IN THE SUPREME COURT OF THE STATE OF IDAHO
Docket No. 37293-2010
THE BUILDING CONTRACTORS )
ASSOCIATION OF SOUTHWESTERN ) Boise, April 2011 Term
IDAHO, )
) 2011 Opinion No. 55
Appellant, )
) Filed: May 25, 2011
v. )
) Stephen W. Kenyon, Clerk
IDAHO PUBLIC UTILITIES )
COMMISSION and IDAHO POWER )
COMPANY, )
)
Respondents. )
)
Appeal from the Idaho Public Utilities Commission.
The order of the commission is affirmed.
Michael C. Creamer, Givens Pursley LLP, Boise, argued for appellant.
Kristine A. Sasser, Deputy Attorney General, Boise, argued for respondent Idaho
Public Utilities Commission.
Lisa D. Nordstrom, Boise, argued for respondent Idaho Power Company.
EISMANN, Chief Justice.
This is an appeal from an order of the Public Utilities Commission revising the
allowances and refunds available to developers of residential subdivisions. We affirm the order
of the Commission.
I. FACTS AND PROCEDURAL HISTORY
On October 30, 2008, Idaho Power Company filed an application with the Idaho Public
Utilities Commission seeking to modify its line extension tariff which applies to requests for
electrical service that require the installation, alteration, relocation, removal, or attachment of
Company-owned distribution facilities. The proposed modification would impact both the cost
of relocating and removing the Company’s distribution facilities and the cost of extending
service to previously unserved locations.
On December 10, 2008, Building Contractors Association of Southwestern Idaho
(“Building Contractors”) filed a petition to intervene in the proceeding, which was granted. The
City of Nampa, the Kroger Company, and the Association of Canyon County Highway Districts
also requested and were granted permission to intervene. The latter three intervenors were later
joined by the Ada County Highway District, which intervened by filing a petition for
reconsideration. This appeal does not involve the issues that these four intervenors raised.
The central issue in this case is the amount that developers must pay when the Company
constructs distribution facilities to serve the lots in a new subdivision. For simplicity, we will
only discuss charges related to installing single-phase residential service. The distribution
facilities include line extensions and terminal facilities. For residential service, the cost of
standard terminal facilities include the labor and material to install one overhead service
conductor, one 25 kVA transformer to serve a 200 amperage meter base, and the power meter.
Typically, the developer does not ask for the power meters to be installed. As homes are
constructed in the subdivision, the homeowner requests to be connected to power, and the
Company installs the drop wire from the transformer to the home and the meter at no cost to the
homeowner.
Historically, the cost of constructing new distribution facilities has been paid partially
from up-front capital contributions from developers and partially from electric rates charged to
all customers. The up-front charge is either based upon the Company’s estimate of the cost of
the particular line extension job or specified in the applicable tariff for standard tasks or
materials. The Company’s estimate was prepared before construction, and the amount charged
the developer was rarely adjusted after construction to reflect the Company’s actual cost for the
work done.
Under the prior tariff, the Company provided developers with a “line installation
allowance,” “per-lot refunds,” and a “vested interest refund” to offset a portion of the
developers’ costs incurred in having the Company construct the distribution facilities. The line
installation allowance is the portion of the estimated cost of the line extension that is funded by
the Company at no charge to the developer. Under the prior tariff, it was equal to the Company’s
cost of providing and installing overhead single-phase transformers within the subdivision. The
2
developer had to pay the additional cost for underground facilities if those were requested. The
per-lot refunds were sums refunded to the developer when a permanent residence connected to
electrical service and occupied a lot inside the subdivision within five years. The per-lot refunds
could be up to $800 each, and a single transformer could serve multiple lots depending upon
their geographic configuration. The vested interest refund was a sum the developer could
receive if another person outside the subdivision paid to connect to the line extension within five
years.
