Heritage Commercial Contractors, Inc. v. City of Helena

JUSTICE WEBER

delivered the Opinion of the Court.

This is an appeal from the grant of City of Helena’s Motion to Dismiss by the First Judicial District Court, Lewis and Clark County. We affirm.

Although the appellant presents two issues for review, the preliminary question of standing is the only question that we need reach at this time:

Did the District Court err in finding that Heritage Commercial Contractors had no standing to object to the City of Helena’s award of a contract to Good Humus Compost Company?

The City of Helena (the City) placed an ad in the legal section of the Independent Record on October 14, 1992. The ad was a “Request for Proposal” to begin a green waste compost program. Heritage Commercial Contractors (Heritage) submitted a written proposal on October 31,1993. Following the initial submission, Heritage supplied supplemental information three times upon request from the City.

On February 14,1994, the City entered into a contract to compost its municipal waste with the Good Humus Compost Company. Heritage protested this award because it contended the City had not opened, the contract to bidding. The City replied that the contract was for a technical service and excluded from bid by § 7-5-4301, MCA.

Heritage commenced action for damages suffered as a result of the City’s negligence in failing to comply with statutes concerning municipal bidding. The District Court granted dismissal to the City because it found that Heritage had no standing to object to the City’s award of a contract. Heritage appeals this ruling.

Did the District Court err in finding that Heritage Commercial Contractors had no standing to object to the City of Helena’s award of a contract to Good Humus Compost Company?

Heritage argues that unless specifically excepted, all municipal contracts must be awarded under the bidding procedures laid out in § 7-5-4301, MCA, et seq. Heritage claims that the contract awarded was not technical as argued by the City, and was not therefore, *92excepted from the bidding requirement. Further, Heritage argues that Baker relied upon by the District Court, does not apply to this case because in Baker bidding took place, whereas in the present case no bidding procedure took place.

The City argues that a contract for services of less than $25,000 can be awarded without use of the statutory bidding procedure. According to the City, the District Court was correct in finding that Heritage had no standing to bring this suit. The City also contends that Heritage has asked for damages which is a new unsupported legal theory; the proper remedy, if Heritage has standing, would be to ask that the bidding take place.

The District Court relied on Baker v. State (1985), 218 Mont. 235, 707 P.2d 20 for the proposition that a party not awarded a public contract fails to have standing to contest the decision by the municipality. While Heritage argues that Baker does not apply because in that fact scenario bidding took place, the Baker case has a much broader scope:

[W]e have held that the discretion of the agency to award public work contracts to the lowest bidder is not subject to judicial review under normal circumstances, (cites omitted). We will not make a contract for the parties. Nor is this Court prepared to venture that Baker would have been awarded the contract if Edsall was not the successful bidder. In the absence of any showing of bad faith, fraud, or corruption of the Department, the exercise of discretion will not be disturbed. (Emphasis added).

Baker, 218 Mont. at 240, 707 P.2d at 24.

Regardless of bidding or no bidding, the only way this Court will review an agency’s discretionary rulings — which would involve the decision in this case — is whether the action taken by the governmental agency was conducted in bad faith, with fraud, or under the influence of corruption. Baker, 218 Mont. at 240, 707 P.2d at 24. Heritage has not introduced a shred of evidence that would taint the City’s decision.

Further, the statutory scheme states that contracts for construction, repair, or maintenance under $25,000 do not need to go through the bidding procedure. Section 7-5-4302, MCA. Contracts that are professional in nature also do not have to be bid. Section 7-5-4301(1), MCA. The contract in contention was under $25,000 and involved professional, if not technical, skills.

We conclude that the contract in question was not subject to the bidding procedure of § 7-5-4301, MCA, et seq. We further conclude *93that Heritage has presented no evidence that the City’s decision was made in bad faith and, therefore, Heritage has no standing to object to the City’s discretionary ruling.

We hold that the District Court did not err in finding that Heritage Commercial Contractors had no standing to object to the City of Helena’s award of a contract to Good Humus Compost Company.

Affirmed.

CHIEF JUSTICE TURNAGE, JUSTICES HUNT and GRAY concur.