Pavarini McGovern, LLC v. Waterscape Resort LLC (In re Waterscape Resort LLC)

*604MEMORANDUM DECISION GRANTING IN PART AND DENYING IN PART PLAINTIFF’S MOTION FOR PARTIAL SUMMARY JUDGMENT

STUART M. BERNSTEIN, Bankruptcy Judge.

The plaintiff Pavarini McGovern, LLC (“Pavarini”) was retained as general contractor by the debtor and defendant Wat-erscape Resort LLC (“Waterscape”) to construct a building (the “Project”) in Manhattan. Allegedly owed approximately $11 million, Pavarini commenced this class action adversary proceeding contending that Waterscape diverted certain trust fund monies owed to Pavarini and, ultimately, the subcontractors that worked on the Project. (See Complaint, dated June 10, 2011 (ECF Doc. # 1).)1 Pavarini has moved for partial summary judgment on the first two counts of the Complaint. For the reasons that follow, the motion is granted in part and denied in part.

BACKGROUND

A. The Deal

1. The Loan Agreements

On or about June 11, 2007, U.S. Bank, National Association and USB Capital Resources, Inc. f/k/a USB Capital Funding Corp. (collectively “US Bank”) made the following loan facilities available to Water-scape to refinance pre-existing debt and fund the construction of the Project, a 45-story hotel and condominium building located at 66-70 West 45th Street in Manhattan:

_Loan_Amount_

Construction Loan $100,112,566_

Project Loan_$ 9,180,486_

Acquisition Loan2 $ 31,321,306

USB Loan$ 8,653,589

(Affidavit of Gary D. Houston in Connection with Pavarini McGovern LLC’s Motion for Summary Judgment, sworn to Aug. 8, 2012 (“Houston Affidavit ”), at ¶ 4 (ECF Doc. # 60).) The Acquisition and USB Loans were fully funded at the closing; the Construction and Project Loans were advanced as construction progressed. (Id.) The Construction Loan was to fund “a portion of the actual hard costs” (see Amended and Restated Construction Loan Agreement, dated June 11, 2007 (“Construction Loan Agreement ”), at 1, ¶ C),3 and the Project Loan was to fund “certain indirect construction costs ... that do not qualify as cost of improvements under the Lien Law.” (See Acquisition and Project Loan Agreement, dated June 11, 2007 (“Project Loan Agreement ”), at p. 1, second paragraph.)4 The Construction Loan was secured by a mortgage, and the Project Loan was secured by a Project Mortgage, Assignment of Rents and Security Agreement. (Houston Affidavit at ¶ 6.)

*6052. Funding the Project

Pursuant to the Construction Loan and Project Loan Agreements, U.S. Bank agreed to make monthly advances to Wat-erscape to fund Project costs. (See Construction Loan Agreement at §§ 3.1 & 3.2; Project Loan Agreement at §§ 3.1 & 3.2.) Waterscape requested advances by submitting monthly Draw Requests to U.S. Bank containing copies of, among other things, invoices of the Project contractors and vendors. (Houston Affidavit at ¶ 9.) The Draw Requests had to be accompanied by a Draw Request Certification that contained affirmative representations by Waterscape to U.S. Bank that, among other things, the funds being drawn would be applied to fund the Project as specified in the requisition. (Id. at ¶ 10.) Once approved, U.S. Bank transferred the funds to Waterscape.

3. The Construction Agreement

On June 28, 2007, Waterscape entered into a contract with Pavarini that designated Pavarini as the Construction Manager for the Project. (See Construction Management Agreement, dated June 28, 2007 (“CM Agreement ”).)5 Pavarini entered into subcontracts with various trade contractors and vendors to perform the necessary work. (Frederick Affidavit at ¶7.) Pavarini was responsible for managing and hiring subcontractors, and was entitled to a fee of 2.75% of the entire cost of construction exclusive of the fee itself. (See CM Agreement at Art. 9.5.1.)

Waterscape was not in privity with the subcontractors; it paid Pavarini and Pa-varini was responsible for paying the subcontractors. Pavarini agreed to provide Waterscape with the necessary paperwork to submit Draw Requests to U.S. Bank for funds with which Waterscape could make periodic payments to Pavarini as work was completed. (See id. at Art. 12.) Among other things, Pavarini was required to submit monthly requests for payment (requisitions) to Waterscape. These monthly requests constituted an express representation by Pavarini, inter alia, that to the best of its knowledge, the payment requested was for work on the Project and that the work performed thus far complied with the CM Agreement. (See id. at Art. 12.1.4.) Within five business days after receipt of Pavarini’s request for payment, Waterscape had to issue a Certificate for Payment or notify Pavarini in writing why it was withholding the Certificate. (See id. at Art. 12.2.) If Waterscape issued a Certificate of Payment, it was required to pay Pavarini within five but no later than thirty days of receipt of the Application of Payment, in full, irrespective of whether it disputed the amounts due Pavarini. (See id. at Arts. 12.3.1 & 19.5.)6 Any disputes were committed to a dispute resolution board (“DRB”). (See id, at Art. 19.5.)

B. The Dispute Between the Parties

The dispute between the parties centers on two sets of events. First, U.S. Bank funded certain requisitions but Waterscape failed to remit all of the funded proceeds *606to Pavarini. Second, Waterscape sold condominium units and paid the proceeds to U.S. Bank rather than Pavarini in satisfaction of its loan obligations. In a nutshell, Pavarini alleges that the funded requisitions and sales proceeds were trust funds under New York’s Lien Law that Water-scape illegally diverted.

