No. 83-533
IN THE SUPREME COURT OF THE STATE OF MONTANA
1984
PRICE BUILDING SERVICE, INC .,
Plaintiff and Respondent,
A. J. HOLMS, and PHYLLIS C. HOLMS,
his wife, ALLAN G. IIOLMS and
MARILYN HOLMS, his wife, et al.,
Defendants and Appellants.
APPEAL FROM: District Court of the Fourth Judicial District,
In and for the County of Missoula,
The Honorable John S. Henson, Judge presiding.
COUNSEL OF RECORD:
For Appellants:
Datsopoulos, MacDonald & Lind; Edward A. Murphy,
Missoula, Montana
For Respondent :
Snavely and Phillips; Robert J. Phillips, Missoula,
Montana
---
Submitted on Briefs: April 26, 1984
Decided: January 4, 1985
-
Clerk
Mr. Justice Daniel J. Shea delivered. the Opinion of the
Court.
The defendants A. J. Holms, Phyllis C. Holms, Allan G.
Holms and Marilyn Holrns, who are the contract owners and
lessors of land and a commercial building, and Harol-d Rhines,
James L. Rhines, and Gloria Rhines, who are the lessees of
land and a commercial building, known as Sound West, appeal a
judgment of the Missoula County District Court foreclosing a
mechanics lien in favor of plaintiff, Price Building Service,
the contractor who extensively remodeled the building on the
land. Price Building Service (the contractor) cross-appeal s
from the judgment, the effect of which was to deny recovery
for prejudament interest and attorney fees. We affirm the
judgment directing foreclosure of the mechanic's lien and
reverse the judgment on interest and attorney fees, and
remand for a determination of the interest and attorney fees.
Defendants raise five issues, the first two involving
the technical sufficiency of the mechanic's lien. First,
they contend that the lien is deficient because although it
contains a legal description of the land, it fails to de-
scribe the building itself. Second, they contend the lien is
d-eficient because it fails to correctly identify either the
lessors or lessees as the owners of the property to which the
lien attached. Third, the lessors contend that although the
contractor was not a party to the agreement, the lessors
agreed with the lessees to pay for improvements up to
$25,000.00 and that the contractor cannot recover any more
from the lessor. Fourth, one of the lessees, Harold Rhines,
contends that the trial court erred in holding that he and
the other lessees were partners, and therefore that Rhines is
liable as a partner. Fifth, the lessors argue that the trial
court erred in refusing to admit for general evidentiary
purposes two exhibits prepared with the objective of showing
the actual value of the remodeling work performed by the
contractor.
In April, 1973, under a contract for deed, the Holms'
purchased portions of several lots and a commercial building
on those lots. Four months later, in August 1973, the Holms'
in turn leased this property and a building, to Harold Rhines
and his son, James L . Rhines, and daughter-in-law, Gloria A.
Rhines. The lease contained an option to purchase and also
contained a stipulatj-on that the Holms as lessors would pay
the first $25,000.00 of anticipated remodeling expenses and
the Rhines' as lessees, would pay all remodeling expenses
beyond $25,000. The buildinq was to be extensively remodeled
to house what is known as Sound West, a retail stereo equip-
ment store. The parties, by oral contract, and without
asking for a formal bid, employed Price Building Service to
do the remodeling work.
The contractor started work in late August, 1 - 9 7 3 , and
finished it during the week ending January 2, 1974. Before
the work was completed, the contractor became concerned over
payment of the bill, and Harold Rhines assured the contractor
that the bill would be paid when the remodeling was
completed.
When the remodeling was completed the contractor submit-
ted a bill for $55,579.12. Two months later, on March 26,
1374, after the lessors and lessees had not paid anything on
the bill, the contractor filed a mechanic's lien on the
property. In describing the property, in addition to the
legal description, the lien referred to ". . . that certain
building and improvements erected upon" the described proper-
ty. In addition, along with the formal lien, was filed a
statement of account for "Sound West," the name of the busi-
ness operating from the remodeled building.
