IN THE SUPREME COURT OF THE STATE OF IDAHO
Docket No. 36523
TERRA-WEST, INC., an Idaho corporation, )
)
Plaintiff-Respondent, )
)
v. )
)
IDAHO MUTUAL TRUST, LLC, an Idaho )
limited liability company, )
)
Defendant-Appellant, )
) Boise, August 2010 Term
and )
) 2010 Opinion No. 136
MIKE URWIN ENTERPRISES, INC., an )
Idaho corporation; RED CLIFF ) Filed: December 23, 2010
DEVELOPMENT, INC., an Idaho )
corporation; ALLOWAY ELECTRIC CO., ) Stephen W. Kenyon, Clerk
INC., an Idaho corporation; ELECTRIC )
WHOLESALE SUPPLY CO., INC., an Idaho )
corporation; KRISTEN R. THOMPSON, an )
individual; ALL PERSONS IN POSSESSION )
OR CLAIMING ANY RIGHT TO )
POSSESSION, )
)
Defendants. )
_______________________________________ )
Appeal from the District Court of the Fourth Judicial District of the State of
Idaho, Ada County. The Honorable Ronald J. Wilper, District Judge.
The order of the district court is affirmed.
Hawley Troxell Ennis & Hawley, LLP, Boise, for appellant. Ryan T. McFarland
argued.
Trout Jones Gledhill Fuhrman Gourley, PA, Boise, for respondent. Daniel L.
Glynn argued
_____________________
1
J. JONES, Justice.
Idaho Mutual Trust, LLC, appeals the order of the district court granting the motion of
Terra-West, Inc., for leave to file an amended complaint. We affirm.
I.
Background
In 2006, Red Cliff Development, Inc., contracted with Terra-West, Inc., to provide
excavation and irrigation related labor and materials for the development of a 40-acre
subdivision in Caldwell. After Terra-West commenced work on the property, Red Cliff entered
into an agreement with Mike Urwin Enterprises, Inc., wherein Urwin purchased the property and
assumed all obligations under Red Cliff‟s contract with Terra-West. Terra-West began work in
August of 2006 and performed under the contract until November 30, 2007, at which point work
was stalled until Urwin could procure governmental approval for certain irrigation projects.
On December 6, 2007, Terra-West recorded a mechanic‟s lien against the property (the
first lien) because it had not been fully compensated for its work to date under the agreement
with Urwin. Idaho Mutual Trust, LLC, had previously obtained an interest in the subject property
evidenced by a deed of trust dated February 6, 2007. Sometime after Terra-West filed the first
lien, Urwin received governmental approval to complete the work on the subdivision, and Terra-
West completed the work on May 25, 2008. Because Terra-West still had not been fully paid
under the agreement, on May 30, 2008, it filed an action to foreclose on the first lien, naming
Idaho Mutual as a party because of its interest in the property. Idaho Mutual responded by filing
a motion to dismiss pursuant to Idaho Rule of Civil Procedure (I.R.C.P.) 12(b)(6), arguing that
the lien claim was defective in that it contained an acknowledgement clause rather than an oath.
On September 3, 2008, the district court ruled in favor of Idaho Mutual, concluding that the
statement in the lien representing that the signer was “knowledgeable of the matters stated
therein and verily believes the same to be true and just” was insufficient to satisfy the
requirement in Idaho Code section 45-507(4) that the lien claimant verify by oath that he or she
believed the lien to be just. Idaho Mutual, however, was not dismissed from the case and the suit
continued on Terra-West‟s other causes of action.1
1
Terra-West‟s complaint also included causes of action for breach of contract and unjust enrichment.
2
In the meantime, on August 12, 2008, Terra-West recorded a second mechanic‟s lien
against the property (the second lien),2 encompassing all the work Terra-West had performed up
to the date of completion.3 Less than six months later,4 on January 16, 2009, Terra-West filed a
motion with the district court for leave to file an amended complaint to foreclose the second lien.
Terra-West attached a copy of the proposed amended complaint to the motion. Idaho Mutual
filed a memorandum opposing the motion for leave to file the amended complaint, arguing that
(1) the district court was jurisdictionally barred from enforcing the second lien because Terra-
West did not commence proceedings to foreclose the lien within six months of the date the
second lien was recorded as required by Idaho Code section 45-510 and (2) that the claims in the
amended complaint could not relate back to the claims asserted in Terra-West‟s original
complaint. The district court disagreed, holding that the second claim of lien “arises out of the
transaction set forth in the original pleading [the first complaint to foreclose on the first lien] and
therefore the amendment relates back to that date.” While the district court discussed whether a
motion for leave to amend a complaint is sufficient to commence proceedings in a mechanic‟s
lien foreclosure action, the district court did not reach a conclusion on that issue. The district
court granted Terra-West‟s motion to amend on April 22, 2009, and Terra-West filed the
amended complaint the following day, which was more than eight months after the second lien
was recorded. Idaho Mutual subsequently filed a motion in the district court for permission to
file an interlocutory appeal of the district court‟s order granting Terra-West‟s motion to amend,
which was denied by the district court. Idaho Mutual then sought and received permission from
this Court to file an interlocutory appeal pursuant to Idaho Appellate Rule 12.