In this proceeding, the Company sought to change the line installation allowance to a
fixed sum of $1,780 for each single-phase transformer, to eliminate the per-lot refunds, and to
shorten the time period for the vested interest refunds to four years. Building Contractors sought
to increase the per-lot refunds to $1000 and to increase the time period for vested interest refunds
to ten years.
The line extension allowance for a residence that was not in a subdivision had been the
cost of standard terminal facilities plus either $1,300 for an all-electric house or $1000 for a
house that did not have electric heat. The Company asked that the allowance for such residences
also be changed to $1780 per transformer for single-phase service.
After considering written comments submitted by the parties, the Commission issued its
initial order on July 1, 2009. It granted the Company’s request to change the line extension
allowance for all residences to a fixed sum of $1780 per single-phase transformer and to
eliminate the per-lot refunds. It rejected both parties’ requests to alter the time period for
receiving vested interest refunds.
On July 13, 2009, Building Contractors filed a request for $28,386.35 in “intervenor
funding” pursuant to Idaho Code § 61-617A. That statute permits the Commission to require
certain regulated utilities to pay all or a portion of an intervenor’s legal fees, witness fees, and
reproduction costs. Building Contractors stated that the request was untimely under Commission
rules due to “the inadvertent and unintentional oversight by its legal counsel with respect to the
correct timing for submission of requests for intervenor funding,” but it requested that the
untimeliness be excused. 1 On July 22, 2009, Building Contractors also filed a petition asking the
1
The request also noted in a footnote that “Building Contractors recognizes that Idaho Code § 61-617A limits the
amount awardable as intervenor funding to $25,000.” It apparently overlooked the fact that the $25,000 limit had
been increased to $40,000 effective July 1, 2003. Ch. 41, § 1, 2003 Idaho Sess. Laws 162, 162-63.
3
Commission to reconsider its findings and conclusions regarding terminal facilities allowances,
per-lot refunds, and the time period for making vested interest refunds.
On August 1, 2009, the Commission granted Building Contractors’s motion for
reconsideration with respect to the amount of the appropriate allowances, and it denied the
motion with respect to extending the period for vested interest refunds and eliminating the per-lot
refunds. On September 3, 2009, the Commission denied Building Contractors’s request for
intervenor funding because it was untimely. On November 9, 2009, Building Contractors filed a
second request for intervenor funding.
Building Contractors submitted additional evidence and argument, and on November 20,
2009, the Commission issued its final order. It denied Building Contractors’ petition for
reconsideration and the second request for intervenor funding. Building Contractors then
appealed.
II. ISSUES ON APPEAL
A. Does the line installation allowance result in unlawful discrimination between new customers
in and outside subdivisions or between new and existing customers?
B. Is the line installation allowance supported by substantial and competent evidence?
C. Did the Commission err in denying Building Contractors’ requests for intervenor funding?
D. Is Building Contractors entitled to an award of attorney fees on appeal?
III. ANALYSIS
A. Does the Line Installation Allowance Result in Unlawful Discrimination between New
Customers in and outside of Subdivisions or between New and Existing Customers?
Building Contractors alleges that the new line extension allowance of $1,780 per single-
phase transformer violates Idaho Code § 61-315, which provides in part, “No public utility shall
establish or maintain any unreasonable difference as to rates, charges, service, facilities or in any
other respect, either as between localities or as between classes of service.”
Building Contractors argues that the new tariff “authorizes a $1,780 allowance per
transformer installed within a residential subdivision and a $1,780 allowance per customer
outside of residential subdivisions.” (Emphases in original.) According to Building Contractors,
“This arrangement patently treats customers inside and outside subdivisions disparately because
4
in a subdivision a single transformer may serve multiple (up to ten) customers if those customers
are located in sufficient proximity to each other, whereas, in the case of a single customer
requesting service outside a subdivision, a transformer will only serve that one customer.” Thus,
it asserts that the Company’s investment per electrical consumer in a residential subdivision
could be less than the investment per electrical consumer outside of a subdivision.
