The plaintiff appeals from the decision of the trial court confirming an arbitration award in favor of the defendant. The plaintiff claims that the court improperly (1) concluded that he had waived the issue of untimeliness and (2) affirmed the arbitrators’ finding that he was not operating a replacement vehicle when he was injured. We affirm the judgment of the trial court.
The plaintiff purchased the Suzuki motorcycle on May 2,1988, and took possession of it on June 4,1988. He continued to operate the Honda motorcycle sporadically after May 2, 1988, and before the accident of June 10, 1988. On September 8, 1988, the plaintiff informed the defendant that he had acquired the Suzuki. At no time before the accident did the plaintiff notify the defendant that he had acquired the Suzuki or that he was removing the Honda motorcycle from service. Following the accident, the plaintiff brought a claim for uninsured motorist benefits under his two policies of insurance with the defendant. The parties submitted the coverage issue to compulsory arbitration before a three person panel. By a two to one vote, the
I
The plaintiff first claims that the arbitrators’ award must be vacated because it was not rendered within the time period allowed by General Statutes § 52-416,2 and the plaintiff had not agreed to the delay and had filed a timely motion to vacate the award.3 The following facts are necessary to resolve this issue.
The parties agreed to a bifurcated arbitration procedure by which the arbitrators would first decide the coverage issues and, if necessary, consider other issues at a later date. They asked the chairman of the arbitration panel to establish a briefing schedule, and requested a forty-five day period for initial simultaneous briefs and another fifteen days for reply briefs. The chairman of the panel thereafter set August 12,1991, for submission of briefs, and August 28,1991, for reply briefs. He further scheduled September 11, 1991, as the date of the arbitrators’ meeting, and notified both
On September 6, 1991, the panel chairman notified the other panel members that the meeting scheduled for September 11, 1991, had to be cancelled because of conflicting trial schedules of two arbitrators; a revised meeting date of October 7, 1991, was suggested. Both parties were sent copies of the chairman’s September 6 letter. On September 10,1991, one of the arbitrators advised the panel that he was unavailable on October 7; he suggested a meeting for one of the following two Mondays. Both parties received copies of this correspondence, as well.
On November 18, 1991, the arbitrators met and reviewed evidence consisting of the two insurance policies and the plaintiff’s deposition. They also considered the briefs submitted by the parties. A majority opinion, dated November 18,1991, was sent to the parties on or about November 27,1991. The dissent carries the date of December 6, 1991.
The plaintiff claims that the statutory deadline of thirty days, mandated by General Statutes § 52-416, ran from the date set for submission of the parties’ reply briefs.4 He argues that the arbitrators did not render the award for more than two months after receiving the reply briefs. The defendant argues alternatively that (1) the award was timely rendered because the hearing took place on November 18,1991, (2) the plaintiff failed to file his application to vacate the award on
General Statutes § 52-416 requires that the rendering of an arbitration award and notification of the award both be given within the thirty day period from the date the hearing or hearings are completed. Hayes v. Travelers Indemnity Co., 26 Conn. App. 418, 421, 601 A.2d 555 (1992). In Hayes, there was “no indication that the parties waived the thirty day . . . period.” Id., 423. Here, on the other hand, the trial court found that there was such an indication. The trial court found that when the parties extended the time for filing their reply briefs with the arbitrators, they also extended the thirty day period for rendering a decision to October 7, 1991. Thereafter, the parties knew, through receipt of copies of various communications, that the arbitrators would not be meeting until an undetermined date after October 7, 1991.
Both parties clearly knew, through counsel, that the arbitrators were attempting to choose a meeting time and date acceptable to all three of them, that the arbitrators had not met within thirty days of the submission of the reply briefs and that, at the time of the last correspondence, the thirty days, if counted from the date the reply briefs were due, had already transpired. During this period, the plaintiff raised no objec
In this case, neither party objected to the arbitrators’ delayed meetings; the parties manifested an agreement that the award would be delayed. “The party challenging an arbitration award . . . bears the burden of demonstrating that the award violates the parties’
Because the trial court properly found that the parties had waived any right to object to the untimeliness of the award, we need not address the defendant’s alternative arguments.
II
The plaintiff next claims that the trial court improperly affirmed the arbitrators’ conclusion that at the time of the accident the plaintiff was not operating a “replacement vehicle” and therefore was not covered by the uninsured motorist provisions of the policies issued by the defendant.
The trial court properly concluded that the determination of whether the plaintiff was operating a replacement vehicle as defined by the provisions of an automobile insurance policy involves more than factual issues; it also involves a question of law requiring the interpretation of provisions of the policy. The court therefore properly conducted a de novo review. Chmie-lewski v. Aetna Casualty & Surety Co., 218 Conn. 646, 667, 591 A.2d 101 (1991); Middlesex Ins. Co. v. Quinn, 27 Conn. App. 573, 576, 609 A.2d 1008 (1992), aff’d, 225 Conn. 257, 622 A.2d 572 (1993). After examining cases from other jurisdictions, the trial court identified two approaches to the definition of replacement vehicle. The first, the “formalistic” approach, requires that the vehicle described in the policy be disposed of or otherwise rendered inoperable at the time of the replacement. The second, “alternative” approach, looks
Under the alternative approach adopted by the trial court, the insured’s intent is an important factor in determining whether a newly acquired vehicle is a replacement vehicle. Under the facts of this case, intent must be determined as of June 4, 1988, the date the plaintiff took possession of the Suzuki motorcycle, not May 2, 1988, the date he purchased the vehicle.
The issue to be determined is whether the trial court properly concluded that there was substantial evidence supporting the arbitrators’ finding that it was not the plaintiff’s intent as of June 4, 1988, that the Suzuki, rather than the Honda motorcycle, should be the insured vehicle. “The substantial evidence test in the context of arbitration requires that a court determine whether substantial evidence exists in the ‘record to support the arbitration panel’s findings of basic fact and whether the conclusions drawn from these facts are reasonable. . . . Substantial evidence will be found to exist if the . . . record supplies a substantial basis of fact from which the court reasonably can infer the fact in issue.’ ” Lawrence v. New Hampshire Ins. Co., 29 Conn. App. 484, 490, 616 A.2d 806, cert. denied, 224 Conn. 923, 618 A.2d 528 (1992).
The record supports the arbitrators’ finding that the plaintiff did not intend to substitute the Suzuki for the Honda motorcycle. The deposition testimony of the plaintiff as to his use of the Honda was conflicting; he stated both that he rode the Honda throughout May and June of 1988 and that the vehicle was inoperable on the street.9 The arbitrators obviously resolved this factual conflict by determining that the plaintiff drove the Honda sporadically after May 2,1988, and before the accident. From this, they inferred “that it was not the [plaintiff’s] intent, as of May 2,1988, that the Suzuki, rather than the motorcycle he continued to drive, should be the insured vehicle.”
Although the arbitrators determined the plaintiff’s intent “as of May 2, 1988,” we do not view this finding as limited to that day alone. May 2,1988, is merely the starting point. The determination is that at no time,
Intent is a question of fact for the trier. State v. Woh-ler, 30 Conn. App. 571, 577, 621 A.2d 751 (1992). We will not reverse the trier’s determination of intent unless the trier could not reasonably have arrived at the conclusion that it reached. Hanson Development Co. v. East Great Plains Shopping Center, Inc., 195 Conn. 60, 65, 485 A.2d 1296 (1985).
“Intention is a mental process, and of necessity it must be proved by the statements or actions of the person whose act is being scrutinized. ... A person’s intention is to be inferred from his conduct.” (Citations omitted.) State v. Patterson, 213 Conn. 708, 721, 570 A.2d 174 (1990). The plaintiff argues that he did not intend to continue operating the Honda motorcycle. There was, however, substantial evidence, from which reasonable inferences could be drawn, that permitted the arbitrators to reach a contrary conclusion as to the plaintiff’s intent.
The arbitrators, as fact finders, have the right to believe or disbelieve the evidence presented in whole or in part. See Connecticut Building Wrecking Co. v. Carothers, 218 Conn. 580, 593, 590 A.2d 447 (1991); Connecticut Light & Power Co. v. Department of Public Utility Control, 216 Conn. 627, 640, 583 A.2d 906 (1990). On the basis of the evidence presented, the
The judgment is affirmed.
In this opinion, Landau, J., concurred.
1.
An effective award may be rendered by a majority of the arbitrators. General Statutes § 52-414 (a).
2.
General Statutes § 52-416 provides: “(a) If the time within which an award is rendered has not been fixed in the arbitration agreement, the arbitrator or arbitrators or umpire shall render the award within thirty days from the date the hearing or hearings are completed, or,‘if the parties are to submit additional material after the hearing or hearings, thirty days from the date fixed by the arbitrator or arbitrators or umpire for the receipt of the material. An award made after that time shall have no legal effect unless the parties expressly extend the time in which the award may be made or by an extension or ratification in writing.
“(b) The award shall be in writing and signed by the arbitrator or arbitrators, or a majority of them, or by the umpire. Written notice of the award shall be given to each party.”
3.
The plaintiff presents this timeliness issue as an alternative to his main argument. We address it first because it is a challenge to the arbitrators’ authority to render an award.
4.
While the parties had agreed to a revised date of September 6, 1991, for submission of reply briefs, the plaintiff actually submitted his brief on August 28, 1991, and the defendant submitted its brief on September 2, 1991.
5.
The plaintiff first raised Ms untimeliness claim in a reply brief he filed with the trial court on February 18,1992, approximately three months after the arbitrators’ award. The court agreed with the defendant that this issue was not timely raised pursuant to General Statutes § 52-420.
6.
General Statutes § 52-420 provides: “(b) No motion to vacate, modify or correct an award may be made after thirty days from the notice of the award to the party to the arbitration who makes the motion.”
7.
The court noted that “proceeding with arbitration without objection after knowledge the arbitrators will not render the award within the time provided constitutes a waiver of any objection pursuant to . . . AAA rules. . . . The American Arbitration Association, Commercial Arbitration Rules § 38 provides: ‘WAIVER OF RULES. Any party who proceeds with the arbitration after knowledge that any provision or requirement of these rules has not been complied with and who fails to state objection thereto in writing, shall be deemed to have waived the right to object.’ ” Diamond Fertiliser & Chemical Corporation v. Commodities Trading International Corporation, 211 Conn. 541, 553 n.8, 560 A.2d 419 (1989).
8.
The trial court relied on cases of our Supreme Court generally indicating that ambiguous conditions and provisions in an insurance policy should be afforded a liberal construction in favor of the insured. See, e.g., McGlinchey v. Aetna Casualty & Surety Co., 224 Conn. 133, 617 A.2d 445 (1992); Middlesex Ins. Co. v. Quinn, 27 Conn. App. 573, 609 A.2d 1008 (1992), aff’d, 225 Conn. 238, 622 A.2d 555 (1993). The court also relied on its conclusion that, under the facts, “the plaintiff could not recover under the ‘formalistic approach.’ ”
9.
At his deposition, the plaintiff was asked by the defendant’s counsel, “[D]id you drive [the Honda] throughout May and June 1988?” He stated, “Very sporadically. It wasn’t running — barely running, I should say.” When asked, “[D]id you drive it up until the time you sold it [in 1989],” he stated that he “stopped riding it shortly after the accident. . . .”
Later, when asked by his attorney whether, on June 10,1988, the Honda was still running and if he was “able to use it on the street,” the plaintiff stated, “No, no. When I say running, it would start. . . .”
The plaintiff also stated that between the time he took possession of the Suzuki on June 4 and the day of his accident on June 10, he did not ride the Suzuki.
10.
Although the arbitrators did not define the term “replace,” the trial court determined that under neither the “alternative” nor the more liberal “formalistic” approach could the plaintiff prevail, in view of the arbitrators’ factual findings. A remand for the purpose of determining which approach the arbitrators used to define “replace” is therefore unnecessary.