This case was submitted on an agreed Stipulation of Facts, which was based on a complete investigation of the circumstances under which the claim arose. On or about July 15, 1968, an emergency situation arose at a building occupied by the Advance Planning Division of the State Road Commission situate at 1200 Airport Road, in Charleston, West Virginia. The septic sewer system backed up causing effluvium to over
We are of the opinion that the emergency nature of this work did not afford sufficient time to follow the usual procedures of preparing a written order and written contracts after submission of bids, and the fact that no one knows who authorized the doing of the work should not prejudice the Claimant from being paid for a prompt and satisfactory performance of what he was called upon to do for the benefit of the State Government. The efflux of sewage in an area where a hundred State employees were working created a serious health hazard and a disruption of the Commission’s activities on behalf of the State, as well as a possible danger to the general public. Time being of the essence, and the work having been done in a competent manner with the approval of the State, the Court is disposed to allow the claim in its entirety based on the reasonableness of the charge as determined by the investigation of the Respondent. It is clearly the moral obligation of the State to pay this claim, notwithstanding the technical procedures for awarding the work were not followed and the identity of the person who ordered the work cannot be established.
Claim allowed in the amount of $1200.00.