Six or eight months after the contractor filed the
mechanic's lien, the Holms paid $22,000.00 to the contractor,
but that is all. In September, 1974, after the mechanic's
lien had been filed, James L. and Gloria A. Rhines exercised
their option to purchase the property, subject of course, to
the contractor's mechanic's lien. They signed a contract for
deed with the Holms'. Harold Rhines, the father of James
Rhines, provided the financing for James and Gloria Rhines to
purchase the property.
The case finally went to trial on the lien foreclosure
action, and the Holms' and Rhines defended in part on the
ground that the contractor had not performed according to
requirements and therefore that the property was in some
respects, defective. As part of the defense the Holms' and
Rhines' offered in evidence two documents that consisted of
construction estimates or bids prepared according to the
remodeling plans, and figured in 1983 dollars, rather then in
1973 dollars when the remodeling was done. Witnesses who
prepared those bids for purpose of trial testified that the
bids did not include all of the ma-terials and labor provided
by the contractor in actually doing the remodeling. The
defendants also did not lay proper foundation concerning the
inflation rate between 1973 and 1983--a ten year span. The
trial court refused one exhibit and admitted one for the
Limited purpose of showing the kind and quantity of materials
necessary to perform the remodeling.
The trial court ordered foreclosure of the lien in the
amount of $33,579.12, but also ordered this amount to be
offset in the sum of $2,740.00 for defects in the contrac-
tor ' s performance. The judgment failed to incl-ude prejudg-
ment interest and attorney fees, and attorneys for the
contractor moved to amend the findings and conclusions to
include these items. The trial court, however, failed to
rule on this motion within the time requirements specified by
Rule 59(d), M.R.Civ.P., and the motions were therefore deemed
denied. Although the trial court had no authority to do so
because of the operation of Rule 59, the court amended the
judgment to include prejudgment interest a-nd attorney fees.
For purposes of appeal we therefore treat the motion to amend
the findings and conclusions as being denied, and we consider
this issue as part of the contractor's cross-appeal.
The lessors and lessee's first attack the validity of
the mechanic's lien by contending that it failed to describe
the building and instead merely described the land. But that
is not the case. The lien specifically referred to the
building on the land, and the evidence disclosed that only
one buil.ding was on the land, the one on which the contractor
performed the work. Clearly this would enable one familiar
with the locality to point the building out as the one corre-
sponding to the description contained in the lien. Under
Varco-Pruden v. Nelson (1979), 181 Mont. 252, 593 P.2d 48,
this was sufficient. Furthermore, under our holding in
General Electric Supply Company v. Bennett, (Mont.. 1981) 626
P.2d 844, 38 St.Rep. 553, the statement of account filed with
the lien, and referring to "Sound West.," would leave little
doubt as to the building referred to.
CORRECTION. In preparing this opinion for pub-
Hon. D a n i e l J . S h e a lication, we noted in our verification of titles and
J u s t i c e , Supreme C o u r t citations the matters listed below. Corrections have
Room 414 J u s t i c e B u i l d i n g been made on our copy of the opinion.
215 N o r t h S a n d e r s
H e l e n a , Montana 59620
F e b r u a r y 6 , 1985
P r i c e B u i l d i n g S e r v i c e , I n c . v . Holms, No. 83-533, Jan. 4, 1985
P a g e 6 , l i n e 8 f r o m b o t t o m --- Montana Farm S e r v i c e Co. v . M a r q u a r t
s h o u l d r e a d Montana Farm S e r v i c e Co. v . M a r q u a r t .
4 P a g e 11, l i n e 6 f r o m b o t t o m --- 94 Mont. - s h o u l d r e a d 94 Mont. -.
97 57
P a g e 1 3 , l i n e 6 --- 1 0 8 Mont. 97, 20 P.2d 622 s h o u l d r e a d 1 0 8 Mont. -,
57
90 P . 2 d 4 8 9 .
--q P a g e 15, l i n e - --- - P.2d 4 5 5 s h o u l d r e a d 506 P . 2 d 4 5 5 .