1. The Funded Requisitions

Pavarini submitted forty-two correspondingly numbered requisitions to Wat-erscape. Waterscape submitted Draw Requests to U.S. Bank for the first forty requisitions. US Bank funded all or part of the forty Draw Requests, but Water-scape did not turn over the entire funded portion to Pavarini. The shortfall, $4,458,616.97 (the “Shortfall”), represents what Pavarini has characterized as diverted trust funds. (See Frederick Affidavit at ¶ 15.) Pavarini also submitted a draft of Requisition no. 41 in the amount of $815,022, which U.S. Bank did not fund and Waterscape did not pay. (Id. at ¶ 16.) On December 22, 2010, after Waterscape terminated the CM Agreement,7 Pavarini sent Requisition no. 42 in the amount of $5,145,809, and the total amount owing under all of the unpaid requisitions aggregates $10,833,132.59.8 (Id. at ¶ 17.)

Although Waterscape has not specifically accounted for the Shortfall, it has offered evidence that "it used all monies received by U.S. Bank per the Draw Requests to pay trust fund expenses. According to Waterscape, it received $85,157,163.64 in advances from U.S. Bank pursuant to the Construction Loan. (See Verified Statement Pursuant to Lien Law sworn to Nov. 11, 2011 (“Verified Statement ”), at 16 & Ex. E (p. 57 of 91).)9 It paid out the aggregate sum of $85,226,259.57 for trust fund purposes, (id. at 17 & Ex. G (pp. 59-89 of 91)), or $69,095.93 more than it drew from U.S. Bank. Pavarini concedes for the purpose of its motion that Waterscape paid this amount and that the payments were for legitimate trust fund expenditures. (See Memorandum of Law in Support of Pa-varini McGovern, LLC’s Motion for Partial Summary Judgment, dated June 25, 2012 (“Pavarini Memo ”), at 7 (see ECF Doc. # 35).)

2. The Condominium Sales Proceeds

In addition to the funded Draw Requests, Waterscape received $14,510,340.00 from the sale of certain condominium units. (See Verified Statement at 17 & Ex. F (p. 58 of 91).) As noted earlier, it paid the net proceeds to U.S. Bank at each closing to reduce U.S. Bank’s loans. (Id. at 16.) Although the Verified Statement does not indicate how the proceeds were applied, Waterscape’s disclosure statement said that they were used to pay back the *607entire principal and interest due on the Project Loan. (Debtor’s Second Amended Disclosure Statement Pursuant to § 1125 of the Bankruptcy Code, dated July 21, 2011 (“Disclosure Statement”), at 17 (ECF/Main Case Doc. # 296).) It appears that there was little if any repayment of the Construction Loan. According to the Disclosure Statement, the balance as of March 1, 2011, was $94,871,542. (Id. at 18.)

C. This Bankruptcy

Waterscape commenced this chapter 11 case on April 5, 2011. On June 9, 2011, Pavarini filed a proof of secured claim in the amount of $10,833,132.59, plus interest, and commenced this adversary proceeding the next day. The Complaint includes seven counts, but the last four were directed at U.S. Bank and have been dismissed by stipulation. (See Stipulation and Order Dismissing Claims Against U.S. Bank National Association and USB Capital Resources, Inc. f/k/a USB Capital Funding Corp., dated Aug. 13, 2012 (ECF Doc. #51).)

Three counts remain against Water-scape as well as other defendants, and Pavarini has moved for partial summary judgment on Counts I and II. In Count I, Pavarini seeks a declaration that the estate holds only bare legal title to any and all trust funds, including the Trust Assets,10 and has no equitable interest in those funds until the claims of Pavarini and the subcontractors are fully satisfied. (Complaint at ¶ 63.) Consequently, Wat-erscape should hold those funds in trust until those claims are resolved. (Id. at ¶ 66.) In Count II, Pavarini alleges that Waterscape diverted trust funds and “should be compelled to identify all trust funds that were diverted and/or distributed by them, and all such trust funds should be recovered and returned to the benefit of Pavarini and the Trade Contractors, as the trust beneficiaries.” (Id. at ¶ 80.)

Approximately one month after Pavarini commenced the adversary proceeding, Waterscape confirmed its Second Amended Plan of Reorganization (“Plan ”). (See Order Approving Disclosure Statement and Confirming Plan of Reorganization, dated July 21, 2011 (“Confirmation Order”) (ECF/Main Case Doc. # 128).)11 The Plan represented the product of substantial negotiation and comment from Pa-varini, U.S. Bank and the Court, and resolved many of the issues raised in this adversary proceeding. The Plan contemplated the sale of the hotel portion of the Project free and clear of all liens, claims and interests. (See Confirmation Order at ¶ 18.) The mechanics lien claims were placed in Class 3. (Plan at § 4.3.) All but $14 million from the hotel sale proceeds would be paid to U.S. Bank in partial satisfaction of its Class 1 claim. (Id. at § 4.1(b).) The balance would fund an $11 million Trust Fund Account for the benefit of the overlapping Class 3 Lien Law/trust fund claimants; the remaining $3 million would fund the Class 5 Reserve Account for the benefit of the unsecured creditors in that class. (Id. at §§ 4.1(b) & 5.3.)

The $11 million contribution to the Trust Fund Account was not an arbitrary amount, and reflected a settlement. Wat-erscape’s original plan essentially provided *608that all of the hotel sales proceeds would be paid to U.S. Bank in partial satisfaction of its secured claims. (See Debtor’s Plan of Reorganization, dated May 6, 2011, at § 4.1 (ECF/Main Case Doc. # 43).) Waterscape also filed a plan modification that provided that the proceeds of any condominium sales would be paid to U.S. Bank until its claims were fully satisfied. (Modification to Debtor’s Plan of Reorganization, dated May 20, 2011, at pp. 2-3 (ECF/Main Case Doc. # 68).) Pavarini objected, arguing that the trust beneficiaries held claims exceeding $10 million, the funds generated by the hotel and condominium units were trust assets, and the trust claims had to be fully satisfied from these proceeds before any monies could be distributed to U.S. Bank. (See Objections of Pavarini McGovern LLC to the Adequacy of the Debtor’s Disclosure Statement and Confirmation of its Plan of Reorganization, dated June 17, 2011, at ¶¶ 19, 21-24 (ECF/Main Case Doc. # 93).)