II.
Issues on Appeal
I. Whether a motion for leave to amend a complaint “commences
proceedings” to enforce a mechanic‟s lien pursuant to Idaho Code section
45-510.
II. Whether either party is entitled to attorney fees on appeal.
2
The lien was filed eighty days after Terra-West completed work on the property, which was within the ninety-day
time limit established by Idaho Code section 45-507(2).
3
Consequently, the second lien incorporated all the work originally claimed under the first lien, from
commencement of the work in 2006 through November 30, 2007, as well as the additional work performed from the
time of the filing of the first lien through the completion of the work on May 25, 2008.
4
Specifically, the motion was filed five months and four days after the second lien was recorded.
3
III.
Discussion
A. Standard of Review
The I.R.C.P. provide that leave of court to amend a pleading shall be freely given when
justice so requires. Idaho R. Civ. P. 15(a). A district court‟s decision to grant or deny a motion to
amend a pleading is reviewed by this Court under an abuse of discretion standard. Indian
Springs, LLC v. Indian Springs Land Inv., LLC, 147 Idaho 737, 750, 215 P.3d 457, 470 (2009).
To determine whether the district court abused its discretion in granting the motion to amend, we
look at whether the district court: (1) correctly perceived the issue as one of discretion; (2) acted
within the boundaries of its discretion and consistent with the legal standards applicable to the
specific choices available to it; and (3) reached its decision by an exercise of reason. Id.
B. Timeliness
Idaho Mutual‟s interlocutory appeal is predicated upon the notion that Terra-West‟s
second lien is unenforceable because of Terra-West‟s failure to comply with the time
requirements of Idaho Code section 45-510. Under the mechanic‟s lien statute, “[n]o lien . . .
binds any building, mining claim, improvement or structure for a longer period than six (6)
months after the claim has been filed, unless proceedings be commenced in a proper court within
that time to enforce such lien.” I.C. § 45-510 (emphasis added). Idaho Mutual argues that
because the second lien was recorded on August 12, 2008, and the amended complaint seeking to
foreclose the lien was not filed until April 23, 2009, the lien no longer existed and the district
court abused its discretion in allowing Terra-West to amend its complaint. Idaho Mutual argues
that Terra-West was required to initiate a separate action by filing a new complaint to foreclose
the second lien, and then move to consolidate the second lawsuit with the pending action, in
order to commence proceedings within the statutory time period. Terra-West, on the other hand,
argues the district court was correct in holding that the second claim of lien addressed in the
amended complaint arose from the same transaction as the original complaint, and thus related
back to the date of the original pleading, which was timely filed. Alternatively, Terra-West
argues that filing the motion for leave to amend the complaint on January 16, 2009, commenced
proceedings on the second lien, thus coming within the six-month limitation under Idaho Code
section 45-510.
4
We affirm the order of the district court granting Terra-West‟s motion for leave to amend
the complaint, although not for the reason articulated by the district court. It is well-settled that
“[w]here an order of a lower court is correct, but based on an erroneous theory, the order will be
affirmed upon the correct theory.” Andre v. Morrow, 106 Idaho 455, 459, 680 P.2d 1355, 1359
(1984). The district court granted Terra-West‟s motion for leave to amend on the ground that the
second claim of lien arose out of the same transaction or occurrence as the first claim of lien and,
thus, the amendment related back to the date the original complaint was filed pursuant to I.R.C.P.
15(c). However, we affirm the district court on the ground that the filing of the motion to amend
the complaint commenced proceedings pursuant to Idaho‟s mechanic‟s lien statute.
Idaho‟s mechanic‟s lien statute does not define when proceedings are commenced to
enforce a lien, nor is there any case law in Idaho dealing with whether filing a motion to amend a
complaint commences proceedings pursuant to the statute. However, Corpus Juris Secondum,
summarizing relevant state and federal case law on the issue, states that
“when a motion to amend a complaint and a proposed amended complaint are
filed prior to the running of the statute of limitations, the motion to amend stands
in place of the actual amended complaint while the motion is under review by the
trial court, and the fact that an order granting the motion to amend is entered after
expiration of the statute of limitations does not make the amended complaint
untimely.”
