No. 8 5 - 3 7
IN THE SUPREME COURT OF THE STATE OF MONTANA
1985
JERRY THIEL and LARRY THIEL,
Plaintiffs and Appellants,
JAMES E. JOHNSON and LORETTA
JOHNSON,
Defendants and Respondents.
APPEAL FROM: District Court of the Sixth Judicial District,
In and for the County of Park,
The Honorable Byron Robb, Judge presiding.
COUNSEL OF RECORD:
For Appellant:
George T. Radovich, Billings, Montana
For Respondent :
Joseph P. Hennessey, Billings, Montana
Submitted on Briefs: May 16, 1 9 8 5
Decided: December 31, 1985
Filed:
Clerk
Mr. Justice John C. Sheehy delivered the Opinion of the
Court.
Jerry Thiel and Larry rhiel appeal from a judgment of
the Sixth Judicial District Court, Park County, which awarded
James and Loretta Johnson the sum (including costs) of
$68,235.72. We affirm.
On January 19, 1981, Jerry and Larry Thiel, as sellers,
entered into a contract to sell the Guest House Motel in
Livingston, Montana, to James and Loretta Johnson as buyers
for $470,000.00. The Johnsons used their home for the
$50,000.00 downpayment, and were thereafter required by the
contract to make two separate regular payments, $1,288.00
monthly to the Thiels for their equity in the Guest House
Motel, and $3,500.00 eight times a year for an underlying
contract owed by the Thiels to a third party. The underlying
contract required interest-only payments in January,
February, March and April of each year because tourism, on
which the motel depended, was down during those months.
The Johnsons were not able to operate the motel
profitably. During late 1981, the Johnsons were in serious
financial difficulty. Thereafter, they did not make the
January, February, March or April 1982 payments.
The contract for sale between the Thiels and the
Johnsons contained default provisions. The clauses provided
that if defaults by the Johnsons went uncured for a period of
30 days after written notice the Thiels could use any means
to enforce collection of the defaulted payments; but to
accelerate the due date of the full amount of the contract
balance, the Thiels would have to serve a further 30 day
notice of acceleration. On April 13, 1982, the Thiels served
a default notice upon the Johnsons based on the nonpayment of
the January, February, March and April 1982 payments.
On May 13, 1982, the Thiels commenced an action in the
District Court for the purpose of recovering the possession
of the motel, together with the liquor license, the
furniture, fixtures, and their attorney fees. On the same
date, they obtained from the District Court an order to show
cause addressed to the Johnsons as to why they should not be
restrained from further interfering with the peaceful
re-entry into the Guest House Motel by the Thiels.
Hearing on the show cause order was had before the
District Court on May 25, 1982 and at the conclusion of the
hearing the matter was taken under advisement by the Court.
On May 27, 1982, the Thiels served a further written notice
upon the Johnsons accelerating the due date of the unpaid
principal balance on the contract, and requiring full payment
thereof within 30 days. On June 3, 1982, the District Court
granted a temporary injunction, allowing the Thiels to take
possession of the Guest House Motel on posting a bond. A
bond was posted by the Thiels and the Johnsons objected to
the sufficiency thereof. Eventually this Court in cause no.
82-191, by way of supervisory control, vacated the bond as
insufficient on June 10, 1982. Thereafter the Thiels
supplied a bond which was accepted by the Johnsons. Thiels
have been and now are in possession of the motel property.
In the meantime, on June 4, 1982, Johnsons filed their
answer and counterclaim to the complaint of the Thiels. In
it they contended that the Thiels had acquiesced in the
nonpayment for the months specified. The Johnsons
counterclaimed for the sum of $95,878.60, the total of
payments that had been made by them on the contract including
the transfer of their house. The Johnsons further contended
that to force them out of the premises, the Thiels had
ignored the notice provisions of the contract for deed, and
had contacted the utility compa.nies in an effort to have
their services to the motel terminated. Johnsons sought
damages from the Thiel-s for "fraudulent malicious acts"
entitling Johnsons to punitive damages.
After trial on the issues, the jury returned a verdict
of $67,587.78 in favor of the Johnsons as actual damages, and
awarded nothing for punitive damages. It is from the
judgment based on that verdict that the Thiels appeal.