Idaho Code § 61-315 requires that there be no unreasonable difference as to charges
between classes of service. The class of service at issue here is constructing new distribution
facilities to extend electrical service to a previously unserved location. Each person or entity
who asks the Company to provide new distribution facilities is given the same amount as a line
extension allowance—$1,780 for each single phase transformer installed. The amount of the
allowance is the same for line extensions in subdivisions and outside subdivisions. Under
Building Contractors’ argument, a developer should receive a credit of $1,780 per lot, which
could be up to $17,800 for one transformer if it could serve residences on ten lots. As the
Commission stated in rejecting Building Contractors’ assertion that there should be a per-lot
allowance rather than a per-transformer allowance, “Permitting a per customer allowance rather
than a per transformer allowance could lead to an allowance inside subdivisions that is greater
than the cost of the terminal facilities required to provide service.” The line installation
allowance and the elimination of the per-lot refund do not violate Idaho Code § 61-315 with
respect to line extensions in and outside of subdivisions.
Building Contractors also contends that the new tariff violates Idaho Code § 61-315
because it discriminates between new and old electricity customers as to the amount that the
Company will invest in their distribution facilities. In making that argument, Building
Contractors relies upon this Court’s opinions in Building Contractors Association of
Southwestern Idaho, Inc. v. Idaho Public Utilities Commission, 128 Idaho 534, 916 P.2d 1259
(1996) (herein called Boise Water), and Idaho State Homebuilders v. Washington Water Power,
107 Idaho 415, 690 P.2d 350 (1984). In the Boise Water case, the issue was “whether in
allocating the entire increased cost of resource supply to new customers via increased hook-up
fees the IPUC regularly pursued its authority to set nondiscriminatory rates.” 128 Idaho at 538,
916 P.2d at 1263. The increased cost of resource supply was caused, in part, by new
requirements of federal law and the need to build a new water treatment plant. We held that the
increased hook-up fees for new customers violated Idaho Code § 61-315 “[t]o the extent that the
5
new hook-up fees are based on an allocation of the incremental cost of new plant construction
required by growth and by the Safe Drinking Water Act.” Id. at 539, 916 P.2d at 1264. In the
Homebuilders case, the Commission required that the power company impose upon customers a
“nonrecurring charge of $50 per installed kilowatt of capacity on all customers who installed
electric space heating, or converted to electric space heating following March 1, 1980.” 107
Idaho at 418, 690 P.2d at 353. The charge only applied to customers who had the option of
choosing either natural gas or electricity for space heating. Id. at 416, 690 P.2d at 351. The
Commission did so “to send to Water Power’s customers a price ‘signal’ which would more
accurately reflect the cost and availability of electricity.” Id. at 418, 690 P.2d at 353. We held
that “the Commission’s order, which differentiates between customers using electricity for space
heating prior to March 1, 1980, and customers who install or convert to electric space heating
after that date, is an invalid classification and violates the legislative prohibition against
discriminatory or preferential rates.” Id. at 421, 690 P.2d at 356.
In both the Boise Water and Homebuilders cases, the Commission imposed a charge on
new customers in order to pay for the increased cost of providing water and electricity
respectively to all of the utility’s customers. The charge was not based solely upon the cost of
connecting the new customers to the utilities’ distribution systems. In Homebuilders, we
expressly stated that the case “presents no factors such as when a non-recurring charge is
imposed upon new customers because the service they require demands an extension of existing
distribution or communication lines and a charge is imposed to offset the cost of the utility’s
capital investment.” Id.
There is nothing in Idaho Code § 61-315 that requires an identical per customer capital
investment by the Company, even if that were possible to achieve. For example, the
Commission’s staff prepared an analysis of the costs for providing electrical service to five
subdivisions completed under the prior tariff. The subdivisions ranged in size from 3 lots to 101
lots. The allowance for terminal facilities, and therefore the amount the Company invested to
provide them, varied from $250.71 per lot in the 101-lot subdivision to $1159.33 per lot in the 3-
lot subdivision.
