The respondents brought this action to reform a contract for getting out and delivering'to the appellant a large quantity of sawed hard-wood lumber, and in the same complaint they seek to recover damages of the defendant for a breach of such contract.
That the respondents may join two such causes of action, one in equity' and one at law, is not controverted. This court has decided that such causes of action may be joined, under the provisions of sec. 2647, R. S. Harrison v. Juneau Bank, 17 Wis. 340, 350. This court has also decided that in such actions the equitable action should be tried by the court, and the legal cause of action by the court and jury. Sec. 2843, E. S.; Harrison v. Juneau Bank, supra; Gunn v. Madigan, 28 Wis. 158, 167. In the regular order of proceeding in an action of this kind, the equitable issue for the *428reformation of the contract should be first tried by the court, and afterwards the legal issues as to the breach and damages. Hammel v. Queen Ins. Co. 50 Wis. 240. The fact that the court submitted all the issues to a jury in the first instance, and took their verdict upon such issues, was not error, as the court, after taking the verdict of the jury upon the issue upon the reformation of the contract, made and filed findings of fact and conclusions of law which sustain the judgment reforming the contract. Harrison v. Juneau Bank, 17 Wis. 340, 350.
We do not understand that the counsel make any complaint upon the regularity of the trial, but insist that there was no necessity for a reformation of the contract, claiming that it was apparent on its face when it was intended that its performance should take place. The mistake in the contract was in stating that it should be performed on or before the 1st of August, 188G, when it appeared on the face of the contract that the contract itself was made December 28, 1886, some months after its performance was required. It was claimed by the plaintiffs that there was a mistake in the date of. performance, and that it -was intended to have been written the 1st day of August, 1887, instead of 1886. We think the court was right in holding that it was necessary to reform the contract to make it conform to the agreement of the parties, before an action for its breach could be sustained. The date of performance stated in the contract being an impossible date, there was nothing to indicate when it was to be performed. Although lumbermen arid men familiar with that kind of business might infer that the date of performance intended was 1887, still there was no certainty about the matter. The date which should be inserted in the contract was the date agreed upon between the parties, and that might have been some other date as well as August 1, 1887.
The appellant alleges as error the introduction of certain *429evidence on the part of the plaintiffs, introduced to prove the agency of the person who made the contract on the part of the defendant. The contract was in fact made on the part of the defendant by one Willis S. Eeed, who claimed to be the agent of the defendant, having power to bind the defendant. There was a conflict of testimony on the subject of the agency of Eeed to make the contract on behalf of the defendant. Eeed testified that he had power to make such contract, and that he was authorized by the defendant to make it. The defendant testified that he was not authorized to bind him by contract, and that he was only sent out by him to find out what he could contract lumber for, and to report to him. Eeed testified that he was sent out to contract for the purchase of lumber to be delivered in the future, and that he was authorized to fix the price to be paid. The defendant and Eeed were the only witnesses whose testimony had a bearing upon the question of agency. In this state of the evidence the court permitted the plaintiff to show by Eeed that, shortly before and after the making of the contract in question, Eeed, as the agent and acting for the defendant, had made contracts with other parties of a like nature to the one made with the plaintiff, and that the plaintiff had recognized such contracts and performed them on his part. The contracts offered in evidence, and to which objections were taken, were all made by Eeed during a single trip made by him to the lumber regions, and both Eeed and the defendant testify that he was acting under the same instructions from the defendant at the time all the contracts offered in evidence were made. Under this state of the facts, it is not certain that there was any error in .permitting the introduction of the evidence, even on a trial b}^ jury, upon the question as to whether the defendant was bound by the contract made by his alleged agent. Chicago & N. W. R. Co. v. James, 24 Wis. 388. In this case we think the evidence as to the *430authority of the agent to make the contract was a part of the evidence upon the issue for the reformation of the contract, and not evidence addressed to the jury upon the question as to its breach and damages. Were it to be held that such evidence was not strictly admissible, still, in an equity case such error would not necessarily reverse the judgment if there is other evidence in the case sufficient to sustain the findings of the court. In this case we think the evidence quite sufficient to sustain the finding that the agent was authorized to make the contract in suit, independently of the evidence that the agent had made other co'ntracts of a like character, which had been recognized and performed by the defendant.
