Sanderson v. Herman

The following opinion was filed January 8, 1901:

Dodse, J.

1. In a case between these same parties relating to a former assessment upon the plaintiffs’ property of the cost of the same work now involved, it was decided that such assessment was invalid because the board of public works did not, at the time of making their assessment of benefits to result from the work to be done in pursuance with sec. 7, ch. VII, Milwaukee Charter [ch. 184, Laws of 1874, as amended], also determine and assess against the same lots the damages, costs, and charges arising from the alteration of established grade previously enacted by resolution of the common council, as required by sec. 8, ch. VIL The first question now raised is whether a situation thus arose and existed, coming within the terms of the statutes for reassessment of special assessments (ch. 262, Laws of 1897, and secs. 1210í¿-1210/?, Stats. 1898), the former of which enactments became law in April, 1897, and the latter in August, 1897. Those acts, identical as to the immediate subject, described the conditions under which reassessment should be made for work done where special assessments had been attempted as: “When such special assessment, or any special assessment certificate, tax sale, tax sale certifi*667cate or special improvement bond based thereon is or may be invalid by reason of failure to make a proper assessment of benefits and damages, or by reason of any failure to observe any provision of law, or by reason of any act or defect in the proceedings upon which such special assessment, special assessment certificate, tax sale, tax sale certificate or special improvement bond, is based.” We can entertain no doubt that the ground of invalidity of the former certificates was entirely within these laws. That ground was obviously a “ failure to observe a provision of law,” namely, the provision of sec. 8, ch. YII, requiring that determination of damages resulting from change of grade should be made at the same time that the benefits to result from the work itself are assessed. Even if, however, a narrower construction were conceded to the statute, namely, that the failure to observe a provision of law must occur in the very act of apportioning the cost after the contract has been let and the work done, still the omission to determine damages from change of grade, which under the charter should precede making the contract, would fall within the third condition of sec. 1210d. It would be “ an act or defect in the proceedings on which such special assessment, or certificate, is based.” The situation presented came clearly within the calls of the statute in question. Work of the character there described had been done, and the special assessment therefor and the certificates issued were invalid for one or more of the reasons specified. Under such circumstances the statute made the cost of the work, not exceeding net benefits ascertained by a reassessment, a lien upon the property, commanded the issue of certificates therefor, and required the inclusion and collection of the amount of such certificate as a tax.

2. Respondents, by way of objection to the reassessment itself, invoke the rule recognized in several cases in this court, that a mere arbitrary imposition is void, and point to *668the uniformity in assessments of benefits both from the work done and from the change of grade,-— $240 to each lot from the former, and $40 to each from the latter, — -as indicating that no discrimination or judgment was exercised. An examination of all the cases cited by respondent, from Johnson v. Milwaukee, 40 Wis. 315, to Hayes v. Douglas Co. 92 Wis. 429, discloses that the proposition therein decided is that the report of the assessing board must show affirmatively that they in fact considered and determined the benefits and damage to accrue to each lot, and that a merely arbitrary assessment, resulting from a rule of apportionment or of arithmetic independently of the exercise of judgment as to the actual benefit or damage, would not suffice. True, it was pointed out that uniformity of assessment was a significant circumstance, as there might be many others, to indicate an evasion of the duty of judgment as to each parcel, and to disprove such declaration in a report. See Kersten v. Milwaukee, 106 Wis. 200. Lack of such uniformity was, however, held suspicious in Johnson v. Milwaukee, supra. In no case, however, has it been held that such uniformity alone was sufficient to overcome the declarations of the officers, if any were contained in their report, though it might serve to further discredit a report and assessment which was barren of such declarations. In Hayes v. Douglas Co., supra, it was said: “ When it is required that the assessment shall be according to benefits accruing to each parcel, an assessment by the frontage rule does not show affirmatively a compliance with the statute.. While such assessment is not necessarily erroneous, it is presumed to be so, unless the return shows that the board has considered that matter and finds that the benefits are in the proportion of the frontage of each parcel.” ' In the present case the return of the board of public works expressly certifies that they did view each lot and consider and determine, as to the same, both the benefits and damages, costs, etc., less *669benefits resulting from change of grade. This official certificate is not overcome by the mere fact that each lot of the same size is determined to have received the same benefit, especially when, as her.e, it is made apparent that all the lots were used substantially alike, as a coal yard on one side of the street, and as a lumber yard on the other, and that the so-called change of grade was such as not to materially affect the accessibility, use, or value of any of them. Such extrinsic facts might not serve to supply the want of necessary averments in the report, but they are cogent to overcome other facts and circumstances by which such aver-ments are sought to be denied. Hennessy v. Douglas Co. 99 Wis. 129.