As explained by the Commission: “Once new customers pay the nonrecurring
charge/line extension costs, they become existing customers and pay pursuant to the same rate
schedule as all other existing customers in their class. As such, there is no distinction between
6
new and existing customers in regard to nonrecurring rates and no rate discrimination.” Building
Contractors has failed to show that the new tariff violates Idaho Code § 61-315.
B. Is the Line Installation Allowance Supported by Substantial and Competent Evidence?
Building Contractors contends that there is not substantial and competent evidence to
support the new tariff. It argues that the Commission did not address the factors mentioned in
Homebuilders and Boise Water. In Homebuilders, we stated, “Any such difference
(discrimination) in a utility’s rates and charges must be justified by a corresponding
classification of customers that is based upon factors such as cost of service, quantity of
electricity used, differences in conditions of service, or the time, nature and pattern of the use.”
107 Idaho at 420, 690 P.2d at 355. In Boise Water we similarly stated, “Any such difference in
rates and charges must be justified by a corresponding classification of customers that is based
on such factors as cost of service, quantity of resource use, differences in the condition of service
or in the time, nature or pattern of the customers’ use.” 128 Idaho at 539, 916 P.2d at 1264.
Building Contractors alleges that there are no findings as to these factors and no evidence in the
record supporting other statements in the Commission’s orders. Whether there is substantial
evidence supporting the Commission’s findings depends upon what factual findings are
necessary to decide the issues in the proceeding.
The Commission performs legislative as well as judicial functions in its proceedings.
Rosebud Enters., Inc. v. Idaho Public Utilities Comm’n, 128 Idaho 609, 618, 917 P.2d 766, 775
(1996). When exercising its legislative function, the Commission is not bound to decide future
cases in the same way it had decided similar cases in the past. Intermountain Gas Co. v. Idaho
Public Utilities Comm’n, 97 Idaho 113, 119, 540 P.2d 775, 781 (1975). There need not be facts
in the record supporting the Commission’s policy determinations made in exercising its
legislative function. See Moon v. North Idaho Farmers Ass’n, 140 Idaho 536, 545, 96 P.3d 637,
646 (2004) (“The existence of facts supporting the legislative judgment is to be presumed.”
(quoting United States v. Carolene Prods. Co., 304 U.S. 144, 152 (1938))).
This proceeding did not involve a difference in rates or charges between or among classes
of customers. Therefore, the factors listed above in Homebuilders and Boise Water were not
relevant. Rather, the Commission made a policy change. Allowances and refunds are sums that
7
the Commission requires the Company to invest in distribution systems for new customers. 2 The
Commission had previously set the allowances and refunds so that the Company would pay to
connect a new customer an amount approximating the average amount it paid to connect an
electricity customer in the past. In a 1995 order, the Commission stated, “We find that new
customers are entitled to have the Company provide a level of investment equal to that made to
serve existing customers in the same class.” However, in this proceeding, the Commission
changed that policy. “So long as regulatory bodies adequately explain their departure from prior
rulings so that a reviewing court can determine that their decisions are not arbitrary or capricious,
orders based upon positions substantially different than those taken in previous proceedings can
be upheld.” Intermountain Gas Co. v. Idaho Public Utility Comm’n, 97 Idaho 113, 119, 540
P.2d 775, 781 (1975). In making the policy change, the Commission stated that it “is addressing
a fundamental principle of utility regulation: To the extent practicable, utility costs should be
paid by those that cause the utility to incur the costs. If the ‘cost-causers’ do not pay, the electric
rates for other customers will be higher.”
Building Contractors states that its appeal “is not premised simply on the fact that the
[new line extension] allowance is smaller than previously required, or that new customers may
pay more to extend service than existing customers who accessed service when facilities costs
were lower.” It concedes “that there will be a cost difference between what new customers pay
for line extensions as compared to old customers.” It argues that the new tariff “results in new
customers overpaying for distribution facilities, in Idaho Power over-earning on its investment to
serve those new customers, and in existing customers necessarily being subsidized in the rates
they pay.” (Emphases in original.) Thus, it contends that the new tariff violates this Court’s
opinions in Boise Water and Homebuilders.