The dispute was eventually resolved by U.S. Bank’s agreement to carve $11 million out of the hotel sale proceeds to fund the Trust Fund Account. This sum was selected because it rounded up and therefore exceeded Pavarini’s approximate $10.8 million claim. All Class 3 claims would be deemed to be disputed, (Plan at § 4.3), and the Class 3 claimants would continue to litigate their rights primarily in non-bankruptcy fora. (Id. at § 5.6(c).) Once a Class 3 Claim was finally resolved, the claim would be allowed and receive payment from the Trust Fund Account. (Id. at § 4.3(c).)

The sale of condominium units, other than those covered in the Verified Statement, was first addressed shortly before confirmation. On May 31, 2011, the Court authorized Waterscape to consummate the pending sales of units 38A, 38B, 38C and 39B free and clear of hens, claims, interests and encumbrances, which would attach to the net proceeds thereof with the same force, effect and validity. (Order Granting Authority to Debtor to (A) Assume and Consummate Pending Sale Agreements for Condominium Units; and (B) Make and Consummate New Sales of Condominium Units, dated May 31, 2011 (“Condo Sale Order”), at ¶6 (ECF/Main Case Doc. # 82).) In addition, Waterscape was authorized to make future sales free and clear of liens, claims, interests and encumbrances at certain minimum prices without further order of the Court, with any liens, claims, interests and encumbrances similarly attaching to the net proceeds. (Id. at ¶ C.) The net proceeds would be held in a separate escrow account pending further order of the Court. (Id. at ¶ F.) Lastly, U.S. Bank and the mechanics lienors were required to deliver releases of any liens of record at the closing. (See id. at ¶ E.)

Under the Plan, the Condo Sale Order continued to govern sales under contracts entered into prior to the Effective Date. The proceeds of post-Effective Date sale contracts, as well as any remaining sale proceeds from pre-Effective Date transactions, were to be distributed pursuant to a “waterfall.” (See Plan at § 5.2(a).) Wat-erscape was required to deposit the first $2 million in the Class 5 Condominium Reserve Account, which would ultimately be transferred to the Class 5 Reserve Account for the benefit of the unsecured creditors. (Id. at § 5.2(a)(iv) & (v).) Once the Class 5 Condominium Reserve Account was fully funded, additional sale proceeds would be deposited into the Secured Claim Reserve Account for payment in order of priority, first to satisfy the balance of the U.S. Bank claims that comprised Class 1 and Class 2, (id. at § 5.2(a)(vii)), and then to satisfy the Allowed Class 3 Claims. (Id. at §§ 5.2(a)(viii) & 5.3.) After any disputed Class 3 Claims were resolved and Al*609lowed Class 3 Claims were paid in full or all mechanics liens were discharged, the Secured Claim Reserve Account would remain subject only to the Chartis Lien as defined in the Plan. (Id. at § 5.2(a)(ix).)

The sale of the hotel closed on January 20, 2012 — the Effective Date of the Plan. CSee Debtor’s Second Post-Confirmation Report and Notice of Effective Date of the Debtor’s Confirmed Second Amended Plan of Reorganization, dated Jan. 20, 2012, at ¶ 3 (ECF/Main Case Doc. # 306).) Water-scape used the proceeds from the hotel sale and pre-Effective Date condominium sales to pay U.S. Bank $109 million in partial satisfaction of its claims, fund the $11 million Trust Fund Reserve Account and fund the $3 million Class 5 Reserve Account. (Id. at ¶ 4.)

D. Pavarini’s Motion

On June 25, 2012, Pavarini moved for partial summary judgment on Counts I and II of the Complaint. As noted, the substance of Pavarini’s claims is that Wat-erscape diverted trust assets, including the Shortfall and the proceeds of the condominium sales that Waterscape admittedly paid to U.S. Bank outside of the Plan. Waterscape concedes that the money it requisitioned from U.S. Bank and the net proceeds from the sale of the condominium units constituted trust funds. (See Verified Statement at 16-17 (scheduling the payments received from U.S. Bank and the condominium sales proceeds as trust funds).) It argues, however, that it did not divert these funds because it used them to pay other trust fund obligations. Furthermore, even if it diverted trust funds, it restored the diverted funds through the establishment of the $11 million Trust Fund Account under the Plan.

Each side cites to provisions of the CM Agreement in support of their respective positions regarding, among other things, the timing of payments, the obligation to make payment notwithstanding a dispute and the right to set off. However, the parties’ contract claims have been committed for resolution to the DRB or other non-bankruptcy courts, and the Court offers no view on those issues. The Complaint raises only Lien Law questions, and the parties have not contended that the Lien Law presents a set of default rules that can be modified by contract between an owner and general contractor. Accordingly, the Court will limit the discussion to the Lien Law.