3. Next it is contended that ch. 262, Laws of 1897, and its re-enactment in secs. 1210(7-1210/’, is unconstitutional. The authority in our own state is overwhelming in support of laws authorizing reassessment both of general taxes and of special assessments. There can be no doubt that the legislature has power to ratify imposition or direct reassessment of taxes which it might originally have authorized. Cross v. Milwaukee, 19 Wis. 509; Dean v. Borchsenius, 30 Wis. 236, 247; Flanders v. Merrimack, 48 Wis. 567. Whatever construction be given to it, sec. 1210d does not transcend the power of the legislature to prescribe conditions upon which the cost of an improvement may be imposed on the property benefited. If it be urged that conditions required by the charter originally cannot now be complied with,— such, for example, as that the ascertainment of benefits and damages cannot now precede the letting of the contracts, as was obviously the policy of the charter,— it is a complete answer that the legislature might originally have authorized a special assessment without making such ascertainment an essential preliminary to contracting. Indeed, had the legislature seen fit to authorize a reassessment *670for the work in raising a street above its lawfully established grade in absence of any resolution lawfully changing the grade, how could we declare such act unconstitutional? The same imposition might have been authorized ■originally without requiring, as a condition, such preliminary action. No respect is suggested by counsel, and none ■occurs to us, wherein sec. 1210$ omits any requirement or preliminary to imposition by reassessment of the expense of public improvements which the legislature might not, in its judgment, have dispensed with as prerequisite to original ■special assessments. That being so, we cannot hold that any constitutional limit to legislative power has been transgressed.

The suggestion that ch. 262, Laws of 1897, had, before the •completion of the reassessment proceedings, been superseded by sec. 1210$, we deem of no importance. The latter is merely a substantial re-enactment of the former, and but perpetuates in existence the same legislation. The proceedings comply with both acts, and each (whichever was in force) authorized them. The fact that the report of the board declares their acts to have been done in compliance with the former act is wholly immaterial. Such declaration is not a denial that they also complied with the later one.

4. The most serious questions raised are whether, under the provisions of the Milwaukee charter, the attempted' ■change of grade by resolution, without any petition therefor, is of any force at all, and, if not of force, whether the ■city government had any jurisdiction or power to improve the street to other than the old grade at expense of the lot-owners. These questions are, however, immaterial, and their decision is not essential, for the reason that it clearly appears from the answer, entitled as it is to liberal construction and to be taken as true, that, from a practical point of view, no *671change has been made or attempted in the actual grade of the street. The increased elevation of the finished pavement was only about six inches above the old established grade, and that only in the center of the street. Such elevation, of course, did not involve expense in grading the street, but, on the contrary, avoided the expense of cutting down the old street to make room for the stones and the substratum necessary for permanently laying them, — expense which must have fallen on the lotowners had the city laid the new pavement at the exact level of the old grade. The result to the lots themselves is alleged to be without injury, cost, or inconvenience. The so-called change of grade was so slight and so without injurious effect that we must look upon it as de minimis, for which the law cares not, and for which the courts should not be troubled to seek remedy. Had the city undertaken to lay the pavement at the elevation in fact adopted, without any resolution purporting to change the established grade, no equity would have been presented in favor of the lotowners to prevent assessment of the cost upon them; and that consideration is not changed or affected by the fact that such a resolution was adopted, although the passage of the resolution might make necessary compliance with sec. 8, ch. VII, of the charter, requiring in such case an assessment of the damages, as decided in the former case.