The only error assigned by the appellant is that the court improperly excluded evidence affecting the question of damages. The following is a copy of the contract, as reformed, upon which the claim for damages is based:
“ToRoh LaKE, Mich., Deo. 2Sth, 18S6. Phoenix Lumber Co., Milwaukee, Wis.— G-ents: We will sell you, and deliver to rail of your vessels at our dock, on or before August 1st, ’87, the following amounts and kinds of lumber, at prices we name; lumber to be log run, with mill culls and hearts out; to be measured straight; no deduction for imperfections; to be inspected and measured here within fifteen days after we report it ready; to be paid for on delivery of each cargo; we to cross-pile the lumber as sawed, and to bear half the cost of measuring and inspecting, and give vessel fair and reasonable dispatch in loading; lumber to be cut well, and also plumb in thickness, and to make a fair proportion of the maple into widths that will rip into 3-inch strips. We would want $500.00 advanced to us within thirty days:
600,000 ft. maple, @ per M. $11 00
100,000 “ elm, @ per M.'. 10 00
50,000 “ bass-wood, @ per M. 10 00
*43125,000 ft. heach, @ per M.$10 00
25,000 “ birch, @ per M. 12 00
25,000 “ ash, @ per M.1. 11 00
20,000 “ red oak, common & better, @ per M. 15 00
“Yours truly, CaMekoN Baos.
“Accepted: PiioeNix Lumber Co.
“By "W". S. Reed.”
The evidence shows that the defendant repudiated the contract, and gave the plaintiffs notice that he would not perform it as early as April, 1887, and before the plaintiffs had sawed any of the lumber, but after they had purchased the logs out of which it might have been sawed. The learned circuit judge held that the rule of damages in this case was the profit which the plaintiffs would have made on the contract had they been permitted to perform the same. The appellant claimed that he had a right to show that the plaintiffs converted the logs into lumber and sold the same during the season of 1887, and that the measure of damages was the difference between what the lumber was sold for and what the defendant had agreed to pay for it, qualified, perhaps, by the fact that the plaintiffs had been to some expense in making the other sales, and any additional cost for manufacturing the lumber in excess of what it would have cost to manufacture the lumber according to the contract.
"We think the learned circuit judge was right as to the rule of damages in this case. As said by the learned counsel for the appellant, the plaintiffs took no steps to perform the contract after they were notified by the defendant that he refused to perform it on his part. The rights of the parties under the contract were fixed at that time. Whatever the plaintiffs did with the logs after that was wholly immaterial to the defendant, except that the plaintiffs could not refuse to do anything more with the logs, and then charge the defendant in damages for their loss. That the *432profit which the plaintiffs could have made on the contract, if they had been permitted to perform the same, is the correct rule of damages, and the one most in accordance with equity, is apparent from many considerations. Suppose the defendant had notified the plaintiffs that he repudiated the contract before anything had been done under it. In such case could the plaintiffs have voluntarily gone on and got out the logs and converted them into money, and charged the defendant with the difference between the contract price and the price they sold them for? It seems to us they could not. Their loss in such case would necessarily be the price the defendant had agreed to pay for the lumber, less the cost of its production by the plaintiffs. Can they enhance such damage against the defendant by going on and manufacturing the lumber and selling it at a price which would not pay for the cost of such manufacturo, and charge the loss to the defendant? We think not. In the case of the sale of merchandise the damages a.re limited by the difference in value of the article sold and the price agreed to be paid therefor, and if the vendor retains the goods sold after the date of delivery fixed on, and after-wards sells the goods for less than they were worth at the time fixed for the delivery, he cannot charge such loss to the defaulting vendee. Chapman v. Ingram, 30 Wis. 290, 295.
The rule as held by the learned circuit judge is the one which this court has established, and is the one which is sustained by the great weight of authority. Salvo v. Duncan, 49 Wis. 151; Nilson v. Morse, 52 Wis. 255; Nash v. Hoxie, 59 Wis. 384; Jones v. Foster, 67 Wis. 296. As the plaintiffs could not enhance the damages against the defendant by their neglect to make the best of what they had on their hands, so they are not bound to lessen the damages by making other .contracts, and performing them, and giv*433ing the benefit of the performance of such contracts to the defendant.
We find no error in the record.
By the Court.— The judgment of the circuit court is affirmed.