DISCUSSION

A. Standards Governing Motion

Rule 56 of the Federal Rules of Civil Procedure, made applicable to this adversary proceeding by Fed. R. BaNkr.P. 7056, governs summary judgment motions. “The court shall grant summary judgment if the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to a judgment as a matter of law.” Fed.R.CivP. 56(a).12 The moving party bears the initial burden of showing that the undisputed facts entitle it to judgment as a matter of law. Rodriguez v. City of New York, 72 F.3d 1051, 1060-61 (2d Cir.1995). Where the non-moving party would have the burden of proof at trial, the movant may obtain summary judgment by showing that “little or no evidence may be found in support of the nonmoving party’s case.” Gallo v. Pru*610dential Residential Servs., L.P., 22 F.3d 1219, 1223-24 (2d Cir.1994); accord Celotex Corp. v. Catrett, 477 U.S. 317, 322-23, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986). If the movant carries this initial burden, the nonmoving party must set forth specific facts that show triable issues, and cannot rely on pleadings containing mere allegations or denials. Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S. 574, 586-87, 106 S.Ct. 1348, 89 L.Ed.2d 538 (1986); see Celotex Corp., 477 U.S. at 324, 106 S.Ct. 2548. In deciding whether material factual issues exist, all ambiguities must be resolved and all inferences must be drawn in favor of the nonmoving party. Matsushita Elec., 475 U.S. at 587, 106 S.Ct. 1348.

The parties must cite to the parts of the record that support or undercut the assertion that a fact is not disputed. Feb. R.Civ.P. 56(c). Under our local rules, the movant must submit a “short and concise statement in numbered paragraphs” of the undisputed material facts, Bankr.S.D.N.Y. R. (“LBR”) 7056-l(b), and the opposing party must submit a statement controverting those material facts that it contends are disputed. LBR 7056-l(c). In each instance, the movant and opposing party must include a citation to admissible evidence that supports or controverts the undisputed nature of material fact. LBR 7056-l(e). The latter requirement allows the Court and the parties to focus on what is and is not in dispute, and provides a roadmap that permits the Court to go directly to the cited evidence to determine whether it supports the statement.

Neither side complied with LBR 7056-1. Pavarini submitted a twenty page, seventy two paragraph statement that contained no more than a handful of citations to any evidence submitted with the motion. {See Pavarini McGovern, EEC’s Statement of Undisputed Facts in Support of Its Motion for Partial Summary Judgment, dated June 25, 2012 {“Pavarini 7056 Statement ”) {see ECF Doc. # 35).) Waterscape’s statement failed to cite any controverting evidence although it contended that many of Pavarini’s factual statements were disputed. {See Water-scape Resort EEC’s Responses to Pavari-ni McGovern EEC’s Statement of Undisputed Facts, dated Aug. 3, 2012 (ECF Doc. # 50).) The failure to comply with LBR 7056-l(e) increased the burden on the Court by requiring it to hunt through the substantial record created by the parties to determine what was and was not in dispute. In the end, the Court has disregarded the parties’ statements, and the only undisputed facts are those identified in this opinion.

B. Disposition of the Motion

1. Introduction

Under Article 3-A of the New York Lien Law, an owner holds in trust the funds received in connection with a contract for the improvement of real property, as well as any rights of action with respect to those funds. N.Y. Lien Law § 70(1) (McKinney 2009). The assets of the trust include, among other things, the funds received and the rights of action for payment under a building loan contract, N.Y. Lien Law § 70(5)(a), and “consideration for a conveyance recorded subsequent to the commencement of the improvement and before the expiration of four months after the completion thereof.” N.Y. Lien Law § 70(5)(d). The trust comes into “existence from the time of the making of the contract ... out of which the claim arises.” N.Y. Lien Law § 71(5). It continues “with respect to every asset of the trust until every trust claim ... has been paid or discharged, or until such assets have been applied for the purposes of the trust.” N.Y. Lien Law § 70(3).

*611Trust funds must be “held and applied for the payment of the cost of improvement.” N.Y. Lien Law § 71(1). If the trustee is the owner, trust claims include “claims of contractors, subcontractors, architects, engineers, surveyors, laborers and materialmen arising out of the improvement, for which the owner is obligated, and also means any obligation of the owner incurred in connection with the improvement for a payment or expenditure defined as cost of improvement.” N.Y. Lien Law § 71(3)(a); accord N.Y. Lien Law § 2(5) (defining “cost of improvement”). The trustee holds bare legal title to the trust funds, and an equitable interest vests in the balance of the trust funds only after all trust claims have been satisfied. RLI Ins. Co. v. New York State Dep't of Labor, 97 N.Y.2d 256, 740 N.Y.S.2d 272, 766 N.E.2d 934, 938 (2002); City of New York v. Cross Bay Contracting Corp., 93 N.Y.2d 14, 686 N.Y.S.2d 750, 709 N.E.2d 459, 462 (1999); Canron Corp. v. City of New York, 89 N.Y.2d 147, 652 N.Y.S.2d 211, 674 N.E.2d 1117, 1122-23 (1996).

The use of trust funds for non-trust purposes constitutes a diversion, and if done voluntarily by the trustee, is also a breach of trust. N.Y. Lien Law § 72(1); see In re Elm Ridge Assocs., 234 F.3d 114, 125 (2d Cir.2000); Aspro Mech. Contracting, Inc. v. Fleet Bank, N.A., 1 N.Y.3d 324, 773 N.Y.S.2d 735, 805 N.E.2d 1037, 1039 (2004). The failure to maintain the books and records required by the Lien Law regarding the trust creates a presumption that trust funds have been diverted, see N.Y. Lien Law § 75(4), but the presumption is only a “permissible inference” and does not shift the burden of proof. See Truax & Hovey, Ltd. v. Grosso (In re Grosso), 9 B.R. 815, 826 (Bankr.N.D.N.Y.1981) (quoting People v. Rosano, 50 N.Y.2d 1013, 431 N.Y.S.2d 683, 409 N.E.2d 1357, 1358 (1980)). Furthermore, the trustee is not required to segregate the trust assets, and “may treat the trust funds as running bookkeeping balances rather than as segregated accounts.” Fentron Architectural Metals Corp. v. Solow, 101 Misc.2d 393, 420 N.Y.S.2d 950, 952 (N.Y.Sup.Ct.1979); accord Caristo Constr. Corp. v. Diners Fin. Corp., 21 N.Y.2d 507, 289 N.Y.S.2d 175, 236 N.E.2d 461, 463 (1968); N.Y. Lien Law § 75(1) & (2).

