Gartner v. City of Detroit

Hooker, C. J.

The plaintiff made a contract with the city of Detroit whereby he undertook to construct a short extension of an existing sewer. The contract was in writing. The specifications referred to in the advertisement for proposals were made a part of the contract. They contained the following provisions: “No tunneling or drilling will be permitted unless by written consent of the board of public works, or unless stated on the plan or diagram to be a tunneled sewer;” also, “All loss or damage arising out of the nature of the work, or from any unforeseen obstructions or difficulties which may be encountered in the prosecution of the same, or from the action of the elements, to be sustained by the contractor. ” A diagram of the proposed extension was also made a part of the contract, and upon its face the words, “ N. B. May be tunneled,” were printed. Plaintiff and the city officers appear to have acted upon a common understanding that ft would be tunneled; but on making the attempt to sink a shaft, as preliminary to tunneling, quicksand was struck, and that plan was abandoned. Plaintiff proceeded to excavate a trench, and finished his job, but at a cost considerably exceeding the contract price, which was paid him. He has brought this action to recover the actual post, $2,024.36, less $500, the contract price. A verdict was directed for the defendant, and the plaintiff has appealed.

It is urged upon the part of the plaintiff:

1. That the city has represented that this ground was such as to admit of tunneling, and that, it having turned out otherwise, the law will imply an obligation to pay the increased cost.

2. That the contract provides that the' contractor shall submit to changes and alterations in the sewer at the direction of the city, and shall be paid for extra work occasioned thereby. He says that a change became necessary in the *23method of doing the work, whereby he is entitled to compensation for his additional labor and expense, under this stipulation.

To us the case seems a simple one. We think that it cannot be said that the fact that the job was let with an expectation that it would be tunneled indicates an intention to represent that it could be tunneled. On the contrary, the language of the contract is a permission to tunnel, and the indication that this was so understood is emphasized by the express provision of the contract quoted, imposing risks of obstructions upon the contractor. The job was advertised and let upon such terms, and, while we appreciate the hardship of having to perform a contract at a loss, we cannot relieve the contractor from the obligation of his contract. See McBrian v. City of Grand Rapids, 56 Mich. 99 (22 N. W. 206).

Eegarding the second point, it is sufficient to say that, in our opinion, counsel ask for a strained construction of the language. The city has asked for no addition to, nor change in, its sewer. Nor has it attempted to dictate as to a method of construction.

The judgment is affirmed.

Moore, Grant, and Montgomery, JJ., concurred.' Long, J., did not sit.