Rude v. Mitchell

Black, J.

This is a suit by contractors to enforce a mechanic’s lien. The case was tried before a referee, and to his report the defendants filed exceptions which were overruled, and the defendants appealed.

The defendants own a lot, 53 by 153 feet, upon which there were two four-story brick buildings, covering the entire property ; one is called the front, and the other the rear building. The floors were not on a level because of the difference in the grade at the front and rear of the lot. On the twenty-eighth of November, 1882, plaintiffs and defendants made a written contract by which the plaintiffs agreed to add two stories to the front and three to the rear building, to change the floors, and to otherwise reconstruct the old buildings according to plans and specifications prepared by the architects, and for all which defendants agreed to pay them the sum of $22,287 in installments as the work progressed. The contract contains a stipulation to the effect *370that the architects, Barnett & Son, may make alterations in the plans and specifications, and that the difference of the cost and expense occasioned by the additions or omissions shall be reasonable and just and shall be figured and priced by the architects and their figures shall be final and bin ding.

After the date of the agreement and before the work was commenced, the parties made a supplemental contract to the effect that each of the three new stories of the rear-building should be made into one room, and because of this change there should be deducted from the contract price $1,429.74, and that there should be added to it for increased thickness of walls and some other specified work $650.10. After the walls were up, floors laid, and one coat of plastering on, the plaintiffs agreed to subdivide these three large rooms according to the first plan for $1,267, using wood instead of brick for the partitions ; thus making the entire contract price $22,774.36. The suit is in two counts, the first is based upon the contract and it is alleged therein that omissions and additions were made by orders of the architects, and that they fixed the prices for such deductions and for the extra work; the second is for the reasonable value of the entire work. The referee found that omissions were made, and that extra work had been done by the plaintiffs, all at the request of the architects ; but that the architects did not fix the prices for these deductions and extra work, and for this reason the plaintiffs could not recover on the first cause of action. He found for .the plaintiffs on the second count, and in making his estimate he took the contract price as a basis, and from that he deducted various amounts because the work was not up to the contract standard, and then added allowances for increased value of some of the work and for the reasonable value of work not included in the contract and specifications.

1. The first contention of defendants is that there *371is no evidence upon which" to support a finding for the reasonable value of the work ; that the contract itself is no evidence of the reasonable value of the work and materials, and especially so in view of the fact that plaintiffs did not comply with the contract. The referee does not find that plaintiffs made, a breach of their contract; on the contrary, he finds that they made a substantial compliance with its terms, and that the deviations that were made from the specifications were made by the directions of the architects, and were therefore made according to the contract. Even had the work not been done in accordance with the contract, still that would not defeat a recovery for the value of the work done; but in such cases the contractors must sustain the loss for such damages as result from the inferiority of the work. Yeats v. Ballentine, 56 Mo. 530. It was said in Marsh v. Richards, 29 Mo. 104: “In such cases, the measure of damages would seem to be justly arrived at by the statement, that if the work, when done under the contract and' in pursuance to its terms, is worth the price agreed upon, what is the work worth, done as it is, proportionally, to the price fixed by the contract?” It is thus seen that even where there has been a breach of the contract, the contract price becomes an element in estimating the measure of the recovery. Of course that would not be true, if both parties abandoned the contract. But in this case there was no breach of the contract, and the contract price is certainly prima-facie evidence of the value of the work and of the materials, agreed to be done and furnished. It is the estimate which the parties to this suit themselves put upon the work and materials.

The referee reports that there was no evidence before him of the value of the work and materials specified in the contract, save that furnished by the contract' itself and the fact that defendants from' time to time made payments apparently upon the contract, aggregating over twenty-one thousand dollars. • With no other *372evidence before him, he properly took the price thus fixed as the value of the work and material. Plaintiffs ought not to recover more than the contract price, however much the work might be worth, with reasonable deductions for all changes which reduced the cost of the materials and value of the work, and these deductions the referee made.

2. The fact that the architects did not fix the amount of the deductions and the prices to be paid for the additional and extra work does not constitute any defense to a recovery on quantum meruit. The agreement was that the difference of the cost by reason of the omissions and additions should be reasonable and just, and should be figured and fixed by the architects. If they failed to fix these prices, that fact constitutes no defense in an action for the value of the work. On such an issue the estimate of the architects would be of no more value than that of any other competent witness. Neenan v. Donohue, 50 Mo. 493; Dinsmore v. Livingston County, 60 Mo. 241; Yeats v. Ballentine, 56 Mo. 530.

3. The mechanics’ lien, as filed with the clerk of the circuit court, begins with the following, to-wit:

1882, Dec. 1st. For alterations and additions, to buildings Nos. 210 and 212 N. Third street, as per plans and specifications.........$22,287 00

For extra work in reinstating building to original plans as per agreement 1,267 00

For difference in alterations as per agreement...................... 650 00

It then sets out specific items and concludes with items like these:

Amount J. A.>Archibald’s bill, extra brick work................. 850 00

Scherps & Koken bill, extra iron work 66 33

The statute makes it the duty of the contractor to *373file with the clerk of the circuit court within the designated time “ a just and true account of the demand due him or them, after all just credits have been given, which is to be a lien upon such building,” etc. It is settled law in this state that a statement showing only the balance due is not such an account as is contemplated by the statute. Graves v. Pierce, 53 Mo. 423; Mc Williams v. Allen, 45 Mo. 573; Coe v. Ritter, 86 Mo. 287. All these cases proceed on the theory that there must be an account which answers to the ordinary signification of the term..

In Hilliker v. Francisco, 65 Mo. 599, the first item of the account was in these words: “To Junction City Stone furnished First National Bank as per contract, $7,790.00.” The suit was one by the sub-contractor, and there was evidence to show that the bank had agreed with the contractor to the sum of seven thousand dollars as compensation to the plaintiffs for the material and labor mentioned in the item. Under these circumstances it was held that the item was sufficiently specific. The item there in dispute, it will be seen, related to the stonework and labor of setting only, and the price is given. In the present case the first item is for $22,287, and there is nothing to show, on the face of the account, what is, or what is not, intended to be included. The Hilliker case furnishes no authority for upholding the account filed in this case, and that case goes to the verge of the law.

Many.things are often included in these building contracts for which the law gives no lien ; and when it calls for a just and true account, it means a fairly itemized account showing what the materials are, and. the work that was done, and the price charged, so that it can be seen from the face of the account that the law gives a lien therefor. A lumping item of the whole contract price on the one hand, and the credits on the other, is no compliance with the law at all. The account *374should be complete on its face, and a reference to plans and specifications for the work done and materials furnished is a worthless reference and adds nothing to the statement. These liens are creatures of the statute and the lienor must make and file an account which is a fair and substantial compliance with the law. If he fails to do this he has no lien for the materials and. work not thus specified.

It is argued that, as this is a case between the contractors and owners of tbe property, there is no need of the same particularity as in cases where a sub-contractor seeks to enforce a lien. The answer is that the statute is the same in both cases, and it makes no such distinction. These liens should not be defeated on mere technical grounds, but there is no hardship in requiring the lienor to verify and file an account which comes within the ordinary meaning of the term. That has not been done in this case.

As to the various counter-claims set out in the answer, it is sufficient to say that the referee made such deductions from the contract price as he believed the evidence would warrant, and we see no reason to differ with his conclusion upon these issues.

The result is that the judgment is reversed in so far as it enforces a mechanic’s lien, but as a money judgment only it is affirmed.

Barclay, J., not sitting; the other judges concur.