2. Count I

According to Pavarini’s moving memorandum of law, Count I seeks a declaration that neither Waterscape nor its estate has a vested interest in the Missing Trust Funds aggregating $14,441,244.07. (Pa-varini Memo at 10.) The Missing Trust Funds roughly correspond to the proceeds of the pre-petition condominium sales13 identified in the Verified Statement,14 (see id. at 7-8,16), and that phrase will be used throughout the balance of this opinion to refer to those proceeds.

Initially, Waterscape argues that Count I has nothing to do with the Missing Trust Funds and instead, concerns only the Trust Assets, i.e., the net proceeds from the condominium unit sales made *612pursuant to the Condo Sale Order and the net proceeds of the hotel sale contemplated under the proposed plan. The disposition of the Trust Assets is addressed by the Condo Sale Order and the Plan. The Condo Sale Order and the Confirmation Order are final and no longer subject to review. To the extent they declare rights different from the Lien Law, they govern.15

Although Waterscape is correct that Count I does not expressly refer to the earlier condominium unit sales identified in the Verified Statement, other allegations in the Complaint refer generally to the use of condominium sale proceeds to repay U.S. Bank, (Complaint at ¶¶ 48 & 49), and these allegations are incorporated by reference into Count I. (Id. at ¶ 62). These allegations are sufficient to bring the question of the Missing Trust Funds within the relief sought through Count I. Furthermore, Waterscape concedes that these condominium sale proceeds as well as the proceeds received in connection with the Construction Loan Draws constituted trust funds under the Lien Law. As such, Wat-erscape held bare legal title, and Pavarini is entitled to partial summary judgment on Count I to that extent.

3. Count II

Pavarini also seeks partial summary judgment on Count II directing Water-scape to turn over all diverted trust funds to Pavarini for the benefit of itself and the subcontractors. As noted, the so-called diverted funds fall into two categories: the Shortfall and the Missing Trust Funds. In each case, the motion presents two questions. First, has Pavarini demonstrated as a matter of law that Waterscape diverted trust funds? Second, if a diversion occurred, is Pavarini entitled to a turnover order or other relief?

a. The Shortfall

Pavarini has failed to demonstrate as a matter of law that Waterscape diverted the Shortfall. Waterscape drew $85,157,163.64 in Construction Loan proceeds from U.S. Bank, and Pavarini concedes for the purpose of its motion that Waterscape paid $85,226,259.57 in trust fund expenses, or $69,095.93 more than Waterscape received from U.S. Bank. The Lien Law “expressly vests discretion in the trustee ‘to determine the order and manner of payment of any trust claims and to apply any trust asset to any purpose of the trust,’ ” Aspro Mech. Contracting, 773 N.Y.S.2d 735, 805 N.E.2d at 1040 (quoting N.Y. Lien Law § 74(1)), and Waterscape had the discretion to use the U.S. Bank Draws to pay other trust fund expenses. Thus, even if I credited Pavarini’s contention that it is entitled to a presumption of diversion, Waterscape rebutted the presumption by offering evidence — which Pa-varini does not dispute — -that an amount greater than all of the U.S. Bank Draws was used to pay trust expenses. See Mike Bldg. & Contracting, Inc. v. Just Homes, LLC, 27 Misc.3d 833, 901 N.Y.S.2d 458, 478-79 (N.Y.Sup.Ct.2010).

Pavarini primarily relies on the provisions of the CM Agreement to argue that Waterscape was required to pay the Shortfall to Pavarini without offset and regardless of any disputes. While the failure to pay the Shortfall to Pavarini arguably breached the CM Agreement, it did not constitute a diversion or breach of trust. Furthermore, any breach claims must be pursued before the DRB.

*613Accordingly, a material factual dispute exists regarding whether Waterscape diverted the Shortfall.

b. The Missing Trust Funds

i. Diversion

According to the Verified Statement, “the net sale proceeds for each [condominium] unit after adjustments and closing costs were paid directly to [US Bank] at the closings to reduce the loan amounts.” {Verified Statement at 17.) Initially, it is no excuse that Waterscape never had possession of the Missing Trust Funds, or that they were paid directly to U.S. Bank at each closing in accordance with the parties’ loan documentation. (See Assa Affirmation at ¶ 34.) A trustee cannot avoid a diversion claim by pledging trust funds to a transferee who is not a beneficiary of the trust under the Lien Law. See Caristo Constr. Corp., 289 N.Y.S.2d 175, 236 N.E.2d at 463 (factor impermissibly received trust funds from its debtor-trustee in payment of outstanding credits); Palm Beach Realty Co. v. Kangieser, Inc., 36 Misc.2d 1058, 233 N.Y.S.2d 641, 643 (NY.Sup.Ct.1962) (use of trust funds to satisfy bank loan constituted diversion), aff'd without op., 19 A.D.2d 862, 243 N.Y.S.2d 413 (1963); cf. In re Dunwell Heating & Air Conditioning Contractors Corp., 78 B.R. 667, 671 (Bankr.E.D.N.Y.1987) (“[A] prior perfected secured creditor in accounts receivable is not entitled to its interest in that collateral until trust beneficiaries under Article 3-A of the N Y. Lien Law have been satisfied in full from those assets traceable to the improvements to which they contributed as subcontractors.”).