406
-.-/ Page 16, l i n e 10 --- § 71-13-124
- s h o u l d r e a d § 71-3-124.
-
-J Page 16, l i n e 11 --- 1 7 1 Mont. - s h o u l d r e a d 1 7 1 Mont.
382 383.
WEST PUBLISHING COMPANY
Box 43526
St. Paul, M N 55164
The second attack on the validity of the lien is a
contention that the contractor failed t o correctly identify
e i t h e r t h e Holms' o r t h e R h i n e s ' a s t h e owners o f t h e p r o p e r -
t y t o which t h e l i e n a t t a c h e d . A s t h i s Court held i n Blose
v. Havre O i l and Gas Cornpany ( 1 9 3 4 ) , 96 BKont. 450, 3 1 P.2d
738, it i s i m p o r t a n t t h a t t h e l i e n i d e n t i f y t h e name o f t h e
owner a g a i n s t whose p r o p e r t y t h e l i e n i s f i l e d s o t h a t t h i r d
p a r t i e s e x a m i n i n g t h e p u b l i c r e c o r d s c a n f i n d an encumbrance
more e a s i l y . Here t h e l i e n r e f e r r e d t o t h e H a r r i s o n s , from
whom t h e Holms were b u y i n g t h e p r o p e r t y , and t o t h e H c l m s '
t h e c o n t r a c t f o r deed p u r c h a s e r s . The R h i n e s ' d i d n o t have
t o b e m e n t i o n e d b e c a u s e a t t h e t i m e t h e l i e n was f i l e d t h e y
had n o t y e t e x e r c i s e d t h e i r o p t i o n u n d e r t h e l e a s e a g r e e m e n t
w i t h t h e Holms'. The l i e n , i n r e f e r r i n g t o t h e H a r r i s o n s and
Holms' a s t h e owners o f t h e p r o p e r t y , was c o r r e c t .
T h i r d , H a r o l d R h i n e s , a s one o f t h e l e s s e e s , c o n t e n d s h e
was n o t a p a r t n e r i n t h e Sound West e n t e r p r i s e , and t h a t t h e
t r i a l court's f i n d i n g t h a t h e was a p a r t n e r , and t h e r e f o r e
l i a b l e t o t h e c o n t r a c t o r on t h e remoc7,eling c o n t r a c t , was i n
error. One may become a p a r t n e r o f a f i r m , a s t o t h e t h i r d
p e r s o n s , b ~ i t h o u t i n t e n d i n g t o , by words spoken o r w r i t t e n o r
by c o n d u c t , and t h e r e b y became l i a b l e t o t h o s e who h a v e i n
good. f a i t h g i v e n c r e d i t t o t h e a c t u a l o r a p p a r e n t p a r t n e r -
ship.
a.
Montana Farm S e r v i c e Co. v. Mar u a r t ( 1 9 7 8 ) , 176 Mont.
3 5 7 , 578 P.2d 315. D u r i n g c o n s t r u c t i o n , when the contractor
e x p r e s s e d c o n c e r n o v e r t h e payment o f t h e b i l l , H a r o l d R h i n e s
p e r s o n a l l y a s s u r e d him t h a t t h e b i l l would b e p a i d when t h e
remodeling was completes. Harold Rhines also asked the
c o n t r a c t o r f o r p e r s o n a l n o t i f i c a t i o n by r e g i s t e r e d m a i l when
t h e remodeling e x p e n s e s e x c e e d e d $25,000.00. F u r t h e r , Harold
R h i n e s s i g n e d t h e l e a s e and assumed i t s b e n e f i t s and b u r d e n s ,
i n c l u d i n g a p r o m i s e t o pay f o r any r e m o d e l i n g c o s t s e x c e e d i n g
$25,000.00 The contractor testifed that Harold R h i n e s had
notified him t h a t t h e Rhj-nes would b e p a y i n g a l l e x p e n s e s
o v e r $25,000.00. Whether o r n o t H a r o l d R h i n e s was t e c h n i -
c a l - l y a p a r t n e r of James R h i n e s , h i s words and c o n d u c t r e a -
sonably led the contractor to believe he was, and the
c o n t r a c t o r t h e r e f o r e c o n t i n u e d t o remodel upon H a r o l d R h i n e ' s
a s s u r a n c e of payment. As t o the contractor, Harold Rhines
was a partner, and therefore liable on the remodeling
contract.
Fourth, t h e l e s s o r s and lessees c o n t e n d t h e t r i a l c o u r t
e r r e d i n e x c l u d i n g two b i d - s t h a t w e r e o f f e r e d t o p r o v e t h a t
the contractor overcharged for materials and labor. The
c o u r t r u l e d t h e b i d s w e r e i r r e l e v a n t because they lacked t h e
proper foundation and w e r e incomplete. The w i t n e s s e s who
prepared t h e b i d s admitted t h a t t h e b i d s d i d n o t include a l l
of the materials and labor provided by the contractor.
Further, the lessors and lessees fa-iled t o lay a proper
f o u n d a t i o n a s t o t h e i n f l a . t . i o n r a t e between 197-1, when the
r e m o d e l i n g was p e r f o r m e d and 1983, when t h e b i d s w e r e p r e -
pared. The b i d s w e r e prepared i n 1.983 d o l l a r s r a t h e r t h a n
1973 d o l l a r s . One b i d was a d m i t t e d f o r t h e l i m i t e d p u r p o s e
of showing t h e k i n d and q u a n t i t y o f m a t e r i a l s n e c e s s a r y t o
perform t h e remodeling. The b i d s c l e e r l y l a c k e d t h e p r o p e r
f o u n d a t i o n and were i n c o m p l e t e , and t h e t r i a l c o u r t d i d n o t
err i n e x c l u d i n g them from e v i d e n c e .
Fifth, the lessors ( t h e Holms'), in seeking t o limit
t h e i r l i a b i l i t y , contend t h e y a r e l i a b l e o n l y t o t h e e x t e n t
of $25,000.00 because they agreed with t h e lessees t o pay
only the first $25,000.00 remodeling c o s t s . However, the
c o n t r a c t o r was n o t a p a r t y t o t h i s c o n t r a c t a n d a t t h e t i m e
the work was done the lessors were the contract owners of the
property. The judqment is against the lessors and lessees,
and the contractor can look to either or both in seeking to
satisfy the judgment. The agreement between the lessors and
lessees on sharing improvement. costs is a matter to be set-
tled only between the lessors and lessees, as the contractor
was not a party to that contract and is not bound by its
terms.
CROSS-APPEAL
The contractor asked the trial court to award prejudg-
ment interest based on S 27-1--211, MCA, and attorney fees
based on S 71-3-124, MCA. In the original findings and
conclusions, however, for reasons unexplained, the trial
court expressly declined to rule on these requests but sug-
gested that the contractor again raise these issues by filing
a motion to amend the findings and conclusions. The contrac-
tor did so, but the trizl court failed to rule on the motion
within the fifteen-day cut-off limit of Rule 59, If.R.Civ.P.,
and therefore the motions were deemed denied as a matter of
law. After it was too late to rule, the trial court did file
amended findings and conclusions, together with a memorandum
opinion, and awarded prejudgment interest and attorney fees.
Rut this order had no effect because it came after the time
to rule had expired. The contractor, therefore, has
cross-appealed on these issues, contending t-hat prejudgment
interest and attorney fees should be awarded. We aqree.
PREJUDGMENT TMTEREST
The contractor originally submitted a bid in the
$36,000.00 ran.ge; however, the construction was not based on
a bid price, but on a cost-plus arrangement. The
lessor-lessees were to pay the contractor his costs for labor
and m a t e r i a l s pl u s 12 p e r c e n t . Throughout t h e c o n s t r u c t i o n
stages t h e contractor sent periodic statements detailing h i s
l a b o r and material. c o s t s . However, b e f o r e c o n s t r u c t i o n was
c o m p l e t e d , c e r t a i n c o n s t r u c t i o n c h a n g e s w e r e made. Although
the lessor-lessees contended t h e c o n t r a c t o r caused t h e need
f o r t h e changes, t h e t r i a l c o u r t found t h e y w e r e done a t t h e
r e q u e s t o f t h e lessee. A t t h e end o f t h e p r o j e c t i n 19?4,
t h e c o n t r a c t o r s e n t a f i n a l b i l l f o r $55,579.12. I t was n o t
p a i d a n d a few months l a t e r i n 1974 t h e c o n t r a c t o r f i l e d a
nechanics lien for the amount owed. Six t o e i g h t months
a f t e r t h e l i e n was f i l e d , t h e l e s s o r p a i d $22,000.00 on t h e
account. When no f u r t h e r payments w e r e made by 1 9 7 5 , the
contractor filed suit to foreclose on t h e mechanics lien.
N o t h i n g was done on t h e s u i t u n t i l 1979 when a d e p o s i -
t i o n was t a k e n . L i t t l e was done z f t e r t h i s a n d t h e c a s e d i d
n o t come t o t r i a l u n t i l 1983, almost nine years a f t e r t h e
completion of t h e c o n s t r u c t i o n p r o j e c t . The r e c o r d r e v e a l s
t h a t t h e c o n t r a c t o r d i d n o t d i l i a e n t l y pursue h i s claim b u t
a l s o r e v e a l s t h a t t h e l e s s o r - l e s s e e s d i d n o t a s k f o r a speedy
r e s o l u t i o n of t h i s m a t t e r . They were c o n t e n t t o l e t t h e c a s e
remain i n a c t i v e .
The trial court found the lessor-lessees owed
$55,579.10, less t h e $22,000.00 paid s i x months a f t e r t h e
l i e n was f i l e d , a n d l e s s $2,740.00 f o r d e f e c t i v e workmanship.
The b a l a n c e found owing was d e t e r m i n e d t o b e s 3 0 , 8 9 3 . 1 2 (it
should actua1l.y be $30,839.12) . In his cross-appeal the
c o n t r a c t o r c o n t e n d s t h a t u n d e r 5 27-1-211, MCA, he i s enti-
t l e d t o p r e j u d g m e n t i n t e r e s t on t h e $30,839.12 a t t h e s t a t u -
tory rate of 6 percent ( 31-1-106, MCA) , and that for
foreclosure of the lien he is entitled, under 5 71-3-124,
MCA, t o attorney fees.
If a claim is certain or can be ascertained by calcula-
tion, S 27-1-211, MCA, allows prejudgment interest. The
statute sets forth only two e:tceptional circumstances in
which interest need not be paid. The statute provides:
"Every person who is entitled to recover
damages certain or capable of being made
certain by calculation and the right to
recover which is vested in him upon a
particular day is entitled also to recov-
er interest lrom that day except during
- -time- the debtor is prevented by
such - as
- - & - - - creditor from paying
I-awor act of the
the -
- debt." Section 27-1-211, MCA.
(Emphasis added. )
The contractor primarily argues that the claim was
certain or capable of being made certain by calculation, and
that the right to recover vested when the final bill was sent
to the lessor-lessees. The lessor-lessees, on the other
hand, advance several reasons to counter the contractor's
certainty argument. In add-ition, they argue that interest
should be dj-sallowed because the contractor failed to dili-
gently prosecute his claim in court. They argue it is unfair
to permit interest over all these years when it was the
plaintiff who failed to prosecute h i . s claim to completion.
We deal first with the failure to prosecute contention.