In both Boise Water and Homebuilders, the charges at issue were not based solely upon
the cost of extending distribution facilities to new customers. Building Contractors’s argument
that new customers are “overpaying” for distribution facilities is not that they are paying more
than those facilities cost the Company to construct. The overpaying argument is simply that with
the lower amount of Company investment in distribution facilities resulting from the elimination
of per-lot refunds, the Company will receive from rates charged new electricity customers more
2
Building Contractors does not contend that there is any statute requiring the Company to invest in facilities to
connect new customers.
8
than it invested in constructing the distribution facilities necessary to connect those customers to
electrical service. Building Contractors asserts that under the former tariff the allowances and
refunds resulted in Company investment that was quite close to the “per customer embedded cost
of distribution,” but the line extension allowances under the new tariff “no longer swing around
any objective anchor that future customers, Commissions, or this Court can hold to.” (Emphasis
in original.) There is no statutory requirement that it do so.
“All charges made, demanded or received by any public utility . . . for . . . any service
rendered or to be rendered shall be just and reasonable.” I.C. § 61-301. The Commission has the
authority to determine charges that are just and reasonable. I.C. § 61-502. In these proceedings,
the Commission determined what would be a fair and reasonable allocation between the
Company and new customers of the cost of constructing the distribution facilities necessary to
connect those customers to electrical service. The Commission found that “Idaho Power’s
proposed fixed allowance of $1,780 for single-phase service and $3,803 for three-phase service
represents a fair, just and reasonable allocation of line extension costs.” Determining what is fair
and reasonable is a discretionary determination. See Quick v. Crane, 111 Idaho 759, 772, 727
P.2d 1187, 1200 (1986) (“[J]udicial discretion ‘requires an actual exercise of judgment and a
consideration of the facts and circumstances which are necessary to make a sound, fair, and just
determination, and a knowledge of the facts upon which the discretion may properly operate.’”).
Idaho Code § 61-629 provides, “The review on appeal shall not be extended further than
to determine whether the commission has regularly pursued its authority, including a
determination of whether the order appealed from violates any right of the appellant under the
constitution of the United States or of the state of Idaho.” “[I]n regularly pursuing its authority
the Commission must enter adequate findings of fact based upon competent and substantial
evidence” and “it must set forth its reasoning in a rational manner.” Washington Water Power
Co. v. Idaho Public Utilities Comm’n, 101 Idaho 567, 575, 617 P.2d 1242, 1250 (1980). Here,
the Commission’s findings as to the Company’s costs to construct distribution facilities to
connect new electricity customers were supported by substantial and competent evidence. There
is no contention that the sums that will be charged to developers for distribution facilities exceed
the Company’s costs in providing those facilities. The evidence supports the Commission’s
finding that it “is addressing distribution costs not resource costs.” The Commission also set
forth its reasoning in a rational manner for changing the allocation of those costs between the
9
Company and developers. With respect to the change in line extension allowances and refunds,
the Commission stated, “These changes relieve one area of upward pressure on rates. Moreover,
the Company’s proposal is impartial to customer class, minimizes subsidization of terminal
facilities costs, and carries the added benefit of administrative simplicity.” As explained by
Commission staff:
Each new customer that is added requires an investment in distribution plant and
terminal facilities. The new investment is undepreciated, while the investment
upon which the Company’s revenue requirement (and rates) is calculated was
both lower on a per customer basis when originally made and is now partially
depreciated. Therefore, when the new plant investment is booked by the
Company, the resulting revenue requirement is higher per customer than it was
before the new customers were connected. The Company then has two
alternatives: increase rates to all customers to cover the increased revenue
requirement, or decrease the revenue requirement by shifting more of the
investment in new distribution/terminal facilities to the customer for whose
benefit those facilities are built.
The Commission regularly pursued its authority, and there is no contention that the order
appealed from violates any of Building Contractors’s constitutional rights. We affirm the
Commission’s order adopting the new tariff.