Although the Verified Statement did not disclose how the proceeds were allocated (which U.S. Bank obligations were paid), the Disclosure Statement revealed that they were used primarily if not entirely to satisfy the Project Loan. {Disclosure Statement at 17.) The use of trust funds to pay the Project Loan was improper, and constituted a diversion for two reasons. First, the payment of the Project Loan was not a “cost of improvement.” A “cost of improvement” includes:

sums paid to take by assignment prior existing mortgages, which' are consolidated with building loan mortgages and also the interest charges on such mortgages, sums paid to discharge or reduce the indebtedness under mortgages and accrued interest thereon and other encumbrances upon real estate existing prior to the time when the lien provided for in this chapter may attach....

N.Y. Lien Law § 2(5) (emphasis added).

According to Pavarini, the U.S. Bank mortgages did not exist prior to the time Pavarini’s rights attached. Pavarini contends that its trust claim arose when the parties signed the CM Agreement on June 28, 2007 because that is the contract out of which its claim arises. See NY. Lien Law § 71(5). The Project Loan was not recorded until July 3, 2007. Pavarini reasons that as a result, the payment of the Project Loan was not a “cost of improvement” within the meaning of the Lien Law. {See Pavarini Memo at 17; Reply Memorandum of Law in Further Support of Pavarini McGovern, LLC’s Motion for Partial Summary Judgment, dated Aug. 17, 2012, at 6-7 (ECF Doc. # 59).)

Pavarini’s argument equates the term “lien” used in section 2(5)’s definition of “cost of improvement” with the “trust claim” referred to in section 71(5). However, the two are not synonymous, and “an Article 3-A trust beneficiary does not have to have a lien or be a lienor.” Harman v. Fairview Assocs., 25 N.Y.2d 101, 302 N.Y.S.2d 791, 250 N.E.2d 209, 210 (1969); accord Ingalls Iron Works Co. v. Fehlhaber Corp., 337 F.Supp. 1085, 1091 *614(S.D.N.Y.1972) (“Under New York law, a trust beneficiary does not acquire the additional status of a mechanic’s lienor.”) Nevertheless, Waterscape has not contested Pavarini’s position, and its failure suggests that it does not dispute it. Rosenblatt v. City of New York, No. 05 Civ. 5521(GEL), 2007 WL 2197835, at *7 (S.D.N.Y. July 31, 2007) (“[p]laintiff effectively concedes defendants’ other arguments ... by her failure to respond to them”); Broad v. DKP Corp., No. 97 Civ. 2029(LAP), 1998 WL 516113, at *3 (S.D.N.Y. Aug. 19, 1998) (explaining that plaintiffs “silence” or failure to respond to defendant’s argument is a “tacit admission” thereof), aff'd 182 F.3d 898 (2d Cir.1999).

Second, even if the repayment of the Project Loan was a “cost of improvement,” the^ use of trust funds was still a diversion because U.S. Bank never filed a Notice of Lending. Section 73(2) of the Lien Law states:

In any action in which it is sought to charge a trustee personally with liability by reason of a diversion of trust assets, the trustee shall be entitled to show by way of defense that the transfer constituting the diversion was made to a transferee named in a “Notice of Lending” filed as provided in subdivision three and that the transfer was made as security for or in consideration of or in repayment of advances made to him as trustee or on his behalf as trustee in accordance with such notice of lending, and that such advances were actually applied for a purpose of the trust as stated in subdivision one or subdivision two of section seventy-one of this chapter.

N.Y. Lien Law § 73(2). The purpose of the Notice of Lending is to inform trust fund beneficiaries that trust funds may be used to repay a lender, and to that extent, will not be available to pay other trust fund beneficiaries. See Aspro Mech. Contracting, 773 N.Y.S.2d 735, 805 N.E.2d at 1040 (filing a notice of lending promotes “the legislative intent to assure ‘public notice of any transaction of the owner, contractor or subcontractor that may lead to depletion of funds available for future trust claims, even where the depletion merely repays advances that were in fact used to pay trust claims accruing at an earlier [d]ate [citation omitted].’ ”); Caristo Constr. Corp., 289 N.Y.S.2d 175, 236 N.E.2d at 466 (“The function of a notice of lending, according to the Law Revision Commission, which drafted the legislation, is to inform prospective suppliers and subcontractors that ‘trust assets receivable by the trustee at a later stage of the improvement have been anticipated for current expense’ [citation omitted].”). The repayment of such a “cost of improvement” in the absence of a Notice of Lending or other notice to trust beneficiaries precludes the trustee from asserting this defense to a claim of diversion. Spectrum Painting Contractors, Inc. v. Kreisler Borg Florman Gen. Constr. Co., 54 A.D.3d 748, 864 N.Y.S.2d 61, 62-63 (2008). Here, Pavarini contends that Waterscape never filed a Notice of Lending, and Waterscape has not disputed this either. Accordingly, this defense is not available to Waterscape.

ii. Restoration

While Pavarini has demonstrated as a matter of law that Waterscape diverted the Missing Trust Funds, Waterscape has established a defense of partial restoration. A trustee or its assignee may defend against a diversion claim by showing that the diverted funds have been restored, and that the funds are available to pay trust claims. See Caristo Constr., 289 N.Y.S.2d 175, 236 N.E.2d at 464 (if the transferee of diverted funds had used its own funds “to pay trust claims and there *615had been no loss to anyone, there would have been no ultimate diversion or loss for which the factor would be liable”) (dicta); Fentron Architectural Metals, 420 N.Y.S.2d at 953 (“If, in fact, there had been any diversion by the payment of ground rents to the owner, he more than made up for it by replacing those sums with other sums which more than restored the partially depleted trust.”); Raisler Corp. v. Uris 55 Water St. Co., 91 Misc.2d 217, 397 N.Y.S.2d 668, 674 (N.Y.Sup.Ct.1977) (“The court holds that the defendants may prove the amounts diverted were restored in such manner that the expectations of those who might look to the construction loan extended by the First National City Bank as a source of credit information were in all respects met.”); Travelers Indem. Co. v. Cent. Trust Co., 47 Misc.2d 849, 263 N.Y.S.2d 261, 265-66 (N.Y.Sup.Ct.1965) (“[I]t is proper to prove that diverted funds have been replaced and the trust purposes fulfilled [citation omitted] which amounts to a showing that a temporary diversion has been corrected.”) (decided under the prior version of the Lien Law), aff'd without op., 27 A.D.2d 803, 1967 WL 21985 (N.Y.App.Div. Feb. 16,1967).