The statute is clear. If the claim is certain or can be
made certain by calculation, interest must be allowed unless
the lessor-lessees were prevented by law from paying the debt
or the contractor prevented them from paying the debt. These
are the only conditions excusi-ng the payment of interest.
Federal Land Bank v. Green (1939), 108 Mont. 56, 67, 90 P.2d
489. Neither of these conditions exists here.
Nor can we accept the argument that as an equitable
matter the contractor's lack of diligence in taking the case
to trial must invalidate the operation of the prejudgment
j-nterest s t a t u t e . T h i s i s - o n e of t h e c o n d i t i o n s which
not
e x c u s e t h e payment o f i n t e r e s t under t h e s t a t u t e . Further-
more, t h e r e c o r d i s j u s t a s c l e a r t h a t t h e l e s s o r - l e s s e e s did
nothing t o o b t a i n a speedy r e s o l u t i o n of t h i s m a t t e r . They
were i n s t e a d c o n t e n t t o l e t t h e c a s e r e m a i n i n a c t i v e w i t h t h e
result that they had the use of over $30,000.00 of the
c o n t r a c t o r ' s money f o r a l m o s t t e n y e a r s . Had t h e y borrowed
this money from any financial i.nstitution, they most
certainly would have been paying a much higher rate of
interest. And by n o t p r e s s i n g t h e c a s e t o t r i a l t h e m s e l v e s ,
t h e y h e l p e d d e l a y e n t r y of judgment, a t which t i m e a judgment
would h a v e c a r r i e d i n t e r e s t a t t h e r a t e of LO percent per
year ( S 25-9-205, MCP,), as opposed to the 1-egal. r a t e of
i n t e r e s t here of 6 percent per year. They c l e a - r l y b e n e f i t e d
from t h e d e l a y o f t r i a l and d e l a y o f judgment.
The lessor-lessees a l s o argue several factors, which,
t h e y c o n t e n d , made it i m p o s s i b l e f o r them t o d e t e r m i n e t h e
damages or t h e a n o u n t owed t o the contractor. It is not
clear whether they contend any one of these factors was
s u f f i c i e n t t o d i s a l l o w prejudgment i n t e r e s t , o r whether t h e
cumulative e f f e c t of t h e s e f a c t o r s r e q u i r e d a d i s a l l o w a n c e of
prejudgment i n t e r e s t . First, t h e y seem t o a r g u e t h a t p r e -
jud9men.t i n t e r e s t i s a l l o w e d o n l y where t h e r e i s a n a c c o u n t
s t a t e d o r where a. f i x e d c o n t r a . c t p r i c e h a s b e e n s e t f o r ful.1
performance. They r e l y (and i m p r o p e r l y s o ) on E s k e s t r a n d v .
5'
&
Wunder ( 1 9 3 3 ) , 9 4 Mont. , 20 P.2d 6 2 2 . With t h i s a s t h e i r
p r e m i s e , t h e y a r g u e t h a t p r e j u d g m e n t i n t e r e s t must h e d i s a l -
lowed h e r e b e c a u s e t h e c o m p l a i n t was i n s t e a d b a s e d on t h e
v a l u e of t h e l a b o r and m a t e r i a l s p l u s 12 p e r c e n t . They c7,o
not s a y why t h e y were u n a b l e t o d e t e r m i n e w h e t h e r t h e con-
t r a c t o r ' s h i l l f o r $55,579.12 was c o r r e c t - - a f i g u r e found by
the trial court to be correct. Second, they argue that their
$25,000.00 counterclaim for co~struction delay damages and
their $7,000.00 counterclaim for defective performance
damages, made it impossible for them to determine the amount
owed to the contractor. Third and finall-y,they contend the
contractor created the uncertainty of determining the final
amount owed because his faulty construction created a
continuing fluctuation in the amount claimed and also
increased the amount claimed. They argue that uncertainty
inheres in this situation because it remained for the trial
court to determine whether the changes and additional
expenses were caused by the contractor's defective
performance of by their constant changes of the job
specifications.