None of the other suggestions of respondents’ counsel seem to us to call for discussion. The defect found in the first proceedings, namely, the failure to include, at the same time with the assessment of benefits from the doing of the work, an assessment of the damages caused by the ostensible change of grade, does not exist in the present proceeding. It is now found that after ascertaining such damages and deducting them from the benefits caused by the improvement the net benefits still exceed the cost of the work, which, therefore, is now reassessed against the lots. The *672reassessment proceedings are regular and comply with the directions of the charter. The facts as established by the admitted allegations of the complaint and by the answer present no equitable reason why th.e plaintiffs should not, in accordance with the policy of the charter and of sec. 1210d, Stats. 1898, pay the cost of the improvement of the street in front of their premises; it being less than the benefits conferred upon them. The conclusion is irresistible, under authority of Wells v. Western P. & S. Co. 96 Wis. 116, that a court of equity ought not to interpose in their behalf to prevent enforcement of such payment by the ordinary statutory machinery. The trial court should have refused to do so, and the judgment appealed from is erroneous.

By the Court.— Judgment reversed, and cause remanded with directions to enter judgment dismissing the complaint.

BaedeeN, J., took no part.

The following opinion wás filed February 1, 1901:

Dodge, J.

Respondents move to amend mandate so as to grant a new trial instead of ordering judgment for the defendant. This motion they predicate on the proposition that the judgment rendered by the circuit court in favor of the plaintiffs was founded upon a “ motion for judgment on the answer,” and contend that, had that motion been denied, they would then have been entitled to try the issue raised by the complaint and answer. Without considering whether that contention is correct, it suffices to point out that the situation upon which it is predicated is not shown by the record. We do not there find that there was a motion for judgment upon the answer. There is no bill of exceptions, and the judgment recites: “This cause having come on for trial before said court upon the answer of the defendant,. . . *673the court finds that all the allegations of the complaint are admitted by the answer of the defendant Henry Herman, and exhibits thereto attached, except such allegations in said complaint as are denied by said answer, and that the answer of the said defendant Henry Herman does not constitute any defense herein, and that the plaintiffs are entitled to judgment in accordance, with the prayer of the complaint.” Upon this we must rely for information as to the proceedings. Iron River v. Bayfield Co. 106 Wis. 587. No other construction can be placed upon the recitation that the cause came to trial upon the answer, than that both parties consented to treat the answer as the basis upon which trial should be had. The record discloses no objection or exception to such trial. The consent to a trial upon that basis must be construed as a stipulation that the answer is true, not alone for the purposes of a motion or for the mere consideration of its sufficiency as a pleading, such as.would be the admission in case of a demurrer, but true for the purposes of a trial from which is to result final adjudication of the rights of the parties. The trial of an action is a very different proceeding from the consideration of a demurrer or of a motion. It would be trifling with the court to invite it, by consent of counsel, to enter upon the trial of an action upon a given basis, and, when decision is reached as the result of such trial, to contend that the proceeding was tentative and experimental only. The view both of the court and of counsel for respondents is rendered apparent by the fact that, at the motion of counsel, final judgment was entered as the result of that trial. If the question submitted were, as counsel now contends, merely the sufficiency of the answer as a pleading, on resolution of which against the plaintiffs they should have a right to try the issues, the reciprocal right to the defendant of amendment in case of decision against him would seem clear, but nowhere in the *674record is suggestion that any of the parties contemplated such a privilege. "We think it plain, therefore, that the present motion of the respondents should be denied. The cause having been submitted to the circuit court for trial upon a given basis, it becomes the duty of this court, on reversing the action in fact taken by that court, to direct the action which would have been proper.

By the Court.— The motion is denied.