The restoration defense is based on the principle that the “law is not designed to impose a penalty upon a violator so as to create a windfall of double repayment for creditors.” Travelers Indem., 263 N.Y.S.2d at 266; accord Raisler Corp., 397 N.Y.S.2d at 673. Moreover, voluntary restoration serves the same purpose as an order directing one liable for diversion to post security to assure the proper distribution of trust assets, or furnish assurance in any other manner that trust funds will be available to pay trust claims. N.Y. Lien Law § 77(3)(a)(v); see Palm Beach Realty Co., 233 N.Y.S.2d at 641 (directing owner who diverted trust funds to post security to protect beneficiaries’ interests pursuant to N.Y. Lien Law § 77(3)(a)(v)). In either case, the spirit of the Lien Law is fulfilled and trust beneficiaries can rely on the restored fund for the payment of their claims.

The settlement that led to the funding of the $11 million Trust Fund Account was intended to restore the trust up to that amount. That $11 million was carved out of the hotel sale proceeds to resolve Pavarini’s objections to the use of hotel and condominium sale proceeds to satisfy the U.S. Bank claims under the Plan. The amount of the Trust Fund Account was based on the amount of Pavari-ni’s claim, and reestablished the trust in a segregated account that cannot be disbursed without further Court order. The terms of the Plan also allowed Waterscape to pay the proceeds from the condominium sales governed by the Condo Sale Order and future sales to U.S. Bank.

Pavarini nevertheless contends that the restoration defense is not available unless “the [restored] funds thereby brought to the improvement are shown to have been used for the purposes of the trust.” (Pavarini Reply at 11 (quoting Raisler Corp., 397 N.Y.S.2d at 673).) Pavarini reasons that Waterscape cannot invoke the restoration defense because no part of the Trust Fund Account has yet been paid to any trust beneficiaries, but the language it quotes it misreads. As the Raisler court explained in the next sentence:

Relief in the nature of setting aside an unauthorized payment or other transfer should not be available to unpaid beneficiaries of a Lien Law trust when the assets contemplated when the work was undertaken have been fully realized, and are available in the form of present cash to meet future trust claims as they mature. To hold otherwise would be to impose a double penalty without any *616explicit statutory authority therefor, such as that found in Section 73 pertaining to the retention of trust funds by a lender in repayment of funds previously advanced.

Raisler Corp., 397 N.Y.S.2d at 673 (emphasis added).

Here, $11 million in Missing Trust Funds has been restored and is “available in the form of present cash to meet future trust claims as they mature.” If Water-scape must pay Pavarini another $11 million after escrowing $11 million from its sale proceeds for the same purpose, it will suffer a double penalty. While the Court does not condone Waterscape’s diversion, its punishment will be the costs of this litigation which, post-confirmation, will ultimately be borne by its members. See Travelers Indent., 263 N.Y.S.2d at 266 (If the defendant proves the restoration defense, “its punishment for the infraction will be the expense of this lawsuit and not liability to the plaintiff, which will have lost nothing by reason of the alleged improper financial dealings.”).

iii. The Balance of the Missing Funds

The Trust Fund Account did not fully restore the Missing Trust Funds. The condominium sales reported in the Verified Statement exceeded $11 million, and Wat-erscape has failed to offer any evidence that the net difference — $3,441,244.0716— has been restored or otherwise secured. The issue concerns the appropriate remedy.

Pavarini’s demand that Water-scape turn over any Missing Trust Funds to Pavarini is premature. The Lien Law provides security for the payment of contractor and subcontractor claims, but the right to payment depends on the law of contracts as well as the Plan. Pavarini’s Class 3 claim was deemed to be disputed, and the Plan left the resolution of those disputes to the DRB. While the Missing Trust Funds are not implicated by the express provisions of the Plan, the intent was to require the trust beneficiaries to fix their claims in non-bankruptcy fora and then to seek payment pursuant to the terms of the Plan.

Furthermore, there are other remedies that may be more appropriate to the extent that any further remedy is necessary. First, the Class 3 claimants can also look to the proceeds of future condominium sales to satisfy their claims. Waterscape stated at oral argument that the U.S. Bank debt had been refinanced, and the Class 3 mechanics lien claims now have the first right to payment from future sales of the condominium units. (Transcript of Hearing, held Aug. 21, 2012, at 6 (ECF/Main Case Doc. # 390).) Thus, there may be sufficient security or other assurances of payment that no further relief is necessary or warranted.17

Second, the Lien Law prescribes remedies for a diversion other than the immediate payment of diverted funds to trust *617beneficiaries. As noted, the Court could order Waterscape to post additional security or furnish assurances to the extent “it appears that there is danger that such assets or asset will be dissipated before judgment or diverted from trust purposes.” N.Y. Lien Law § 77(3). The Trust Fund Account cannot be disbursed absent further order of the Court and there is no danger of its dissipation. Moreover, it appears that the subcontractor claims may be subsumed within the Pavarini claim, raising a substantial question whether any further assurances are necessary.