Contrary to the lessor-lessees' assertions, Eskestrand
v. Wunder, supra, does not hold interest can be awarded only
where there is an account stated or where there is a fixed
contract price at the inception of the construction which has
not been changed. The statute merely requires that the
damages be certain, or capable of ascertainment by calcula-
tion. Here the contract was for costs of labor and materials
plus 12 percent. The total of this figure was $55,579.12,
this was the bill given to the lessor-lessees, and this was
the figure which the trial court found to he correct.
Furthermore, the dispute over part of the claim here did
not convert the contractor's claim into one on which prejudg-
ment interest would not run. A dispute on the amount owed on
part or all of a claim in the form of a denial of part or all
of the amount owed, or in the form of a counterclaim for
construction delay and defective performance, does not trans-
form a plaintiff's claim into one that does not bear
prejudgment interest. It is the nature of the complaint
rather than the character of the defense that determines the
right to preiudgment interest. City of Seattle v. Dyad
Const., Inc. (Wash.App. 1977), 565 P.2d 423. In fact, this
Court held in Federal Land Ea.nk v. Green (1939), 108 Mont.
Lj fy
.2d 622; that the right to prejudgment interest was
not defeated where the amount stated in filing a lien was
overstated, as long as the correct amount constituting the
debt was ascertainable. And in Farrington v. Freeman (Minn.
1959), 99 N.W.2d 388, the court held a plaintiff's claim for
prejudgment interest was not defeated because the defendant
had filed an unliquidated counterclaim for costs of remedying
defects in plaintiff's work. These cases expressly or
impli-citly recognize that the right to prejudgment interest
should not be cut off by the simple defensive move of
claiming an offset or filing a counterclaim that directly or
indirectly creates an issue as to the amount owed. The
statute creating the right to prejudgment interest was not
meant to be nullified by the mere existence of such defensive
pleadings.
The existence of a valid contest on the amount owed c a p ,
however, affect both the amount. awarded to the plaintiff on
the main debt and the amount of prejudgment interest awarded.
If the amount owed is reduced by a valid setoff or counter-
claim, interest is then normally allowed only on the balance
due after deductjons of the offsetting zmounts and payments
that may already have been made. Hanson v. Cove11 (Cal.
1933), 24 P.2d 772. In fact, that is what the trial court
did in this case. Jt found the amount owed to be $55,579.12,
that S22,000.00 had already been paid, and that this amount
should be further reduced by $2,740.00 allowed for defective
performance. As we noted before, however, the trial court's
decj-sion on the prejudgment interest question came too late
to constitute a decision favoring an allowa.nce of prejudgment
interest.
The prejudgment interest statute, in existence since
1895, merely sets forth a broad area in which the 1-eqislature
has determined prejudgment interest should be allowed as a
matter of right with the exception that it need not be paid
if a law has prevented the debtor from paying the debt or if
the creditor has done something to prevent the debtor from
paying the debt. It is merely part of the l.aw of damages
that has, as its objective, that of making the injured person
whole.
Though the statute also reauires the amount to be cer-
tain or determinable by calculation, when considered with the
other statute vesting discretionary power in the t.rier of
fact to award prejudgment interest in almost all other situa-
tions ( 5 27-1-212, MCA) , it is clear that the legislature
intended prejudgment interest under S 27-1-211, MCA, to be
the rule rather than the exception. Section 27-1-212, on the
other ha.nd, deals with an award of prejudgment interest in
a l l - si-tuations "not arising out of contract." It provides:
"In an action for the breach of an obli-
gation not arising from contract - -
a.nd in
every ca-se oppression, fraud, - or
malice. interest - be aiven. in -
mav the
discretion - - jury.
of the This section
does not apply in actions for recovery of
damages arising from injury to a person
or property brought against a governmen-
tal entity under Title 3 , chapter 9,
parts 1 through 3, as amended." (Empha-
sis added.)