54 C.J.S. Limitations of Actions § 329. See, also, Buller Trucking Co. v. Owner Operator
Independent Driver Risk Retention Group, Inc., 461 F. Supp. 2d 768, 776-77 (S.D. Ill. 2006)
(“the settled rule in both federal and state court is that a complaint is deemed filed as of the time
it is submitted to a court together with a request for leave to file the amended pleading.”).
Idaho Mutual argues that in determining when proceedings are commenced under Idaho
Code section 45-510, this Court should apply the literal wording of I.R.C.P. 3(a), which provides
in pertinent part that “[a] civil action is commenced by the filing of a complaint with the court . .
. . No claim, controversy or dispute, may be submitted to any court in the state for determination
or judgment without filing a complaint or petition as provided in these rules . . . .” Idaho R. Civ.
P. 3(a). Under Idaho Mutual‟s reading of this rule, in conjunction with Idaho Code section 45-
510, Terra-West did not commence proceedings to enforce the second lien until it filed its
amended complaint on April 23, 2009, over two months after the expiration of the six-month
period.
5
The problem with Idaho Mutual‟s argument is that it presupposes I.R.C.P. 3(a) governs
the context of when an amended complaint commences proceedings. To the contrary, the plain
language of Rule 3(a) demonstrates that the Rule is geared toward the filing of an original
complaint. Of course, the typical lien foreclosure action is commenced upon the filing of a
complaint, just as Terra-West did when it sought to foreclose its first lien. However, neither the
language in Rule 3(a), nor the commencement language in Idaho Code section 45-510,
contemplates the situation of an amended complaint. With the exception of the brief time allotted
for amending a complaint as a matter of right under I.R.C.P. 15(a),5 the first step in amending a
complaint is to request permission from the court by filing a motion for leave to amend the
complaint. Idaho R. Civ. P. 15(a). Under Rule 3(a), a plaintiff has unilateral control over the
timing of the original complaint and bears the responsibility of commencing the proceeding
within the applicable time limitation. However, in the context of an amended complaint, the
plaintiff only has unilateral control over the timing of the filing of the motion for leave to amend,
but does not have unilateral control over when the motion may be granted.
The plaintiff has no way of controlling or even predicting the time at which any
permission to amend will be granted, and thus no ability to control the date on
which the amended complaint itself may be filed. It may take only a matter of
days before the motion is allowed and the complaint can be filed, but it may be a
matter of weeks, or even months, depending on a host of factors, all of which are
outside the plaintiff‟s control.6 If the [time limitations] cannot be satisfied until
the later filing of the amended complaint after the motion to amend has been
allowed, the [limitation] period will effectively be shortened by some
unpredictable amount of time, as a plaintiff would have to file the motion to
amend some considerable period in advance of the expiration of the [limitation]
period and simply hope that the court‟s ruling would be sufficiently prompt. It is
only that first step, the filing of the motion, that the plaintiff can control. Thus, the
filing of the motion is comparable to the original filing of the complaint, both in
the sense that each is the first step that a plaintiff takes and the first document that
a plaintiff files with the court concerning the action, and in the sense that both the
filing of the original complaint and the filing of the motion to amend are steps that
remain unilaterally in the plaintiff‟s control.
5
I.R.C.P. 15(a) provides “[a] party may amend the party‟s pleading once as a matter of course at any time before a
responsive pleading is served . . . . Otherwise a party may amend a pleading only by leave of court or by written
consent of the adverse party. . . .” Idaho R. Civ. P. 15(a).
6
The facts of this case illustrate this point perfectly. The district court, in its order granting Terra-West‟s motion,
indicated that it had “received and reviewed the motion before the mechanics lien statutorily expired, although oral
argument was not heard until after that date.” This demonstrates that all parties were ready to proceed on Terra-
West‟s motion before the six-month time period expired, and the only issue was getting the hearing set on the
calendar, which of course, was beyond Terra-West‟s control.
6
Nett v. Bellucci, 774 N.E.2d 130, 136 (Mass. 2002). In sum, there is a substantial difference
between the procedure for filing an original complaint under I.R.C.P. 3(a) and the procedure for
filing an amended complaint pursuant to I.R.C.P. 15(a).
Idaho Mutual argues that the better rule is to require the plaintiff to initiate a separate
foreclosure action and consolidate the cases in order to satisfy the timeliness requirements of
Idaho Code section 45-510. Idaho Mutual notes that:
Terra-West could have timely filed a separate action to foreclose the [s]econd
[l]ien. It also could have moved to consolidate that separate action with this one.
That approach would have avoided the expiration of the [s]econd [l]ien while
Terra-West‟s motion to amend was pending. Instead, Terra-West chose to follow
[a] needlessly risky path . . . .
