (3) determine the level of reserve capacity which would provide a net economic benefit to customers of the company, provided the department shall also consider the New England Power Pool reliability standard, the state energy policy as stated in section 16a-35k and any other factors which the department deems appropriate and adjust such level accordingly and (4) exclude from the company’s rates, in a manner which shall provide the optimal short-term and long-term benefits to customers of the company, the costs associated with generating facilities which provide reserve capacity in excess of the level, including any adjustments, determined by the department under subdivision (3) of this section.”
5.
Electrical generating capacity is classified according to the characteristics of the generating unit that produces it. Baseload units, such as nuclear power and coal-powered plants, have high capital costs but very low fuel, or variable, costs and are designed to run as many hours per year as possible to distribute their costs over the largest number of generation hours. Peaking units, such as gas turbines, have very low capital costs but high fuel costs. These units are typically run infrequently during the year, such as when heavy electrical demand exists. In between base load and peaking units are oil-fired, intermediate units.
6.
The DPUC conducted its capacity sales analysis pursuant to its statutory mandate in General Statutes § 16-19e (a) (5) to ensure that the level and structure of rates charged utility customers reflect prudent and efficient management. See footnote 18, infra.
7.
The DPUC reserved the right to invoke either analysis in subsequent cases.
8.
Because we affirm the trial court’s judgment sustaining the DPUC’s capacity sales analysis, we do not consider the claims raised by CL&P and the OCC regarding the DPUC’s excess capacity analysis.
9.
General Statutes (Rev. to 1989) § 4-183 (g) provides: “The court shall not substitute its judgment for that of the agency as to the weight of the evidence on questions of fact. The court may affirm the decisions of the agency or remand the case for further proceedings. The court may reverse or modify the decision if substantial rights of the appellant have been prejudiced because the administrative findings, inferences, conclusions, or decisions are: (1) In violation of constitutional or statutory provisions; (2) in excess of the statutory authority of the agency; (3) made upon unlawful procedure; (4) affected by other error of law; (5) clearly erroneous in view of the reliable, probative, and substantial evidence on the whole record; or (6) arbitrary or capricious or characterized by abuse of discretion or clearly unwarranted exercise of discretion.”
10.
The court also stated, without any elaboration, that the record supported the DPUC’s decision as “logical and rational.” See footnote 14, infra.
11.
CL&P’s initial administrative appeal to the Superior Court raised various constitutional claims. CL&P has not, however, pursued any of those claims in this appeal and we do not, therefore, consider them.
12.
General Statutes § 16-19e (a) provides in relevant part: “In the exercise of its powers under the provisions of this title, the department of public utility control shall examine and regulate the transfer of existing assets and franchises, the expansion of the plant and equipment of existing public service companies, the operations and internal workings of public service companies and the establishment of the level and structure of rates in accordance with the following principles . . . (4) that the level and structure of rates be sufficient, but no more than sufficient, to allow public service companies to cover their operating and capital costs, to attract needed capital and to maintain their financial integrity, and yet provide appropriate protection to the relevant public interests, both existing and foreseeable .. . .”
13.
In order to facilitate judicial review, an appellant seeking review of a rate order on the ground that it violates General Statutes § 16-19e (a) (4) should do more than merely assert such a claim. The appellant should articulate, with particularity, how the rate order in question fails to comport with the specified factors in § 16-19e (a) (4). The appellant should also distinguish the claim that a rate order violates § 16-19e (a) (4) from other grounds on which the rate order is challenged, such as whether the order is supported by substantial evidence.
14.
We recognize that in its memorandum of decision, the court did find that the record supported the DPUC’s decision as logical and rational. This may be an indication that the court concluded that the decision was neither arbitrary or capricious. See Woodbury Water Co. v. Public Utilities Commission, 174 Conn. 258, 263, 386 A.2d 232 (1978). In the absence of any elaboration upon the court’s summary statement, however, we cannot determine whether the court properly conducted its review of the DPUC’s decision pursuant to General Statutes § 4-183 (g).
15.
Typically, following our review of an administrative record to determine whether substantial evidence exists to support an agency’s decision, we would state only whether we had concluded that such evidence exists. Generally, in such decisions, the substantial evidence question is only one of numerous issues raised in an administrative appeal. Because the core of this case, however, is the substantial evidence issue, the discussion that follows is more elaborate than usual.
16.
The DPUC’s written decision in this case clearly states the agency’s conclusions with respect to the capacity sales analysis. The decision does not, however, contain any express findings of basic fact pertaining to that analysis. We, therefore, find it necessary to examine the record ourselves
17.
In order to provide for unexpected demand or temporary loss of generating units, utilities are required to have generating capacity beyond their expected peak demand, the maximum demand experienced by a utility as a result of retail customer power requirements. This additional capacity is referred to as a reserve margin, or requirement. See Madison Gas & Electric Co. v. Public Service Commission of Wisconsin, 109 Wis. 2d 127, 131 nn.6-7, 325 N.W.2d 339 (1982).
18.
General Statutes § 16-19e (a) (5) provides: “In the exercise of its powers under the provisions of this title, the department of public utility control
19.
NEPOOL and CL&P agreed with the DPUC that $89/kw represented the replacement cost of peaking capacity. CL&P did not agree, however, that the $89/kw figure was the appropriate one to use in calculating the rate exclusion.