Accordingly, while Waterscape has established only a partial restoration defense, the appropriate remedy with respect to the balance of the Missing Trust Funds cannot be determined on the state of this record. Pavarini has failed to establish as a matter of law that it is entitled to the turnover of any portion of the Missing Trust Funds at this time, and its motion for partial summary judgment is also denied to that extent.

The Court has considered the other issues raised by the parties, and to the extent not specifically addressed are found to lack merit. The parties are directed to settle a proposed order consistent with this decision and contact chambers to schedule a conference at which to discuss further proceedings in this matter.

. "ECF” refers to the docket in this adversary proceeding; “ECF/Main Case” refers to the docket in Case No. 11-11593.

. As explained in the succeeding text, the Project and Acquisition Loans were contained in a single loan agreement.

. A copy of the Construction Loan Agreement is annexed as Exhibit 1 to the Houston Affidavit. A copy of the Construction Loan Agreement and a Lien Law § 22 affidavit were filed with the New York County Clerk on June 14, 2007. (Affidavit of William Frederick in Support of Pavarini McGovern LLC’s Motion for Partial Summary Judgment, sworn to June 25, 2012 (“Frederick Affidavit"), at ¶ 6 (see ECF Doc. # 35).) The version of the Frederick Affidavit filed on the Court's Electronic Case Filing system is incomplete, unsigned and un-sworn, but the copy delivered to chambers is verified and complete.

.A copy of the Project Loan Agreement is annexed as Exhibit 2 to the Houston Affidavit.

. The CM Agreement is annexed as Exhibit 2 to the Frederick Affidavit.

. Article 19.5 of the CM Agreement provided that:

Costs for disputed Work shall be funded by [Waterscape] with the normal requisition process. Within 10 business days of the submission of a requisition [Waterscape] shall provide notice to [Pavarini] of any disputed portion of a requisition. [Water-scape] may submit the matter to the DRB for resolution. However, the subject payment will not be delayed and will be made 50% by the Owner as a Change Order and 50% from the Contingency pending resolution by the DRB....

. On September 27, 2010, Waterscape sent Pavarini a letter terminating the CM Agreement. (See Termination Letter, dated Sept. 27, 2010.) A copy of the Termination Letter is annexed as Exhibit A to the Affirmation of Solly Assa in Opposition to Motion for Partial Summaiy Judgment, dated Aug. 3, 2012 ("Assa Affirmation ”) (ECF Doc. # 48).

. On September 22, 2010, Pavarini filed a Notice of Mechanic's Lien in the sum of $12,179,601.59, an amount that reflected what was due the subcontractors and Pavarini. (See Notice of Lien, filed Sept. 22, 2010.) A copy of the Notice of Lien is annexed as Exhibit A to the Declaration of Jason B. Bailey, dated Aug. 2, 2012, which is attached to the Cross Motion for Summary Judgment filed by Jason B. Bailey on behalf of Estate Hardwood Floors Corp. d/b/a Kultar Flooring, dated Aug. 13, 2012 (ECF Doc. #52). As noted below, Pavarini filed a proof of secured claim in this case limited to the unpaid amount of the requisitions — $10,833,132.59.

.A copy of the Verified Statement is annexed to the Frederick Affidavit as Exhibit 20.

. "Trust Assets” means "the proceeds generated from the Debtor’s proposed sale of condominium units of the Project pursuant to this Court’s Order entered on May 31, 2011, and the Debtor’s proposed sale of the hotel portion of the Project, i.e., the Hotel Assets, pursuant to the Debtor’s pending Plan of Reorganization filed on May 6, 2011.” (Complaint at ¶ 46.)

. A copy of the Plan is annexed to the Confirmation Order.

. Pavarini’s motion is governed by the amendments to Rule 56 that became effective on December 1, 2010. Although some language has changed, the standard for granting summary judgment remains unchanged and nes. amendments will not "affect continuing development of the decisional law construing and applying these phrases.” Fed.R.Civ.P. 56 advisory committee’s note (2010).

. One of the condominium sales generating proceeds of $1.8 million identified in the Verified Statement actually closed on October 27, 2011, after the entry of the Condo Sale Order and confirmation of the Plan but prior to the January 20, 2012 Effective Date. (See Verified Statement, Ex. F.) Neither side commented on this "discrepancy,” and I assume the closing related to a contract that was entered into the before the Condo Sale Order.

. The Missing Trust Funds reflect the difference between the proceeds of the condominium unit sales reported in the Verified Statement ($14,510,340.00) and the trust fund expenditures made by Waterscape in excess of the U.S. Bank Draws ($69,095.93).

. Pavarini concedes that it is not relevant at this stage to determine whether the proceeds of the sale of the hotel qualify as trust funds because of the $11 million escrow carved out of those proceeds under the Plan. (Pavarini Memo at 11.)

. This amount reflects a credit to Water-scape to the extent that its payment of trust fund expenses exceeded the U.S. Bank Draws.

. I agree that Waterscape cannot offset any amounts Pavarini allegedly owes Waterscape under the CM Agreement against claims by Pavarini that Waterscape diverted trust funds because mutuality is lacking. Waterscape would owe a debt in its capacity as trustee but would have a claim under a breached construction contract. See Ross-Viking Merch. Corp. v. A. Cyanamid Co. (In re Ross-Viking Merch. Corp.), 151 B.R. 71, 74 (Bankr.S.D.N.Y.1993) (“The existence of a fiduciary duty or a trust relationship in one of the capacities of a party involved in an attempted setoff will not satisfy the concept of mutuality.”). It does not follow, however, and I do not decide whether either party can assert an offset against the other in the proceedings before the DRB.