The approach advocated by Idaho Mutual is contrary to the principles of judicial economy and
practicality. Requiring a plaintiff to file a separate action, followed by a motion to consolidate, in
order to meet the statutory time requirement, would create needless confusion and duplication in
the perfection of a mechanic‟s lien. It is this Court‟s responsibility to interpret statutes, and in
doing so, we must construe statutes so as to give effect to the legislative intent. State v. Payne,
146 Idaho 548, 575, 199 P.3d 123, 150 (2008). Because Idaho‟s mechanic‟s lien statute is
constitutionally mandated (IDAHO CONST., art. XIII, § 6) and intended to be liberally construed in
favor of lien claimants (Pierson v. Sewell, 97 Idaho 38, 41, 539 P.2d 590, 593 (1975)), it is
doubtful that the additional procedural hurdles suggested by Idaho Mutual were intended by the
Legislature.
While the Legislature has the power to enact substantive laws, the Supreme Court has the
inherent “power to fashion the procedures necessary to perform [its] duties.” City of Boise v.
Ada County, 147 Idaho 794, 802, 215 P.3d 514, 522 (2009). In that case we observed:
“[T]he Legislature has recognized the courts‟ inherent power in this regard by
enactment of [Idaho Code] section 1-1622 [which] provides:
When jurisdiction is, by this code, or by any other statute,
conferred on a court or judicial officer all the means necessary to
carry it into effect are also given; and in the exercise of the
jurisdiction if the course of proceedings be not specially pointed
out by this code, or the statute, any suitable process or mode of
proceeding may be adopted which may appear most conformable
to the spirit of this code.”
7
Id. at 803, 215 P.3d at 523. In other words, because the Legislature is silent on this issue, it is this
Court‟s responsibility to apply a meaning of “commence proceedings” that is consistent with the
spirit and policy of Idaho‟s mechanic‟s lien statute. Under the approach urged by Idaho Mutual,
a plaintiff would inevitably be forced to incur additional litigation costs associated with filing a
separate action and scarce judicial resources would be wasted by adding an unnecessary case to
the court‟s calendar.
Moreover, the approach suggested by Idaho Mutual has been rejected by federal courts
applying analogous rules of federal procedure. This Court has previously recognized that federal
case law provides persuasive authority when interpreting rules under the I.R.C.P. that are
substantially similar to rules under the F.R.C.P. Black v. Ameritel Inns, Inc., 139 Idaho 511, 515,
81 P.3d 416, 420 (2003); see also Chacon v. Sperry Corp., 111 Idaho 270, 275, 723 P.2d 814,
819 (1986) (noting that whenever possible, the Court should “interpret[] our rules of civil
procedure in conformance with the interpretation placed upon the same rules by the federal
courts.”). The text of F.R.C.P. 3, which states “[a] civil action is commenced by filing a
complaint with the court,” is nearly identical to the text of I.R.C.P. 3(a).
An analysis of federal cases dealing with the interplay between F.R.C.P. 3 and the effect
of filing a motion for leave to amend a complaint supports the conclusion that a motion for leave
to amend commences proceedings. For example, in Mayes v. AT&T Info. Sys., Inc., the plaintiff
filed a motion for leave to amend the complaint and attached a copy of the amended complaint to
the motion. 867 F.2d 1172, 1173 (8th Cir. 1989). The motion was later granted, but the amended
complaint was not filed until six days after the statute of limitations for the plaintiff‟s cause of
action had expired. Id. The court recognized the requirement in F.R.C.P. 3 for commencing an
action, but noted that the procedure for filing an amended complaint was different because filing
an amended complaint requires leave of the court. Id. The court ultimately held that “the
amended complaint [was] deemed filed within the limitations period.” Id. See also Moore v.
State, 999 F.2d 1125, 1131 (7th Cir. 1993) (“As a party has no control over when a court renders
its decision regarding the proposed amended complaint, the submission of a motion for leave to
amend, properly accompanied by the proposed amended complaint that provides notice of the
substance of those amendments, tolls the statute of limitations, even though technically the
amended complaint will not be filed until the court rules on the motion.”); Rademaker v. E.D.
Flynn Export Co., 17 F.2d 15, 17 (5th Cir. 1927) (holding that a motion to amend “stands in the
8
place of an actual amendment.”); Longo v. Pennsylvania Elec. Co., 618 F. Supp. 87, 89 (W.D.
