Silvester v. City of St. Louis

BURGESS, J.

— This is an action by plaintiffs to recover of defendant the sum of ten thousand three hundred dollars, being the amount, and interest from July 28, 1897, of the award of commissioners for damages to plaintiffs’ property in St. Louis in a proceeding by said city to establish and open Compton avenue, a public highway, from Magnolia avenue southwardly to its intersection with Wilmington road. The trial resulted in a judgment for defendant from which plaintiffs appeal.

The facts briefly stated are about as follows: On December 26, 1893, the defendant city undertook to establish ' Compton avenue, a public highway from Magnolia avenue *605southwardly to its intersection with Wilmington road, and to that end adopted ordinance No. 17346. Thereafter on the first day of August, 1894, the city instituted suit in the circuit court, the necessary opening proceedings for the appropriation of private property for that purpose.

The plaintiff, Sarah A. Silvester, owned a parcel of land fronting one hundred and ninety-nine feet six and one-fourth inches on Compton avenue,-and under the scheme for opening and extending Compton avenue a strip of her land would be taken off the eastern edge thereof to a uniform width of twelve feet six and one-fourth inches, thus making the required strip twelve feet six and one-fourth inches by one hundred and ninety-nine feet six and one-fourth inches.

Commissioners were regularly appointed by the circuit court, and in their report duly filed they awarded the plaintiff, Sarah A. Silvester, eight hundred dollars, as the value of the land proposed to be taken, and ten thousand dollars as the value of certain improvements thereon.

In accordance with section 9 of article 6 of the city charter, the report of the commissioners, after having been filed in the circuit court, was reported to the municipal assembly, which approved it.

Certain exceptions which had been filed were heard, with the result that the court reduced the damages awarded plaintiff for her improvements to ninety-five hundred dollars, but leaving the aw'ard for the land at eight hundred dollars, thus making the total damages allowed her ten thousand three hundred dollars. All of the exceptions having been disposed of, the court entered a final judgment confirming the report and a certified copy thereof was duly delivered, in accordance with section 10 of article' 6 of the charter, to the comptroller, who furnished a copy thereof to the assembly. The assembly thereupon passed through both of its branches, a bill for the appropriation of *606the amount necessary to pay the damages assessed in the opening proceedings, but this bill was vetoed by the mayor and returned to the branch of the assembly wherein it originated. Thereafter, the mayor’s veto was sustained in both houses of the assembly and no appropriation for the payment of the damages was ever made, nor was any other step had or taken in reference to the opening of Compton avenue.

Thereupon, the plaintiffs brought this suit against the city of St. Louis, for the amount of the award of the commissioners, together with interest thereon from July 28, 1891, the day when the circuit court approved the report. The petition recites that the municipal assembly made the necessary appropriation for the payment of the damages ascertained by the commissioners, but upon the trial it was conceded that this allegation was not founded in fact, and the facts as they are above stated were agreed upon by stipulation, and upon them the case was submitted to the lower court. It was also admitted upon the trial that the next session of the municipal assembly, following the confirmation of the report, had expired.

Plaintiffs contend that the vote by the municipal assembly for the payment of all the damages to property-owners affected by the condemnation proceedings, was sufficient in law to entitle plaintiff, Mrs. Silvester, to her damages as assessed, and make it equivalent to a common-law judgment upon which she is entitled to maintain this action, regardless of the fact that the ordinance passed by both branches of the assembly for the appropriation of tire amount necessary to pay the damages assessed in tire opening proceedings was vetoed by the mayor.

By the provisions of section 9, article 6, of the charter of the defendant city, it is provided that the city may at any time before the final confirmation of the report of commissioners appointed in any condemnation proceedings, dismiss and withdraw said proceedings. Judge Dillon, in passing upon the *607same subject in his work on Municipal Corporations, Vol. 2 (4 Ed.), section 608, says:

“Under the language by which-the power to open streets and to take private property for that purpose is usually conferred upon municipal corporations, they may at any time before taking possession of the property under completed proceedings, or before the final judgment, recede from or discontinue the proceedings they have instituted. This may be done, unless it is otherwise provided by legislative enactment, at any time before vested right in others have attached. Until .the assessments of damages have been made, the amount can not be known; and on the whole, it is reasonable, that after having ascertained the expense of the project, the corporation should have the discretion to go on with it or not, as it sees fit, it being liable in proper cases for any wrongful acts injurious to the owner, as shown in the next section.”

