[PUBLISH]
IN THE UNITED STATES COURT OF APPEALS
FILED
FOR THE ELEVENTH CIRCUIT U.S. COURT OF APPEALS
________________________ ELEVENTH CIRCUIT
SEPTEMBER 30, 2009
No. 08-10983 THOMAS K. KAHN
CLERK
________________________
D. C. Docket No. 07-00071-CV-FTM-29-DNF
ALAN STEIN,
KAREN STEIN,
Plaintiffs-
Counter-Defendants-
Counter-Claimants-
Appellees,
versus
PARADIGM MIRASOL, LLC,
a Florida limited liability company,
Defendant-
Counter-Claimant-
Counter-Defendant-
Appellant.
________________________
Appeal from the United States District Court
for the Middle District of Florida
_________________________
(September 30, 2009)
Before TJOFLAT and CARNES, Circuit Judges, and HOOD,* District Judge.
CARNES, Circuit Judge:
In a market-based economy the price of housing, like other goods, is subject
to swings. There was a sharp upward swing in housing prices between late 2000
and the end of 2005, and the resulting bubble was bigger in Florida than it was in
most other states. Home prices there rose eighty-two percent in absolute terms
during that short period, outstripping the national increase by thirty-one percent.
See Gabriel Montes Rojas et al., The Florida Housing Boom, 3 Fla. Focus 1, 2
(2007). All bubbles eventually burst, as this one did. The bigger the bubble, the
bigger the pop. The bigger the pop, the bigger the losses. And the bigger the
losses, the more likely litigation will ensue. Hence this case.
I.
On March 9, 2005, Alan and Karen Stein signed a contract with Paradigm
Mirasol, LLC to purchase for $895,900 a condominium unit in Mirasol I, a six-
story condominium building that was being developed in a luxury resort
community near Fort Myers, Florida. The Steins made a down payment of
$205,370, which included a deposit of $179,180 and an additional payment of
*
Honorable Joseph M. Hood, United States District Court for the Eastern District of
Kentucky, sitting by designation.
2
$26,190 for upgrades. The contract specified that time was of the essence and that
the condominium would be built within two years, although the contract included a
force majeure provision that allowed for delays under certain circumstances. The
contract also specifically waived the Steins’ right to speculative, punitive, and
special damages. As a result, if Paradigm breached the contract the remedies
available to the Steins were limited; they could choose specific performance or
they could get back their deposit with interest and any actual damages.
After the housing bubble burst, the Steins had second thoughts about their
decision to purchase the condominium unit. Wanting out of their contract, they
seized on to the Interstate Land Sales Full Disclosure Act, 15 U.S.C. § 1701 et seq,
a federal statute that has become an increasingly popular means of channeling
buyer’s remorse into a legal defense to a breach of contract claim. On January 16,
2007, just three weeks before the condominium was completed, the Steins gave
Paradigm written notice that they were terminating the contract because Paradigm
had failed to provide them with a property report as required by the Disclosure Act.
The Steins also demanded that Paradigm return all of the $205,370 they had paid.
Paradigm refused, contending that the contract between the parties fits within the
exemption set out in the Act for “the sale or lease of any improved land on which
there is a residential, commercial, condominium, or industrial building, or the sale
3
or lease of land under a contract obligating the seller or lessor to erect such a
building thereon within a period of two years.” See 15 U.S.C. § 1702(a)(2).
Paradigm did complete construction of the condominium building and the
Stein’s unit in two years, as it had contracted to do. On February 8, 2007, twenty-
three months after the contract was signed, Paradigm provided the Steins with a
notice of issuance of the Certificate of Occupancy. That same day, the Steins filed
a complaint in district court, alleging that Paradigm had violated the Disclosure
Act and seeking to revoke the contract and to recover damages and attorney’s fees.1
Undeterred, Paradigm attempted to schedule a closing date of February 20, 2007,
which would have been within the two-year completion period. The Steins refused
to close. Paradigm filed a counterclaim seeking to retain the Steins’ deposit as
liquidated damages.
The parties agreed that the material facts were undisputed and filed cross-
motions for summary judgment. The district court granted summary judgment in
favor of the Steins, allowing them to terminate the contract and requiring Paradigm
to return all of the money the Steins had paid it. The court held that the contract’s
force majeure clause fatally undermined Paradigm’s obligation to complete
1
The complaint also alleged a state law claim for conversion based on Paradigm’s
refusal to return the deposits.
4
construction within two years because the scope of that clause extended beyond
events the law would recognize as establishing impossibility of performance.
Additionally, the court held that Paradigm could not claim the two-year completion
exemption because the contractual provision barring special damages rendered
Paradigm’s obligation to construct the condominium “illusory.” This is
Paradigm’s appeal.
II.
This case turns on whether the contract is exempt from the requirements of
the Interstate Land Sales Full Disclosure Act. See 15 U.S.C. § 1702(a)(2). If, as
the district court concluded, the contract is not exempt, the Steins are entitled to the
judgment they received. If the contract is exempt, Paradigm is entitled to a
judgment in its favor. With the judgment goes the money the Steins deposited with
Paradigm.
The Disclosure Act is a consumer protection statute that “was intended to
curb abuses accompanying interstate land sales.” Winter v. Hollingsworth Props.,
Inc., 777 F.2d 1444, 1448 (11th Cir. 1985). Although its primary purpose is to
“protect purchasers from unscrupulous sales of undeveloped home sites,” id. at
1447, it also applies to the sale of developed land, including the sale of
condominiums, id. at 1449. The Act “utiliz[es] disclosure as its primary tool” to
5
discourage fraud. Id. at 1447. It requires developers selling or leasing property to
provide the purchaser with a property report before the sales contract is signed.
See 15 U.S.C. § 1703(a)(1)(B). If the developer fails to provide a property report,
the purchaser generally has the right to revoke the contract. Id. § 1703(c).
Paradigm did not provide the Steins with the property report.
The Disclosure Act does include a list of exemptions from its requirements.
See id. § 1702(a). The one at the center of this case is the exemption that applies to
“the sale or lease . . . of land under a contract obligating the seller or lessor to erect
. . . a [condominium] building thereon within a period of two years.” Id. §
1702(a)(2). The dispute is over the meaning of the word “obligating.” The
contract provided that Paradigm would complete construction of the Steins’
condominium within two years and Paradigm actually did so. But was the contract
one “obligating” Paradigm to do so within the meaning of the exemption provision
in § 1702(a)(2) of the Disclosure Act? That is the $64,000 question, or more
accurately, the $205,370 question in this case.
Deciding whether the contract in this case fits within the § 1702(a)(2)
exemption requires that we look to both federal and state law. Because the
Disclosure Act is a federal statute its interpretation is a matter of federal law, Caley
v. Gulfstream Aerospace Corp., 428 F.3d 1359, 1369 n.9 (11th Cir. 2005), so we
6
will use principles of statutory interpretation from federal decisions to construe the
term “obligating.” We must also look to state contract law to see what remedies
the Steins would have under the contract if Paradigm had not constructed the
condominium within the two-year period specified in the § 1702(a)(2) exemption.
See Markowitz v. Ne. Land Co., 906 F.2d 100, 105 (3d Cir. 1990). Florida law
will inform us about the extent and nature of Paradigm’s legally enforceable
obligation to fulfill its contractual promise to complete construction within two
years.
We begin our federal law analysis by looking to the text of the Disclosure
Act. See Harris v. Garner, 216 F.3d 970, 972 (11th Cir. 2000) (en banc) (“[C]ourts
should always begin the process of legislative interpretation . . . with the words of
the statutory provision.”); United States v. Steele, 147 F.3d 1316, 1318 (11th Cir.
1998) (“In construing a statute we must begin . . . with the language of the statute
itself.” (quotation marks omitted)). Although the Act defines some terms, neither
the word “obligating” nor its variants “obligate” and “obligated” are among them.
A term that is undefined in a statute carries its ordinary meaning. Crawford v.
Metro. Gov’t of Nashville & Davidson County, __ U.S. ___, 129 S. Ct. 846, 850
(2009); Perrin v. United States, 444 U.S. 37, 42, 100 S. Ct. 311, 314 (1979).
The ordinary meaning of the word “obligating” is: binding by legal or moral
7
duty. See Merriam-Webster Online Dictionary, http://www.merriam-webster.com
(last visited Sept. 30, 2009) (defining “obligate” as “to bind legally or morally” and
“obligation” as “something one is bound to do”); American Heritage Dictionary
857 (2d College ed. 1982) (defining “obligate” as “[t]o bind, compel, or constrain
by a social, legal, or moral tie”); Oxford English Dictionary Online,
http://dictionary.oed.com (draft rev. 2009) (defining “obligate” as “[t]o bind (a
person) morally” or “[t]o bind (a person) legally”); Random House Unabridged
Dictionary 1336 (2d ed. 1993) (defining “obligate” as “to bind or oblige morally or
legally”); see also Black’s Law Dictionary 1103 (8th ed. 2004) (defining “obligate”
as “[t]o bind by legal or moral duty”).2 Federal statutes, generally speaking,
concern themselves with legal instead of moral duties, and the Disclosure Act is no
exception.
Given the context and the ordinary meaning of “obligating,” the §
1702(a)(2) exemption applies when a contract imposes a legal duty on the
developer to perform his promise to construct the condominium or other building
within two years. The nature and extent of the duty a contract imposes, however,
is a matter of state contract law. See Norfolk & W. Ry. Co. v. Am. Train
Dispatchers Ass’n, 499 U.S. 117, 129, 111 S. Ct. 1156, 1164 (1991) (“The
2
Copies of the internet materials cited in this opinion are on file in the Clerk’s Office.
See 11th Cir. R. 36, I.O.P. 10.
8
obligation of a contract is the law which binds the parties to perform their
agreement.” (citation and internal quotation marks omitted)); Sturges v.
Crowninshield, 17 U.S. (4 Wheat.) 122, 197 (1819) (Marshall, C.J.) (“A contract is
an agreement, in which a party undertakes to do, or not to do, a particular thing.
The law binds him to perform his undertaking, and this is, of course, the obligation
of his contract.”). A legal duty, contractual or otherwise, is one that the law will
require a party to perform, or to pay for not performing, by bringing to bear public
force. See Am. Banana Co. v. United Fruit Co., 213 U.S. 347, 356, 29 S. Ct. 511,
512 (1909) (Holmes, J.) (“Law is a statement of the circumstances, in which the
public force will be brought to bear upon men through the courts.”); Oliver
Wendell Holmes, Jr., The Common Law 40 (M. Howe ed. 1963) (“The law
threatens certain pains if you do certain things, intending thereby to give you a new
motive for not doing them.”).
A.
If it appeared to the Steins that Paradigm was not going to complete
construction within two years, they had available the remedy of specific
performance to force Paradigm to live up to its agreement. Or, if the Steins
preferred, they could have waited until it was too late for Paradigm to finish by the
deadline. At that point their remedy would have been to rescind the contract, get
9
their money back with interest, and recover any actual damages they had suffered.3
The Steins contend that those remedies are not good enough to “obligate”
Paradigm to construct the condominium in two years, as required by § 1702 (a)(2)
of the Disclosure Act. They argue that without the remedies of special,
consequential, punitive, speculative, and indirect damages, which they expressly
waived in the contract, they cannot inflict enough legal pain on Paradigm to force
it to carry out its contractual duty to finish within two years.
Specific performance or injunctive relief, if vigorously pursued, ordinarily
will be enough to force a seller to fulfill its contractual obligations within the time
a contract requires. Florida law provides that a party may sue for specific
performance and obtain an injunction that “shall specify the time within which the
act shall be performed.” Fla. R. Civ. P. 1.570(c); see also Wilson v. Sandstrom,
3
The remedies clause of the contract provided:
If, for any reason other than Seller's failure to make Seller's title marketable,
Seller fails to perform this Agreement and Buyer is not in default of this
Agreement, Buyer may seek specific performance or elect to terminate this
Agreement by written notice to Seller, in which event the deposit shall be
returned to Buyer upon demand, with any interest accrued thereon, and Buyer
may commence an action to recover only actual and direct damages
(out-of-pocket amounts actually paid by Buyer to third parties). Under no
circumstances may Buyer seek or be entitled to recover any special,
consequential, punitive, speculative or indirect damages, all of which Buyer
specifically waives, from Seller for any breach by Seller of its obligation under
this Agreement or any representation, warranty or covenant of Seller hereunder.
(emphasis added).
10
317 So. 2d 732, 736 (Fla. 1975) (“A mandatory temporary injunction may be
issued requiring specific performance of a contract.”). If it had appeared to the
Steins that Paradigm was not moving quickly enough to complete construction
within two years, they could have obtained an injunction to force it to do so.
Failure to comply with the injunction requiring it to finish construction within two
years would have subjected Paradigm to civil and criminal contempt penalties.
Roth v. Roth, 973 So. 2d 580, 592 (Fla. 2d DCA 2008) (recognizing that a party
may be held in contempt “for failing to perform a specific act” required by a
specific performance judgment); Riley v. Riley, 509 So. 2d 1366, 1367–70 (Fla.
5th DCA 1987) (holding that a judgment that “requires the performance of an act”
is enforceable by civil and criminal contempt penalties (emphasis omitted));
Firestone v. Ferguson, 372 So. 2d 490, 492 (Fla. 3d DCA 1979) (holding that a
party may be held in contempt for refusing to comply with a specific performance
judgment requiring the party to sell a piece of real estate).
A court order requiring a party to perform as it promised or face civil and
criminal contempt sanctions obligates the party to keep its contractual promise.
The theory behind injunctive relief, after all, is that parties can be forced to take
action that the law demands. Because Florida law provided the Steins with the
remedy of injunctive relief to force Paradigm to finish construction of the
11
condominium within two years, the contract was one “obligating” Paradigm to do
so.
It might be argued that Paradigm could evade its obligation under the
contract and thwart the specific performance remedy simply by conveying the
property to another purchaser, as it would have had a special incentive to do if the
market value of the property had gone up. It is true that injunctive relief is not
available where the property is conveyed to another purchaser before the injunction
issues. See Samara Dev. Corp. v. Marlow, 556 So. 2d 1097, 1101 (Fla. 1990)
(“Specific performance alone is not sufficient because the developer could sell the
property to a third party in the interim, thereby nullifying the availability of
specific performance.”). In that situation, however, Florida law provides for more
than specific performance, regardless of what the contract says about remedies.
Under Florida law, notwithstanding any contractual limitation of remedies, when
the seller frustrates the buyer’s specific performance right by selling the property
to someone else, the buyer may recover the seller’s entire profit from the sale. See
Seaside Cmty. Dev. Corp. v. Edwards, 573 So. 2d 142, 146–47 (Fla. 1st DCA
1991) (holding that even though the contract limited the buyers’ remedies to
specific performance or a refund of earnest money, they were entitled to damages
in the amount of the difference between the contract price and the fair market value
12
of the property where the seller thwarted the buyers’ right to specific performance
by selling the property to another at a higher price). Thus, Paradigm would not
have been able to deprive the Steins of the benefit of their bargain and take for
itself any increase in the market value of the condominium during the construction
period. Florida law would not permit that, regardless of the contract’s remedies
limitation clause.4
As a result, even with the limitation of remedies clause, the Steins had an
effective remedy to enforce Paradigm’s contractual promise to complete the
construction of the condominium within two years. They could have obtained an
injunction and brought to bear the threat of civil and criminal contempt if Paradigm
was in the process of breaching by not working fast enough. Or if Paradigm had
breached the contract by selling the property to another buyer, the Steins could
have recouped the benefit of their bargain in the form of damages equal to the
difference between their contract price and the fair market value of the property.
That is in addition to the return of their deposit with interest. Insofar as remedies
are concerned, the law would have threatened or inflicted enough pain on
4
Regardless of any breach by Paradigm, the Steins would not have been able to recover
speculative or punitive damages. As the district court pointed out, however, under Florida law
those types of damages are not recoverable for breach of contract anyway. See A.R. Holland,
Inc. v. Wendco Corp., 884 So. 2d 1006, 1008 (Fla. 1st DCA 2004) (speculative damages);
Ferguson Transp., Inc. v. N. Am. Van Lines, Inc., 687 So. 2d 821, 822 (Fla. 1996) (punitive
damages). So for those types of damages, the limitations of remedies clause had no effect.
13
Paradigm for breaching the contract to make the contract one “obligating the seller
or lessor to erect such a building thereon within a period of two years” within the
meaning of § 1702 (a)(2).5
B.
