The plaintiff appeals from the judgment of the trial court denying his application for an order to confirm an arbitration award and granting the defendants’1 application to vacate the arbitration award. The plaintiff contends that the trial court improperly disturbed the arbitrator’s decision regarding the arbitrability of the dispute. We agree and reverse the judgment of the trial court.
The following facts are relevant to this appeal. On August 27, 1990, the plaintiff, the defendants and Jeffrey Larson entered into two separate contracts, a management contract and a purchase contract. These contracts set forth conditions under which the plaintiff and Larson were to manage and to have an option to purchase State Paint, Inc., a business owned by the defendants. Each contract contains two provisions of importance to this case, a mandatory negotiation provision2 and an arbitration provision.3
After the plaintiff filed his application to confirm the arbitration award, the defendants sought to vacate the award pursuant to General Statutes § 52-4184 on the ground that the dispute was not arbitrable due to the parties’ failure to negotiate as required by the contracts. See footnote 2, supra. The trial court found that the question of arbitrability had not been waived by the defendants and that it had been submitted to the arbitrator.5 The trial court then reviewed the evidence, both testimonial and documentary,6 presented to it regard
There is no doubt that the arbitrability of the dispute between the parties is the central issue in this appeal. The resolution of this issue, however, must turn on the question of whose province it is to determine arbitrability — -the arbitrator’s or the court’s?
“The authority of an arbitrator to adjudicate the controversy is limited only if the agreement [between the parties] contains express language restricting the breadth of issues, reserving explicit rights, or conditioning the award on court review.” Garrity v. McCaskey, 223 Conn. 1, 5, 612 A.2d 742 (1992); Carabetta Builders, Inc. v. Hotz Corporation, 30 Conn. App. 157, 160, 619 A.2d 13 (1993). “Arbitration is a creature of contract. It is the province of the parties to set the limits of the authority of the arbitrators, and the parties will be bound by the limits they have fixed. . . . Whether the parties have agreed to submit to arbitration not only the merits of the dispute but the very question of arbitrability, as well, depends upon the
Here, the contracts provide for arbitration of “[a]ny dispute or question arising under the provisions of [the contracts] which has not been resolved [through the mandatory negotiation procedure].” The parties’ intent to have the question of arbitrability decided by an arbitrator is reflected not in the express terms of their agreements but in the broad language of the arbitration clause of their contracts. See Turner Construction Co. v. Eppoliti, Inc., supra, 144. The contract contains no exclusionary language removing the question of arbitrability from the arbitrator’s domain. See id. Nowhere does the contract affirmatively state that failure to comply with the mandatory negotiation provision will operate as a bar to arbitration. See Gary Excavating, Inc. v. North Haven, supra, 123. Under such circumstances, we conclude that “the above all-inclusive language of the agreement requires a determination that the parties intended the question of arbitrability to be determined by the arbitrators.” Bridgeport v. Bridgeport Police Local 1159, 183 Conn. 102, 105, 438 A.2d 1171 (1981).
“[B]y virtue of the broad scope of [the arbitration clause] of the contracts], the appropriate body to hear
“[W]hen arbitration is consensual, rather than statutorily imposed, judicial review is limited in scope. ... If the parties mutually agree to submit their dispute to arbitration, the resulting award is not reviewable for errors of law or fact. . . . Judicial review of unrestricted submissions is limited to a comparison between the submission and the award to see
The judgment is reversed and the case is remanded with direction to render judgment granting the plaintiffs application to confirm the arbitration award and denying the defendants’ application to vacate or correct the arbitration award.
In this opinion the other judges concurred.
1.
In addition to the named defendant, Helen Kampner is a defendant and a party to this appeal.
2.
In nearly identical language, the management contract and the purchase contract have the following “mandatory negotiation” provision: “[The parties] agree that they will attempt to negotiate in good faith any dispute of any nature arising under this [agreement]. The parties shall negotiate in good faith at not less than two negotiation sessions prior to seeking any resolution of any dispute under the [arbitration provision] of this [agreement], Each party shall have the right to legal representation at any such negotiation session.” (Emphasis added.)
3.
In nearly identical language, the management contract and the purchase contract have the following “arbitration” provision: “Any dispute or question arising under the provisions of this [agreement] whieh has not been resolved under [the mandatory negotiation provision] shall be determined by arbitration before one (1) arbitrator appointed by the American Arbitration Association. Arbitration proceedings shall occur at a neutral location in Waterbury, Connecticut, and shall be conducted in accordance with the rules then applicable of the American Arbitration Association. The decision of the arbitrator shall be final and may be entered in any court having jurisdiction thereof. Each party shall pay one-half of all costs and expenses of such arbitration.” (Emphasis added.)
4.
General Statutes § 52-418 (a) provides in pertinent part: “Upon the application of any party to an arbitration, the superior court . . . shall make an order vacating the award if it finds any of the following defects: (1) If the award has been procured by corruption, fraud or undue means; (2) if there has been evident partiality or corruption on the part of any arbitrator; (3) if the arbitrators have been guilty of misconduct in refusing to postpone the hearing upon sufficient cause shown or in refusing to hear evidence pertinent and material to the controversy or of any other action by which the rights of any party have been prejudiced; or (4) if the arbitrators have exceeded their powers or so imperfectly executed them that a mutual, final and definite award upon the subject matter submitted was not made.”
5.
In fact, the trial court found that the parties “agreed at the conclusion of the arbitration hearing to submit their correspondence to the arbitrator so that the arbitrator could decide the issue or arbitrability.”
6.
The proceedings before the arbitrator were not recorded.