And where the condemnation proceedings have been rightfully discontinued, the person whose land has'been sought to be condemned can not maintain mandamus to compel payment of the sum estimated by the commissioners to be his damages, nor can he maintain an action for that purpose; but he may have an action for damages for any wrongful and injurious acts done by the corporation in course of the condemnation proceedings. [2 Dillon’s Municipal Corporations (4 Ed.), sec. 609.] ■

In-the following section (610), the same author remarks:

“Nor has the municipal corporation always been considered as concluded and bound to pay the damages awarded, although the report of the commissioners appointed by it had been confirmed. The act to enable the city of Baltimore to procure a supply of water authorized the city to condemn lands, required the inquisition of damages to be returned to the circuit court, and provided that it ‘should be confirmed by said court at its *608next sitting, if no sufficient cause to the contrary be shown, and the Valuation when paid or tendered shall entitle the city to use the land as fully as if it had been conveyed by the owner.’ It was held that the city was not bound by the mere inquisition of damages, although confirmed by the court, to pay the amount awarded, but could, nevertheless, abandon the location in question; that the judgment of confirmation simply decided the-value of the land, and that payment or tender of the valuation is necessary to give the city a title to the property. It was admitted by the court, however, that if the owner suffered loss or injury by reason of the wrongful acts of the city, he might, recover damages therefor.” ■

The same rule is announced in Lewis on Eminent Domain, sections 655, 656.

City of St. Joseph v. Hamilton, 43 Mo. 282, was a proceeding for the purpose of widening a street in that city and to condemn a strip of ground of the defendants for that purpose. A judgment was rendered against the city upon an award made by commissioners in widening the street, and it'was sought by Hamilton to enforce the judgment. It was ruled that the city might dismiss its proceedings at any time before final judgment in the circuit court, and that the only liability that would be incurred would be the expenses, so if excessive damages were allowed and it be thought expedient to do so, it might decline to proceed with the work. The same rule is announced State ex rel. Rogers v. Hug, 44 Mo. 116; Simpson v. Kansas City, 111 Mo. 237; Whyte v. City of Kansas, 22 Mo. App. 409.

Where the city chooses to abandon the enterprise or declines to take possession or make use of the property, there is no divestiture of the title from the owner, and he is not entitled to pay therefor from the public. It is, therefore, entirely discretionary with it whether it will pay the damages assessed and take the property, or abandon it altogether. Condemnation *609proceedings for public uses could not be prosecuted in cities upon any other theory, for in many cases juries might award damages so exaggerated as to render it impossible for them to do so, hence, the right is accorded them of refusing to take the property or pay the damages assessed if it feels disposed to do so.

Plaintiffs, however, contend that under section 10, article 6, of the city charter, the action of the two houses of the municipal assembly in voting the amount of damages to them under the judgment of the court confirming the report of commissioners, was sufficient and effective without the concurrence of the mayor, as if it were a mere resolution of the two houses. That section provides that after the report of the commissioners has been approved and final action taken thereon by the court, the assembly shall “make an appropriation for the payment, out of the city treasury, of all damages assessed in favor of the owners of property appropriated, and the city treasurer shall cause the same to be paid to the parties entitled thereto, respectively, or into the court for their use, as provided by ordinance.” So that it will not do to say that an ordinance approved by the mayor, was not a prerequisite to the payment of the money. No other con elusion -can be reached when section 10 of article 6, and section 26 of article 3, and section 14 of article 5, are read together.

Our conclusion is that the judgment should be affirmed, and it is so ordered.

All concur.