Alternatively, the Steins contend that even if the contract’s limitation of
remedies clause does not take it out of the § 1702 (a)(2) exemption, the force
majeure clause does. That clause provides:
Construction of the condominium unit will be complete and ready for
possession within two (2) years from the execution of this Purchase
Agreement in compliance with the Interstate Land Sales Full
Disclosure Act; provided, however, that Seller shall not be responsible
for any delay caused by acts of God, weather conditions, restrictions
imposed by any governmental agency, labor strikes, material
shortages or other delays beyond the control of the Seller and the
completion and occupancy date shall be extended accordingly.
(emphasis added).
The district court concluded that this force majeure clause rendered “the
apparent obligation [to complete construction in two years] illusory.” As two
examples of what could have happened, the court pointed to a Florida case where
5
The Florida Supreme Court has interpreted the Disclosure Act differently than we do.
See Samara, 556 So. 2d at 1099–1101. Although we respect its views, we are not bound by
Samara’s interpretation even in cases arising in Florida because it is a federal statute we are
interpreting. The Samara Court appears to have applied Florida statutory construction decisions
in arriving at its conclusion. For example, it explicitly applied state law to give “great weight” to
the HUD guidelines, id. at 1099, which is far more weight than we can give them under
Skidmore v. Swift & Co., 323 U.S. 134, 140, 65 S. Ct. 161, 164 (1944). See infra note 6.
14
delay was excused under a similarly worded force majeure clause due to excessive
rain and another one where the president of the development company’s heart
attack was held to be beyond the control of the company for force majeure
purposes. See Devco Dev. Corp. v. Hooker Homes, Inc., 518 So. 2d 922, 923 (Fla.
2d DCA 1987) (excessive rain); Camacho Enters., Inc. v. Better Constr., Inc., 343
So. 2d 1296, 1297 (Fla. 3d DCA 1977) (heart attack). The court then concluded
that the force majeure clause rendered Paradigm’s obligation illusory under the
Disclosure Act because the clause excuses delays that would “not qualify under
Florida’s impossibility of performance principles.” Neither the district court nor
the Steins have explained why the standard of legal impossibility should be the
measure of obligation under the § 1702 (a)(2) exemption—why any force majeure
clause that extends beyond legal impossibility renders a contract non-exempt.6
6
Paradigm argues that the force majeure clause is limited to legal impossibility because
“Florida law construes force majeure clauses to exclude only those delays that are excusable
under the doctrine of impossibility.” To support that contention, Paradigm cites Florida Power
Corp. v. City of Tallahassee, 18 So. 2d 671, 675 (Fla. 1944), but that decision does not shoulder
the proposition. In Florida Power the delay was caused by a hurricane—an act of God. Id. The
court was concerned with only that kind of delay. That does not mean the court was narrowing
the force majeure clause at issue (and all force majeure clauses in all Florida contracts) to cover
only acts of God.
It appears to us that force majeure clauses broader than the scope of impossibility are
enforceable under Florida law. See Devco, 518 So. 2d at 923 (holding that excessive rain
excused delay under the contract’s force majeure clause as a condition outside of the seller’s
control); St. Joe Paper Co. v. State Dep’t of Envtl. Regulation, 371 So. 2d 178, 180 (Fla. 1st
DCA 1979) (implicitly recognizing that a force majeure clause excusing delays for “any cause . .
. not within the reasonable control of the company” was enforceable); Camacho, 343 So. 2d at
1297 (enforcing the contract’s force majeure clause to excuse delay based on the president of the
15
This force majeure clause covers events that may or may not happen, but
whether they do is “beyond the control of the Seller.” This type of clause is not an
opt-out provision; it is limited in scope. See Gen. Injectables & Vaccines, Inc. v.
Gates, 527 F.3d 1375, 1377 (Fed. Cir. 2008) (delays caused by subcontractors are
within the builder’s control and therefore not excused by “beyond the seller’s
control” force majeure clauses); Hutton Contracting Co. v. City of Coffeyville, 487
F.3d 772, 779 (10th Cir. 2007) (same); Stand Energy Corp. v. Cinergy Servs., Inc.,
760 N.E.2d 453, 457 (Ohio Ct. App. 2001) (“Mistaken assumptions about future
events or worsening economic conditions, however, do not qualify as a force
majeure.”). The clause does not make the two-year duty illusory. See Johnson
Enters. of Jacksonville Inc. v. FPL Group, Inc., 162 F.3d 1290, 1311 (11th Cir.