This statute clearly permits an award of prejudgment
interest in al-most all other cases, but it requires the
discretion of the jury or the judge if tried to the court.
Tn contrast, 5 27-1-211, MCA, is not a discretionary statute.
Rather, it mandates interest as long as the legal situation
fits within the broad quidel-ines of the statute. Determining
whether a cause of action fits within the framework of the
statute, particularly the question of whether the claim is
determined or can be determined by calculation, is not always
an easy one. However, the overriding purpose of the statute
can be best preserved if it is remembered that its purpose is
to fully compensate the injured party for the loss of use of
his money during the period j n which a valid claim was not
paid. We believe, as did the court in Mitchell v. Flandro
p&t.
(Idaho 1972), P.2d 455, that the objective of fu1l.y
compensating the injured party, and that is the primary
objective of the prejudgment interest statute, should predom-
inate over other equitable considerations. If the legisl-a-
ture has chosen to provide a right to prejudament interest
( 5 7 - 1 - 2 1 ) , the primary objective of the courts, where
possible, should be to award prejudgment interest.
The statutory policy favoring an award of prejudgment
interest to a plaintiff whose claim falls within the hroad
framework of § 27-1-211 does not result in an iniustice to a
defendant who has valid reason for not paying the entire
claim, and who must resort to the courts to present his
reason for not paying the entire claim. If the trial court
reduces the plaintiff's claim because of' a valid offset or
counterclaim that can be determined by calculation,
prejudgment interest would be permitted under S 27-1-211. On
the other hand, if the setoff or counterclaim cannot be
d-etermined by cal.culation, it still may be such that a
defendant may be awarded interest under $ 27-1-212, in the
discretion of the judge or jury. An award of interest under
either S 27-1-211 or 27-1-212 would further reduce the amount
the plaintiff b~ould be ultimately awarded and would more
nearly approximate a fair resolution of the controversy in
recognition of a defendant's right to assert an offset or
counterclaim. It may lead to a speedier resolution of a
controversy if a plaintiff knows that a valid offset or
counterclaim may al.so bear prejudgment interest.
ATTORNEY FEES
The request for attorney fees in the J j e foreclosure
..n
is based on statute, S 7143-124, MCA. In atz zinger v.
Remco, Inc. (1976), 171 Mont. z ? 5 5 8 P.2d 650, this Court
held that the statute mandates an award of attorney fees to a
cLeimant whose lien is successfully established. The
lessor-lessees do not argue otherwise. As we have previously
indicated, the trial court's ruling awarding attorney fees
came too late to constitute part of a judgment favoring
attorney fees, and therefore the plaintiff has filed his
cross-appeal. The statute is clear, and it applies here.
Plaintiff is entitled to an award of attorney fees.
DISPOSITION
In summary, we affirm the judgment forecl.osing a
mechanic's lien in the amount of $33,579.12, Less the offset
of $2,740.00 for defective performance. We reverse the order
denying prejudgment interest and a.ttorney fees. We remand to
the District Court for a hearing on the interest to be award-
ed and the attorney fees to be awarded. Plaintiff is enti-
tled to prejudgment interest on the $33,579.12 net amount
found to be due. However, the trial court must also deter-
mine, in his discretion, whether the lessor-lessees are
entitled to prejudgment interest on the $2,740.00 offset for
defective performance.
The t r i a l c o u r t a l s o found t h a t t h e l e s s o r i s n o t p e r -
s o n a l l y 1 i a b l . e beyond t h e $25,000.00 a g r e e d t o , and a l t h o u g h
t h i s i s s u e i s n o t o n a p p e a l a s s u c h , we a f f i r m t h i s h o l d i n g
so that the parties are s u r e of their rights during the
f u t u r e proceedings i n t h e t r i a l c o u r t .
We affirm in part, reverse in part, and remand for
f u r t h e r proceedings c o n s i s t e n t with t h i s opinion.
W Concur:
e
Chief J u s t i c E