Bruns v. Capstick

Rombauer, P. J.

This is an action to enforce a mechanics’ lien by the contractor against the owners of the property. The claim sued for amounted in the aggregate to $1,814.57, of which amount $1,225 was claimed to be due by the terms of an express contract, and $626 for extra work, the aggregate being subject to a credit of $26.43. The petition contains biit one count, including both the express contract and the extra work, but the petition was not challenged on that account. The answer, which purports to be filed by both defendants, contains a general denial, and a counterclaim for damages caused to the defendants by non-performance of the contract. The cause was tried by the court without a jury. ’ No instructions were asked by either party, or given by the court of its own motion. The trial resulted in-a judgment for plaintiff for $1,525, and a finding for the plaintiff on the defendant’s counterclaim. It thus appears that the court found for plaintiff for the full amount of the contract price, and cut down plaintiff’s claim for extra work.to the extent of about one-half. The errors assigned are that the judgment is unsupported by substantial evidence ; that the court admitted illegal evidence for plaintiff; and that it ruled out evidence offered by the defendants, which was ' both competent and relevant.

Proceeding to examine these complaints in their inverse order, we find that the record does not contain any exception whatever to the rulings of the court in *399rejecting evidence offered; that question, therefore, is not before us for review.

The record does contain three exceptions to the admission of testimony. The first of these is to the admission of the building contract, which was objected to on the ground that it was void and uncertain, and did not show any contract in any tangible form. As the written contract was executed by the owner of the property and purported to cover the entire subject with which it deals, the objection is without merit. The second is to the admission of a plan of the building, referred to in the contract, and shown by the evidence to have been inspected by the defendants before execution of the latter instrument. This objection is also-wholly untenable. The third is to the admission of the lien account, and is the only one worthy of serious consideration.

The trial of the cause was begun on the day on which the plaintiff offered in evidence the lien account. No objection was made to the offer at the time, and the account was thereupon read in evidence. At the conclusion of that day’s proceedings, the defendants requested the court to lay over the further hearing to a subsequent day for the purpose of enabling them to adduce evidence showing the value of the extra work. The court granted the request, and postponed the further hearing of the case for the purpose indicated, and no other. On the day to which the further hearing was thus adjourned, the defendant' moved , the court to exclude from the evidence the bill of items filed with the clerk, and introduced as evidence in this case by the plaintiff ( meaning the lien account). The court refused to entertain the motion on the ground that the hearing had been adjourned for the sole purpose of enabling the defendants to adduce evidence as to the reasonable value of extra work, and the case would not be reopened for other purposes.

*400The action of the court was not erroneous. The rale in regard to objections to evidence in this state is succinctly stated in the case of Hannibal & St. Joe Ry. Co. v. Moore, 37 Mo. 341, thus: “Evidence should be admitted or excluded when it is offered on, the trial, and the bill of exceptions should show that the objections were made when the evidence was offered, and the specific ground of objections should be stated at the time, otherwise the objections will be presumed to have been waived. When evidence has been admitted with or without objection, it is proper for the court to give instructions upon the legal effect of such evidence ; and, if no sufficient evidence has been introduced to warrant the jury in finding a verdict for the plaintiff, the court may instruct the jury to find for the defendant, unless the plaintiff will take a nonsuit.”

This brings us to the controlling question, namely, whether there was substantial evidence to warrant the judgment as far as it affects the lieu. If the plaintiff failed to establish any of the essential facts which would entitle him to a mechanic’s lien, the judgment must be reversed, even though no objections were made to any part of his evidence. A judgment unsupported by substantial evidence, when challenged on that ground upon appeal from that judgment, cannot stand. The law demands that judgments should be rendered upon sufficient pleadings and substantial evidence, and when they are rendered in opposition to this rule they are judgments against the law. As there was substantial evidence that the plaintiff had performed his contract, and had done extra work at least equal in value to the amount awarded to him by the court on that account, there is nothing for review here on that branch of the case. The evidence also shows that he filed his lien account within the time required by law, and instituted his suit to foreclose his lien in due time. The only question still open is, whether such lien account was the account required by the statute.

*401The account filed is as follows:

“St. Louis, September 10, 1889.

i(3Irs. Ellen Cap stick, to Bruns & Weiss, Dr., Carpenters and Builders, 1518 Leffingwell avenue.

“May 16.

‘ ‘ Contract entered into with Mrs. Ellen Capstick, for a two-story framed house, etc., as per

plans for the sum of.......................$1,225.

(Twelve hundred and twenty-five dollars, including a two-room frame house, etc.)

“Exteas.

Porch, 2 story, 4 feet wide, 24 feet long, including painting, and stairs................. $120 00

12 openings of windows and doors at $10 each, including paint........................ 120 00

250 feet composition roofing................ 10 00

Plastering 3 rooms......................... 67 00

2,500 feet of joist siding and scantling....... 50 00

500 feet stair Y. P. flooring................. 12 00

Building permit............................ 2 00

Sliding door — extra....................... 35 00

Front porch............................ 35 00

Extra in and outside painting............... 75 00

Carpenter labor on extra 3 rooms............ 100 00

$626 00

$1,751 00

Credit by roofing paid tor by order.......... 36 43

Balance due................................1,741 57

It is evident upon an inspection of the first item of this account that it is insufficient as a matter of law. diving to the item its greatest probative force, namely,

*402that the words “contract entered into with Mrs. Ellen Capstick for a two-story frame house as per plans for the sum of $1,225,” are inferentially synonymous with “value of labor and material furnished under a contract with Mrs. Ellen Capstick for the erection of a two-story frame house as per plan, $1,225,” still the item would, under the decision of the supreme court in Rude v. Mitchell, 97 Mo. 365, and the decision of this court in Smith v. Haley, 41 Mo. App. 620, be legally insufficient as a statement of an item in a lien account. This is not a case, where the statement of the item is sufficient, and its character as a lienable item depends on outside evidence, as was the case in Schulenburg & Boeckler Lumber Co. v. Strimple, 33 Mo. App. 158, but one where the insufficient statement of the item vitiates the lien as to that item. Being an item for which a lien has not been established, it must be rejected from the account as a matter of law. The other items of the account are sufficiently stated, and, as the court specifically found on those items, we might affirm the judgment to the extent of the court’s finding on those items; their amount however is insignificant, as compared with the entire recovery, and we will not do so. Nor can we affirm the judgment as a money judgment merely against the defendant Ellen, as she is a married woman, nor against the defendant Samuel, as he is no party to the contract; nor can we make the amount of the j udgment a charge in equity upon the defendant Ellen’s property, as the necessary data for that purpose are lacking both in the pleadings and evidence. The only disposition we can make of the case is to reverse the judgment and remand the cause, so that the plaintiff may take such action in the premises as he is further advised. So ordered.

All the judges concur.