Pa. 1985) (“The timely filing of [the] Motion to Amend and not the final court approval was
sufficient to meet the requirement of FED. R. CIV. P. 3 that „a civil action is commenced by the
filing of a complaint with the court.‟”).7
An important part of the analysis in many of the cases discussed above involves whether
the defendant had notice of the substance of the proposed amendment prior to expiration of the
statutory time period either because the plaintiff had attached the amended complaint to the
motion for leave to amend, or because the text of the motion itself detailed the substance of the
proposed amendment. For example, in Moore, the court found it necessary that the motion for
leave to amend be “properly accompanied by the proposed amended complaint,” so as to provide
“notice of the substance of those amendments.” 999 F.2d at 1131. Similarly, in Rademaker,
central to the court‟s analysis was that the defendant had been served with the motion prior to the
expiration of the statute of limitations, and the motion “fully and comprehensively” laid out the
substance of the proposed amendment. 17 F.2d at 17.
In this case, because Idaho Mutual was not dismissed from the case following the
invalidation of the first lien, the motion for leave to file the amended complaint gave notice to
Idaho Mutual within the six-month jurisdictional time limit that Terra-West was seeking to
foreclose the second lien. Terra-West served Idaho Mutual with the motion pursuant to I.R.C.P.
5(a), which requires a party filing a motion for leave to amend to serve the written motion on
each party to the case affected by the motion. Idaho R. Civ. P. 5(a). Furthermore, the proposed
amended complaint was attached to the motion for leave to amend, which further demonstrates
that Idaho Mutual had notice of the commencement of the foreclosure action within the six-
month time limitation.
Idaho Mutual argues that many of the cases cited above are distinguishable because they
involve statutes of limitations, whereas this case deals with a strict jurisdictional bar. More
specifically, Idaho Mutual argues that Idaho Code section 45-510 is not a mere statute of
limitations, but rather acts as a jurisdictional bar because the lien is void for all purposes if not
brought within the time designated by the statute. However, this argument is without
7
The view that proceedings may be commenced by filing a motion to amend has also been adopted by many state
courts. See, e.g., Mauney v. Morris, 340 S.E.2d 397, 400 (N.C. 1986) (finding that filing a motion to amend “is
sufficient to start the action.”); Frazier v. East Tenn. Baptist Hosp., Inc., 55 S.W.3d 925, 930 (Tenn. 2001) (holding
that a motion to amend “stands in the place of the actual amended complaint.”). Idaho Mutual has not cited any case
on point holding otherwise from Idaho or any other jurisdiction.
9
consequence because the lien claimant preserves the court‟s jurisdiction by commencing
proceedings through the filing of the motion to amend the complaint. Therefore, the analysis of
what step commences an action brought by way of an amended complaint is not affected by
whether the deadline for commencing the action is set by a statute of limitations or some strict
jurisdictional bar. Idaho Mutual may be correct in arguing that this case is distinguishable from
those cases holding that filing a motion for leave to amend tolls the running of the statute of
limitations because the jurisdictional bar in Idaho‟s mechanic‟s lien statute cannot be tolled.
However, in coming to our holding today, we find that the filing of the motion to amend
commences the action and stands in the place of the amended complaint, which is different than
concluding that the statutory time period under Idaho Code section 45-510 is tolled.
Idaho Mutual also points to this Court‟s decision in Griggs v. Nash, 116 Idaho 228, 775
P.2d 120 (1989), in support of the proposition that Idaho has already decided that an action
added by amended complaint is not commenced until the amended complaint itself is filed with
the court. In that case, two defendants moved for leave of court to file a third-party complaint
against an attorney for legal malpractice. Id. at 234, 775 P.2d at 126. The motion for leave was
made within the two-year statute of limitations, but the district court did not rule on the motion
until eight months later, after the limitations period had expired. Id. Citing I.R.C.P. 3(a), this
Court held that the action was not commenced until the third-party complaint was actually filed
with the court. Id.
However, our decision in Griggs is distinguishable from the case at bar because it
concerned the timeliness of a third-party complaint, which is categorically different than a
motion to amend to add a new claim against a party who is already part of the action. In the
context of a third-party complaint, there may be good reason to prefer the more cumbersome
method of requiring the filing of an independent action against the third party to commence the
proceedings. Under I.R.C.P. 14(a), a motion for leave to file a third-party complaint, even if the
proposed complaint is attached to the motion, does not give any notice to the third party that it
may be subject to an impending action. Because the third party would not be served with the
motion for leave to file a third-party complaint, the third party may discover, after the expiration
of the applicable statute of limitations, that a previously filed motion to which the third party had
no notice, commenced the proceedings. Such a rule is contrary to the purposes of any statute of
limitations, which functions to prevent stale claims and to protect a defendant‟s reasonable
10
expectation that his earlier conduct can no longer give rise to liability. See Hawley v. Green, 117
Idaho 498, 501, 788 P.2d 1321, 1324 (1990). However, the same rationale does not apply in this
case. As mentioned above, Idaho Mutual was served with the motion for leave to amend, as well
as the proposed amended complaint. Idaho Mutual, unlike a party that has not yet been joined,
had notice of the substance of the proposed amendment before the six-month period expired
under Idaho Code section 45-510. Consequently, Griggs is distinguishable because this case does
not present the same notice concern.