C. Did the Commission Err in Denying Building Contractors’s Requests for Intervenor
Funding?
On July 13, 2009, Building Contractors requested intervenor funding in the sum of
$28,386.35. On September 3, 2009, the Commission denied that request as untimely under the
Commission’s rules of procedure. After the Commission had partially granted Building
Contractors’s request for reconsideration, Building Contractors filed a second request for
intervenor funding on November 9, 2009. The amount it requested was $60,965.25, which
included the sum denied in its first request. The Commission ruled that because the first request
had been denied because it was untimely filed, it would not consider those sums. It also held that
due to the granting of the reconsideration, the second request was timely filed as to the
$32,578.90 incurred during the reconsideration phase of the proceedings.
Idaho Code § 61-617A(2) provides:
The commission may order any regulated electric, gas, water or telephone
utility with gross Idaho intrastate annual revenues exceeding three million five
10
hundred thousand dollars ($3,500,000) to pay all or a portion of the costs of one
(1) or more parties for legal fees, witness fees, and reproduction costs, not to
exceed a total for all intervening parties combined of forty thousand dollars
($40,000) in any proceeding before the commission. The determination of the
commission with regard to the payment of these expenses shall be based on the
following considerations:
(a) A finding that the participation of the intervenor has materially
contributed to the decision rendered by the commission; and
(b) A finding that the costs of intervention are reasonable in amount and
would be a significant financial hardship for the intervenor; and
(c) The recommendation made by the intervenor differed materially from
the testimony and exhibits of the commission staff; and
(d) The testimony and participation of the intervenor addressed issues of
concern to the general body of users or consumers.
The Commission has discretion in determining whether to award expenses to an
intervenor under Idaho Code § 61-617A(2). Idaho Fair Share v. Idaho Public Utilities Comm’n,
113 Idaho 959, 963, 751 P.2d 107, 111 (1988) (overruled on other grounds by J.R. Simplot Co.
Inc. v. Idaho State Tax Comm’n, 120 Idaho 849, 862, 820 P.2d 1206, 1219 (1991). Because the
factors are connected by the word “and,” the Commission must find that all four listed factors
exist in order to award expenses under the statute.
The Commission found that Building Contractors’s participation did not materially
contribute to the decision rendered by the Commission. It stated that Building Contractors’s
arguments were essentially the same as it had presented in a 1995 proceeding and that the
Commission did not find them persuasive then. Building Contractors argues that it presented
evidence and arguments in this proceeding, but it has not shown how the Commission erred in
concluding that such evidence and arguments did not materially contribute to the decision
rendered by the Commission. Active participation in the proceeding is not sufficient to show
material contribution to the ultimate decision. Building Contractors argues that the Commission
misinterpreted this factor as providing that “a party only is entitled to intervenor funding if they
prevail on an issue.” (Emphasis in original.) Building Contractors does not point to any portion
of the Commission’s ruling so indicating, and we likewise have been unable to find any such
language in the Commission’s decision. Building Contractors has not shown that the
Commission abused its discretion in denying the requested intervenor expenses.
D. Is Building Contractors Entitled to an Award of Attorney Fees on Appeal?
11
Building Contractors requests an award of attorney fees on appeal pursuant to Idaho
Code § 12-117 and the private attorney general doctrine. To be awarded attorney fees under
either of those provisions, the party must be the prevailing party on appeal. Viking Constr., Inc.
v. Hayden Lake Irr. Dist., 149 Idaho 187, ___, 233 P.3d 118, 131 (2010). Because Building
Contractors is not the prevailing party on appeal, it is not entitled to an award of attorney fees on
appeal. We therefore need not address whether, had it prevailed, attorney fees could have been
awarded under either the statute or the doctrine.
IV. CONCLUSION
We affirm the order of the Public Utilities Commission, and we award respondents costs
on appeal.
Justices BURDICK, J. JONES, W. JONES, and HORTON CONCUR.
12