1998) (recognizing the “fundamental principle of contract law” and Florida law
that an obligation is illusory when it “appears on its face to be so insubstantial as to
impose no obligation at all”); Port Largo Club, Inc. v. Warren, 476 So. 2d 1330,
1333 (Fla. 3d DCA 1985) (recognizing that a contractual provision renders an
obligation “illusory” when it allows a party “to breach with impunity”). Nor does
the clause make the two-year duty subject to the seller’s discretion. Events beyond
a party’s control are, by definition, not in its discretion.
development company’s heart attack as a circumstance “beyond the control” of the developer).
We proceed with that understanding.
16
The two examples that concerned the district court do not concern us.
Delays caused by excessive rainfall or by the seller suffering a heart attack are not
within the seller’s control or subject to his whim. No seller can command the sky
to open up and more rain to fall, and we are not aware of anyone deliberately
inflicting a heart attack on himself to delay the performance of a contractual duty.
The Disclosure Act is an anti-fraud statute. See Winter, 777 F.2d at 1447.
Allowing for reasonable delays caused by events beyond the seller’s control does
not promote or permit fraud. It does not transform the seller’s obligation into an
option. See Atteberry v. Maumelle Co., 60 F.3d 415, 420 (8th Cir. 1995) (“The
question is whether [the contractual provision] allows nonperformance by the
seller at the seller’s discretion.” (internal quotation marks omitted)). Even though
the contract excuses delays beyond the seller’s control, it is still one “obligating”
Paradigm to complete construction of the condominium within two years for
purposes of § 1702 (a)(2) of the Disclosure Act.7
7
The HUD Guidelines state that “as a general rule delay or nonperformance must be
based on grounds cognizable in contract law such as impossibility or frustration and on events
which are beyond the seller’s reasonable control.” Guidelines for Exemptions Available Under
the Interstate Land Sales Full Disclosure Act, 24 C.F.R. § 1710 appx. A, at A-2, available at
www.hud.gov/offices/hsg/ramh/ils/ilsexemp.cfm. They also say that “[c]ontract provisions
which allow for nonperformance or for delays for construction completion beyond the two-year
period are acceptable if such provisions are legally recognized as defenses to contract actions in
the jurisdiction where the building is being erected.” Id. The syntax of the first statement makes
it ambiguous. Assuming it means what the second statement implies, the guidelines’ position is
that force majeure clauses that go beyond defenses the law already provides take a contract out
of the § 1702 (a)(2) exemption.
17
III.
We REVERSE the judgment of the district court and REMAND for
judgment to be entered in favor of Paradigm.
Because the HUD Guidelines are not “published regulations subject to the rigors of the
Administrative Procedure Act, including public notice and comment,” they do not deserve full
Chevron deference. Reno v. Koray, 515 U.S. 50, 61, 115 S. Ct. 2021, 2027 (1995) (internal
quotation marks omitted); see also Chevron U.S.A., Inc. v. Natural Res. Def. Council, Inc., 467
U.S. 837, 104 S. Ct. 2778 (1984). A guidelines position is entitled to only as much deference as
it merits based on the “thoroughness evident in its consideration, the validity of its reasoning, its
consistency with earlier and later pronouncements, and all those factors which give it power to
persuade, if lacking power to control.” Skidmore, 323 U.S. at 140, 65 S. Ct. at 164. Little or no
deference is due to the guidelines’ position that any force majeure clause that goes beyond
events amounting to legal defenses takes the contract out of the § 1702 (a)(2) exemption. No
reasoning at all, much less thorough reasoning, is provided for that proposition. And it is
inconsistent with the guidelines’ other position that remedies limitations do not take a contract
out of the exemption unless they excuse nonperformance by the seller “at the seller’s discretion”
or “permit the seller to breach virtually at will.” 24 C.F.R. § 1710 appx. A, at A-1. It is anything
but consistent to set the bar that low for remedies limitations and then raise it so much higher for
delay caused by events that are out of the seller’s control.
18