Finally, Idaho Mutual argues that permitting Terra-West to foreclose the second lien,
which incorporates all the work originally claimed under the first lien, as well as the additional
work completed after the filing of the first lien, is tantamount to permitting Terra-West to revive
an invalid lien. However, Terra-West is not prohibited from foreclosing the second lien, even
though it encompasses work originally claimed under the first invalid lien. In White v.
Constitution Mining & Mill Co., we held that a mechanic‟s lien, “if any exists at all, relates back
to the date of the commencement of the work or improvement or the commencement to furnish
the material.”8 56 Idaho 403, 420, 55 P.2d 152, 160 (1936). In that case, several employees filed
a mechanic‟s lien against the property of their employer, the mining company, for unpaid salaries
pursuant to an employment contract. Id. at 407, 55 P.2d at 153−54. Prior to the employees
actually filing the lien, a judgment creditor of the mining company levied an attachment on the
mining company‟s property. Id. at 407, 55 P.2d at 153. The employees subsequently brought a
suit to foreclose on the lien, and the court entered a judgment in their favor for the amounts
claimed. Id. at 408, 55 P.2d at 154. However, the court also found that the portion of the
judgment covering wages earned prior to the attachment by the judgment creditor was superior to
that of the judgment creditor‟s claim, but the portion covering work performed after the
attachment was inferior to the judgment creditor‟s claim. Id. We reversed the trial court‟s
decision, finding that the employees‟ liens were not affected by the judgment creditor‟s
attachment and the whole amount claimed by the employees was superior. Id. at 425, 55 P.2d at
162. Central to our analysis was the fact that all of the work claimed under the mechanic‟s lien
was completed pursuant to one continuous employment contract, and therefore, the lien attached
at the time the work began and encompassed all work subsequently done under the contract. Id.
8
The phrase “relates back” as used in this case should not be confused with the phrase “relate back” as used when
applying the relation-back doctrine pursuant to I.R.C.P 15(c).
11
Pursuant to this analysis, so long as a lien is filed within ninety days after the completion
of the labor or services, the lien may encompass the entirety of the work performed under a
single contract. The fact that a lien claimant previously attempted, but failed, to file a lien under
the same contract does not prohibit that same party from filing and foreclosing a second lien. In
other words, the lien attaches at the time that work is commenced under a contract, and if all
work is completed pursuant to that same contract, a lien claimant may file a mechanic‟s lien
encompassing all such work so long as the statutory guidelines are fulfilled. Thus, in this case,
the existence of the first invalid lien is wholly irrelevant, other than to provide the forum upon
which Terra-West could file a motion to amend the original complaint. All of the work that
Terra-West claimed when filing both the first lien and the second lien was done pursuant to one
contract. Consequently, Terra-West is not prohibited from filing and foreclosing the second lien
even though it encompassed work claimed under the first invalid lien.
Therefore, we conclude that Terra-West‟s motion for leave to amend the complaint
commenced proceedings within the statutory time period pursuant to Idaho Code section 45-510,
and Terra-West is not barred from filing and foreclosing the second lien. We find this conclusion
is supported by the majority of federal and state courts, and is consistent with this Court‟s stated
policy that lien statutes are to be liberally construed “so as to effect their objects and promote
justice.” Metro. Life Ins. Co. v. First Security Bank of Idaho, 94 Idaho 489, 493, 491 P.2d 1261,
1265 (1971). Other than pointing to the most conservative interpretation of I.R.C.P. 3(a) and the
strict jurisdictional limitations of Idaho‟s mechanic‟s lien statutes, Idaho Mutual has not
articulated a compelling rationale for preferring the more cumbersome method of initiating a
new proceeding and consolidating the cases. The more efficient procedural route of moving the
court for leave to file the amended complaint gives effect to the objects of the mechanic‟s lien
statute and avoids any unnecessary and inefficient procedural maneuvering. Thus, the district
court did not abuse its discretion in granting Terra-West‟s motion for leave to amend the
complaint.
C. Attorney Fees
Both parties argue that they are entitled to attorney fees under Idaho Code section 12-
121. However, “where the appeal is interlocutory in nature and the action will be remanded for
further proceedings, neither party is the prevailing party on appeal.” Doe v. Boy Scouts of Am.,
148 Idaho 427, 431, 224 P.3d 494, 498 (2009). Because we do not yet know who will ultimately
12
prevail in this action, any determination of the prevailing party is premature. City of McCall v.
Buxton, 146 Idaho 656, 667, 201 P.3d 629, 640 (2009). When the district court makes its
prevailing party determination on remand, any award of attorney fees made then may include
attorney fees for this appeal. Lexington Heights Dev., LLC v. Crandlemire, 140 Idaho 276, 287,
92 P.3d 526, 537 (2004).
IV.
Conclusion
Therefore, we conclude that the filing of the motion for leave to amend the complaint
commenced proceedings within the statutory time period and we therefore affirm the order of the
district court granting leave to file the amended complaint. Costs to Terra-West.
Justices BURDICK and HORTON CONCUR.
Chief Justice EISMANN, dissenting.
Idaho Code § 45-510 provides insofar as is relevant, “No lien provided for in this chapter
binds any building, mining claim, improvement or structure for a longer period than six (6)
months after the claim has been filed, unless proceedings be commenced in a proper court within
that time to enforce such lien . . . .” The issue is the meaning of the words “proceedings be
commenced.” The majority holds that filing a motion to amend a complaint constitutes
commencing proceedings to foreclose a mechanic‟s lien. Because that holding conflicts with our
opinion in Griggs v. Nash, 116 Idaho 228, 775 P.2d 120 (1989), and with the unambiguous
wording of the statute, I respectfully dissent.
In Griggs v. Nash, 116 Idaho 228, 775 P.2d 120 (1989), two defendants in a lawsuit filed
a motion for leave to file a third-party complaint on January 29, 1987. Under the facts in the
record, the two-year statute of limitations would run on their third-party claim on September 9,
1987. Id. at 234, 775 P.2d at 126. The trial court signed an order granting the motion on
September 8, 1987, but the defendants did not file their third-party complaint until September 23,
1987, after the statute of limitations had run. This Court held that the cause of action was barred
by the statute of limitations, reasoning as follows:
On January 29, 1987, EMSI and Van Gelder filed a motion pursuant to
I.R.C.P. 14(a) for leave to file a third-party complaint against Trout. A copy of
the third-party complaint was attached to the motion. On September 8, 1987, the
13
trial court signed an order granting EMSI and Van Gelder leave to file their third-
party complaint. The order was filed on September 10, 1987. The third-party
complaint was filed on September 23, 1987. Pursuant to I.R.C.P. 3(a), an action
is commenced by the filing of a complaint. Therefore, the action contained in the
third-party complaint was not commenced until September 23, 1987. This was at
least 14 days after the two-year statute of limitations had run. Therefore, we
affirm the trial court‟s ruling that the third-party complaint was barred by I.C. § 5-
219(4).
Id. (emphasis added).
There is no material difference in the wording of the relevant statute in Griggs and the
wording of the mechanic‟s lien statute in this case. In Griggs, the action had to be “commenced
within the periods prescribed in this chapter after the cause of action shall have accrued.” Idaho
Code § 5-201 (emphasis added) Under the mechanic‟s lien statute, the lien expires “unless
proceedings be commenced in a proper court within [six (6) months after the claim has been
filed] to enforce such lien.” Idaho Code § 45-510 (emphasis added). Griggs cannot be logically
distinguished on the ground that it was a motion to file a third-party complaint. In that case, a
motion to amend a pleading was not the commencement of an action, and in this case the motion
to amend a pleading likewise cannot be the commencement of foreclosure proceedings. The
argument regarding no control over how long it would take the trial court to rule upon the motion
to amend applies equally in both situations.
The majority seeks to distinguish Griggs and this case by arguing that the third party in
Griggs had no notice of the pending litigation while in this case Idaho Mutual had notice that
Terra-West at least intended to foreclose its first lien. Our prior cases do not support a
distinction based upon that rationale.
In Willes v. Palmer, 78 Idaho 104, 298 P.2d 972 (1956), a contractor filed a claim of lien
to secure the unpaid balance owing him for work done on the residence of a married couple. The
wife “was present during most of the time the work was being done and directed that
considerable of the additions be included.” Id. at 107, 298 P.2d at 973. The contractor later
timely filed an action to foreclose the lien, but named only the husband as a defendant. At the
commencement of the trial, the contractor was permitted by the trial court to amend his
complaint by adding the wife as a defendant. She obviously knew of the proceedings because
she was personally present at the trial, joined in the answer filed by her husband, and elected to
proceed with the trial rather than have a continuance to prepare. Id. She and her husband
14
appealed a judgment in favor of the contractor and argued that the lien could not be foreclosed
because she was made a party after the statutory duration period of the lien had expired. This
Court agreed, holding, “The action not having been brought against [the wife] within the six
month period, the lien as to her interest in the property was wholly lost.” Id. at 108, 298 P.2d at
974. In addition, we held “that the half interest of the husband could not be severed from that
of the wife by foreclosure and sale to satisfy the mechanic‟s lien, and that . . . the right to
foreclose as to the husband‟s interest must also be denied.” Id. at 109, 298 P.2d at 975. This
Court did not inquire as to when the wife learned of the foreclosure proceedings.
In Boise Payette Lumber Co. v. Weaver, 40 Idaho 516, 234 P. 150 (1925), the lumber
company, the plumbing and heating contractor, and the builder were all unpaid after completion
of a home. The contractor and builder filed mechanic‟s liens, but the lumber company instead
took a promissory note secured by a mortgage on the home. The lumber company filed an action
to foreclose its mortgage and made the lien claimants defendants. They filed answers and cross-
claims upon their respective liens, but the contractor did not file a cross-complaint against the
landowner to foreclose his mechanic‟s lien until more than six months after he had filed his
claim of lien. Prior to the expiration of that six-month period, he and the landowner had filed a
written stipulation that the time for foreclosing his lien could be extended for six months. This
Court held that the contractor had lost his lien. We stated, “The time within which an action to
enforce a lien can be commenced after the lien has been filed cannot be extended, as against
another incumbrancer, by an agreement between the lienor and the owner to extend the time of
payment.” Id. at 521, 234 P. at 152. Even though the contractor had filed a cross-claim against
the mortgagee regarding his lien, he lost his lien because he had not also timely filed a cross-
claim against the landowner, who was a party to the litigation and would have known of the
cross-claim against the mortgagee. Based upon the stipulation, the landowner also obviously
knew that the contractor intended to foreclose his lien.
The majority also contends that because this is remedial legislation, we need not follow
the statute as written. That is inconsistent with the above cases and is inconsistent with the
nature of the mechanic‟s lien. The statute clearly states that the lien expires unless a pleading to
foreclose the lien is filed within the statutory period.
In Western Loan & Building Co. v. Gem State Lumber Co., 32 Idaho 497, 185 P. 554
(1919), the landowner granted a mortgage covering a city lot, and the mortgage was duly
15
recorded. About five months later, a supplier who had furnished construction materials used in
constructing a building on the lot recorded a claim of lien, and the supplier later timely
commenced an action against the landowner to foreclose the lien. The supplier did not name the
mortgagee as a defendant in that action. After the time for foreclosing the lien had expired, the
mortgagee filed an action to foreclose its mortgage. The supplier answered and filed a cross
claim to foreclose its lien. This Court held, “As against the mortgage lien, the lien for material
furnished, if any existed, is lost, because the action to foreclose the same was not commenced
within the time limited by the statute.” Id. at 500-01, 185 P. at 555 (emphases added). This
Court went on to explain, “The limitation prescribed by statute of the time within which an
action must be brought in a proper court for the foreclosure of a mechanic’s lien is not the
ordinary statute of limitation, which is waived, if not pleaded.” Id. at 501, 185 P. at 555
(emphasis added). Rather, “„The time within which the suit must be brought operates as a
limitation of the liability itself as created, and not of the remedy alone. It is a condition attached
to the right to sue at all.‟” Id. (quoting from The Harrisburg, 119 U.S. 199, 214 (1886))
(emphasis added).
In the similar case of Palmer v. Bradford, 86 Idaho 395, 388 P.2d 96 (1964), mortgagees
brought an action to foreclose their mortgage, and they named as a defendant the supplier who
had filed a claim of lien against the property but had not commenced an action to foreclose its
materialman‟s lien. During the succeeding two and one-half years after the claim of lien had
been filed, the landowner had made six, semiannual payments of $1.00 each to the supplier. The
supplier believed that those payments repeatedly extended the time within which to foreclose its
lien pursuant to that portion of Idaho Code § 45-510 which provides that if payment on account
is made and such payment is endorsed on the record of the lien, the time period within which to
commence foreclosure proceedings is “six months after the date of such payment.” This Court
held that the statute only provided for one six-month extension and therefore the supplier‟s lien
had ceased to exist because it had not commenced a foreclosure action with the required time.
We stated:
The statute creates and limits the duration of the lien. The statute also
gives jurisdiction to the court to foreclose or enforce a lien on certain conditions,-
the filing of a claim of lien, and the commencement of the action within the time
specified after such claim is filed. If these things are not done no jurisdiction
exists in the court to enforce the lien. When the limit fixed by statute for duration
of the lien is past, no lien exists, any more than if it had never been created.
16
Id. at 401, 388 P.2d at 99 (emphasis added). We did not broadly construe section 45-506 to
permit repeated extensions of the time within which to foreclose the lien.
We have strictly followed the statutory requirement that the lien claimant must timely
commence proceedings by filing a pleading to foreclose the lien within the statutory time period.
The statute is clear and unambiguous, and we should continue to follow it.
Justice W. JONES CONCURS.
17