CC-Aventura, Inc. v. Weitz Company, LLC

Court: Court of Appeals for the Eleventh Circuit
Date filed: 2012-10-11
Citations: 492 F. App'x 54
Copy Citations
Click to Find Citing Cases
Combined Opinion
            Case: 11-11191   Date Filed: 10/11/2012   Page: 1 of 7

                                                          [DO NOT PUBLISH]

             IN THE UNITED STATES COURT OF APPEALS

                     FOR THE ELEVENTH CIRCUIT
                      ________________________

                             No. 11-11191
                       ________________________

                   D. C. Docket No. 1:06-cv-21598-PCH

CC-AVENTURA, INC.,

                                       Plaintiff - Counter Defendant - Appellee,

CLASSIC RESIDENCE MANAGEMENT LIMITED PARTNERSHIP,

                                                             Plaintiff - Appellee,

et al.,
                                   versus

WEITZ COMPANY, LLC,

                               Defendant - Cross Defendant - Cross Claimant -
                                     Counter Claimant - Third Party Plaintiff -
                                               Counter Defendant - Appellant.

                       ________________________

                Appeal from the United States District Court
                    for the Southern District of Florida
                      _________________________

                             (October 11, 2012)

Before DUBINA, Chief Judge, and PRYOR and ANDERSON, Circuit Judges.
               Case: 11-11191     Date Filed: 10/11/2012     Page: 2 of 7

PER CURIAM:

      In this surety case, obligee/contractor Weitz contends that the district court

erred by failing to properly follow the majority opinion in Dooley & Mack

Constructors, Inc. v. Developers Surety & Indemnity Co., 972 So. 2d 893 (Fla.

Dist. Ct. App. 2007). The district court concluded that the surety Fidelity was not

liable on a surety bond because Weitz had failed to give notice to Fidelity of the

subcontractor Aero’s default before Weitz undertook to remedy the default itself.

      In Dooley, the subcontractor defaulted on its obligations. Id. at 894. Rather

than notify the surety, the obligee/contractor remedied the default itself and then

brought suit against the surety. Id. The majority in Dooley interpreted the surety

bond (which included by incorporation the subcontract between the

obligee/contractor and the subcontractor) to have two alternative routes by which

the surety could face liability if the subcontractor defaulted on its obligations: (1)

the bond itself stated that the obligee/contractor could notify the surety of the

default and require that the surety remedy the default; or (2) the subcontract

(incorporated into the bond) stated that the obligee/contractor could remedy the

default itself and then later sue the surety to cover the shortfall.

       The Dooley majority conceded that if the obligee/contractor had proceeded

under the first route, then it would have been required to first give notice to the

                                            2
                Case: 11-11191        Date Filed: 10/11/2012       Page: 3 of 7

surety, because that provision was included with “standard” surety bond language

that requires the obligee/contractor to first give notice. Id.1 But the court

concluded that the second route (where the obligee/contractor could remedy the

default itself) did not include any of the “standard” surety language that requires

notification, id. at 895, and it also did not include any other language explicitly

requiring notice to be given, id. (citing RLI Ins. Co. v. St. Patrick’s Home for the

Infirm & Aged, 452 F. Supp. 2d 484 (S.D.N.Y. 2006), for the proposition that the

“absence of [an] explicit notice requirement of principal’s default to surety

distinguishes cases finding that notice is condition precedent to surety’s payment

under bond.”). Since the obligee/contractor proceeded under this second route, it

did not have to give prior notice to the surety.

       In the case sub judice, the bond (and, by incorporation, the subcontract)

similarly has two routes by which the surety could be exposed to liability if the

subcontractor defaulted: the surety could undertake to remedy the default, or the

obligee/contractor could undertake to remedy the default. But unlike the scenario

in Dooley, the record in this case shows that both routes did include an explicit

       1
                The Dooley majority noted that “[u]nder a familiar term of a ‘standard’ surety
bond, which is included in this one, such a failure [to first provide notice to the surety] would
indeed result in a termination of the surety’s obligations.” Dooley, 972 So. 2d at 894. The
“familiar term” of a “standard” surety bond in Dooley was quoted as: “Whenever subcontractor
shall be, and declared by Obligee to be in default under the Subcontract, . . . the Surety may
promptly remedy the default . . . .” Id. at 894 n.1 (emphasis in original).

                                                 3
               Case: 11-11191       Date Filed: 10/11/2012       Page: 4 of 7

requirement that notice first be given to the surety,2 and it also was included along

with the same provision as the “standard” language that would require notice to

first be given (as Dooley itself acknowledged).

      In other words, the language of the relevant documents in Dooley was

different from the relevant language here. In Dooley, the subcontract gave the

general contractor “the option, but not the obligation, to notify.” In contrast, the

subcontract in this case made reference to Weitz’s ability to remedy the default, but

only after Weitz terminated the subcontractor’s performance for cause, and thus

only after reasonable notice.3 Reading all the language in the relevant documents


      2
             The pertinent part of the bond stated:

      Whenever Principal shall be, and be declared by Obligee to be in default under the
      subcontract, the Obligee having performed Obligee’s obligations thereunder:

      (1) Surety may promptly remedy the default subject to the provisions of paragraph
      3 herein, or;

      (2) Obligee after reasonable notice to Surety may, or Surety upon demand of
      Obligee may arrange for the performance of Principal’s obligation under the
      subcontract subject to the provisions of paragraph 3 herein; . . . .

Doc. 1173-3 (emphasis added).
      3
             Section 10.1 of the subcontract provided:

      If [Aero] fails or neglects to carry out [its] Work in strict compliance with the
      Subcontract Documents or is otherwise in default of any of its obligations under
      the Subcontract Documents, and fails to commence and continue correction of
      such default or neglect with diligence and promptness, [Weitz] may, after 48
      hours following delivery to [Aero] of written notice thereof and without prejudice
      to any other remedy [Weitz] may have, (i) supplement [Aero’s] performance with

                                               4
                Case: 11-11191         Date Filed: 10/11/2012         Page: 5 of 7

here harmoniously in order to give effect to all provisions, as Florida law requires,

it is clear in this case that the surety, Fidelity, had a right to reasonable notice

before Weitz undertook to arrange for the performance of the work to cure the

default.4 In Dooley, the obligee/contractor proceeded under a route that did not




       additional material, supplies, equipment or labor, pay for same and deduct the
       amount so paid from any money then or thereafter due [Aero] (if such offset is not
       sufficient, [Aero] shall pay any deficiency promptly upon demand), or (ii)
       terminate [Aero’s] continuing performance under the Agreement. Termination of
       performance may be immediate (without prior notice) in the event of conditions
       hazardous to persons or property. Such termination of performance shall be
       deemed for cause, and Section 10.4 [Consequences of Termination for Cause]
       shall apply thereto.

Section 10.4 provided:

       Upon a termination of [Aero’s] continuing performance under the Agreement for
       cause, [Weitz] may, without limitation to any other available remedies, proceed as
       follows: (i) direct [Aero] to immediately leave the site, but to give possession of
       all completed materials and supplies at the site or stored off-site, to [Weitz] for
       use in completing [Aero’s] Work; . . . [Weitz] shall also provide or cause to be
       provided such other materials, supplies, tools, equipment, machinery, labor,
       services and other items necessary to complete [Aero’s] Work; or (ii) by
       registered or certified mail addressed to [Fidelity] . . . require [Fidelity] to provide
       such materials, supplies, tools, equipment, machinery, labor, services and other
       items as may be necessary to complete [Aero’s] Work in strict compliance with
       the Subcontract Documents. [Weitz] shall apply any unpaid balance of the
       Subcontract Sum to pay for such completion costs; provided, that [Weitz] may
       first require [Aero] or [Fidelity] . . . to fund any anticipated excess completion
       costs. In all such events, if the unpaid balance of the Subcontract Sum exceeds the
       costs of completing [Aero’s] Work together with interest on such costs and
       together with any offsets and deductions available to [Weitz], such excess shall be
       paid to [Aero]. However, if such costs, interest deductions and offsets exceed such
       unpaid balance, [Aero] or [Fidelity] shall pay the difference to [Weitz] upon
       demand.
       4
               See note 2, supra.

                                                  5
                 Case: 11-11191       Date Filed: 10/11/2012       Page: 6 of 7

require notice to first be given to the surety, and so the surety was not relieved of

its obligations just because the obligee/contractor failed to give notice before

undertaking to remedy the default itself. But in our case, the contract language was

written differently, and it did require that Weitz first give notice to the surety

before Weitz undertook to remedy the default itself.

       Weitz’s argument has been that it did not need to give notice before

undertaking to remedy the default itself. Accordingly, Weitz has not challenged

the district court’s conclusion it never sent “reasonable notice” to Fidelity.5

       Because Weitz was required to give reasonable notice to Fidelity before

Weitz undertook to remedy Aero’s default, and because Weitz has failed to

challenge the district court’s conclusion that Weitz never gave reasonable notice,

we agree with the district court that Fidelity is not liable on the surety bond. As

Dooley stated, under Florida law, a surety is relieved of its obligation if the

obligee/contractor fails to give the notice that is required by the bond. See Dooley,

972 So. 2d at 894.

       For the foregoing reasons, the judgment of the district court is



       5
                Weitz’s reply brief suggests that failure to thus notify a surety of default
(triggering the surety’s right to cure the default) would discharge a surety only upon a showing of
prejudice. We decline to address that argument because it was raised for the first time in the
reply brief.

                                                 6
     Case: 11-11191   Date Filed: 10/11/2012   Page: 7 of 7

AFFIRMED.