The first issue as stated by the appellants on appeal is
whether the District Court committed error by giving an
improper jury instruction indicating that an oral waiver
could alter a written contract, that a collection attempt
must be made prior to the due date of the next payment or it
will be deemed waived, and otherwise incorrectly stating the
law.
Johnsons offered instruction no. 28, given as court's
instruction no. 14, told the jury:
You are instructed that when a payment Is due
pursuant to contract, that payment may be waived
by the one who is to receive the payment. The
waiver may be either express or implied.
An implied waiver occurs when a contract payment is
past due, and the one who is to receive the payment
makes no attempt to collect the payment within a
reasonable time. A reasonable time is presumably a
short time after the payment is due, and before the
next payment is due.
An express waiver occurs when the one who is to
receive payment tells the one who is to make
payment, either orally or in writing, that the
payment or payments need not be made on the due
date. An express waiver must continue for the
period of time specified by the one who is to
receive payment.
Thiels ' principl-e objection to the instruction is that
it allowed recovery on implied waiver. As we will show later
in this opinion, there was evidence of an express waiver by
the Thiels of the payment for the first. 4 months of 1982.
Waiver may be express or implied. We said in Kelly v.
Lovejoy (19771, 172 Mont. 516, 565 P.2d 321:
As to the second issue, the Kellys' admitted
acquiescence to the presence of Lovejoys' horses
constituted a waiver and Kellys are therefore
estopped from asserting the restrictive covenant
against Lovejoys. Waiver is genera.11~ defined as a
voluntary and intentional relinquishment of a known
right, claim or privilege. [Citing cases.] Mundt
v. Malon, 106 Mont. 242, 76 P.2d 326; Farmers
Elevator Company of Reserve v. Anderson, 170 Mont.
175, 552 P.2d 63. Waiver may be proved by express
declarations or by a course of acts and conduct so
as to induce the belief that the intention and
purpose was to waive. Northwestern Fire & Marine
Insurance Company v. Pollard, 74 Mont. 1.42, 238 P.
594.
172 Mont. at 520, 565 P.2d at 323-24.
In Northwestern Fire & Marine Insurance Company v.
Pollard, supra, cited in the foregoing Kelly v. Lovejoy case,
this Court specifically held that a right may be waived by
implication as well as by agreement. Although waiver is
mainly a question of intention and must be manifested in some
unequivocal manner, a waiver may be founded upon express
.
written statements, oral express statements or acts or
conduct which induce the belief that the intention and
purpose is to waive.
Thiels further raise as an issue an objection to that
portion of the instruction which stated. that a waiver of
payment was impliedly made by Thiels if they did not attempt
to collect within a short time after the payment was due and
before the next payment was due. Objection to that portion
of the instruction was not made before the District Court,
and will not be considered by us on appeal. Specific
objections to portions of instructions are required by Rule
51, M.R.Civ.P.; objections not made before the trial court
will not he considered for the first time on appeal. Nott v.
Booke (Mont. 19811, 633 P.2d 678, 680, 38 St.Rep. 1507, 1510;
Wolfe v. Schultz Refrigeration (19791, 188 Mont. 511, 518-19;
614 P.2d 1015, 1019; Franck v. Hudson (1962), 140 J / o t 480,
!ln.
484-85, 373 P.2d 951, 953. We therefore do not pass on the
validity of that portion of the instruction.
The second contention of the Thiels on appeal is that
the jury verdict is totally unsupported by substantial
evidence at trial.
Loretta Johnson testified that she met with the Thiels
in Billings in the month of January 1982 to discuss the
payments coming due. She testified that at the meeting, she
told the Thiels that the low winter month's revenue, the
increases in utility rates that had occurred, and other
financial difficulties had made it impossible for the
Johnsons to do the things they planned to do with the motel.
and still keep up with the payments on the motel. She was
told, she testified, that this was "fine," and all the Thiels
were concerned about was to keep the underlying contract
current. She said she was told that as long as she would
keep the underlying contra-ct holder "happy" they were willing
to work with her and that "they would be glad to extend their
payments to be made until the summer season started rolling
again. "
The direct evidence of one witness who is entitled to
full credit is sufficient proof of any fact. Section
26-1-301, MCA. Substantial evidence to support the jury
verdict is all that is required. (See Gunnels v. Hoyt (Mont.
1981), 633 P.2d 1-187, 1191, 38 St.Rep. 1492, 1495, for a
discussion of the standard of review by this Court where the
sufficiency of the evidence to support the judgment is
attacked on appeal.)
The final contention raised by Thiels is that the
District Court erred in submitting to the jury an issue of
bad faith between the parties of the contract because their
bargaining positions were approximately equal, the contract
represented a nonadhesive transaction and the Thiels were
acting in accordance with the court order entitling them to
repossession of the motel premises.
The District Court submitted the issues through its
instructions in the following manner: The jury was
instructed to find first whether or not the plaintiffs had
waived payments for the months of January, February, March
and April 1982. They were told if the answer was yes then
they should determine whether or not the Thiels acted in had
faith or fraudulently in foreclosing on the defendants. If
they found so, then they were to determine the damages. The
court further instructed that a party to a contract owed the
other party to the contract a duty to act in good faith and
deal fairly, in order not to deprive the other party of the
benefits of the contract. It told the jury that bad faith is
the opposite of good faith, and generally implies or involves
actual or constructive fraud, a design to mislead or deceive
another, or 2 neglect or refusal to fulfill some contractual
obligation with an interested or sinister motive.
The court also instructed the jury concerning
constructive fraud, to which instructions the Thiels make no
objection on appeal. In fact each party offered an
instruction defining constructive fraud.
The District Court in this case instructed the jury that
the measure of damages from an unlawful act or omission of
another person is the amount which would compensate for all
the detriment proximately caused thereby whether it could
have been anticipated or not. The District Court further
instructed the jury that punitive damages could be awarded
for oppression, fraud, or malice, actual or implied.
As we noted, the jury awarded compensatory damages, but
not punitive damages.
The evidence in this case, in the light most favorable
to the Johnsons, was that after agreeing that they would
waive the time for payments due in the first four months of
1382, Thiels suddenly, without warning to the Johnsons, sent
a notice of default on April 13, 1982; that Thiels ousted. the
Johnsons from possession of the motel before the time for
accelerated payment of the full debt had expired, by sending
their agent, Larry Myers, to take possession of the motel and
its furniture and equipment; that before moving to take
possession, and to declare default, Theils had advised the
utility companies that the Johnsons were unable to pay their
utility bills and that the motel premises were about to be
repossessed.
In our recent decision in Nicholson v. United Pacific
Insurance Co. , (No. 84-247, Decided December 17, 1985) , the
majority of this Court declined "to extend the breach of
implied covenant to all contract breaches as a matter of
law." In that case this Court said an implied covenant of
good faith and fair dealing is not an obligation arising from
a contract (The writer hereof does not agree with that
conclusion, but that is unimportant in the case at bar. I
would impl-y the covenant in every contract.) Under
Nicholson, the nature and extent of an implied covenant of
good faith and fair dealing is measured in a particular
contract by the justifiable expectations of the parties. If
the action of the party in breaching the contract is
arbitrary, capricious or unrea.sonable, under Nicholson such
conduct exceeds the justifia.bl.e expectations of the other
party to the contract, and gives rise to tort liability for
compensatory and punitive damages.
Here the jury awarded Johnsons actual damages, but
refused to assess punitive damages in their verdict. The
result is the same, for all practical purposes, as though the
jury decided the issue simply on a breach of contract basis.
It is true that here the District Court instructed the
jury on a measure of damages that is ba-sed on tort. Section
27-1-317, NCA. However, the damages awarded by the jury here
are 1ittl.e different from what would be recoverable through
breach of contra-ct damages, that is, such detriment as was
proximately caused by the breach or in t-he ordinary course of
things would be likely to result therefrom. Section
27-1-311, MCA. The failure of the District Court to
distinguish between damages arising from a breach of contract
provision, and damages for the tort of bad faith is in this
case harmless in view of the jury verdict awarding only
compensatory damages.
The contention of the Thiels that they cannot be held in
bad faith for taking possession of the motel premises because
they were acting in accordance with a court order ignores the
fact that the court order was obtained prematurely at their
insistence. Thiels did in fact, through th.e court, obtain
possession of the motel before they were contractually
entitled to do so, which should have been after the service
of the requisite notices of default and acceleration provided
in the contract.
The judgment of the District Court is therefore
affirmed.
Justice
We Concur: