LHC, INC. v. Alvarez

                                       No. DA 06-0407

                IN THE SUPREME COURT OF THE STATE OF MONTANA

                                           2007 MT 123


LHC, INC., a Montana corporation,

               Plaintiff and Respondent,

         v.

ROBERTO ALVAREZ, as Trustee of the Alvarez
Family Trust u/d/t dated October 10, 1088,

               Defendant and Appellant,

         and

FIRST NATIONAL BANK OF MONTANA, INC.,

               Defendant.


APPEAL FROM:          The District Court of the Eleventh Judicial District,
                      In and For the County of Flathead, Cause No. DV 04-662C,
                      Honorable Stewart E. Stadler, Presiding Judge


COUNSEL OF RECORD:

               For Appellant:

                      Phillip J. O’Connell, Attorney at Law, Missoula, Montana

               For Respondent:

                      Paul G. Sandry and Scott G. Hilderman, Johnson, Berg,
                      McEvoy & Bostock, PLLP, Kalispell, Montana


                                                     Submitted on Briefs: April 18, 2007

                                                                 Decided: May 30, 2007

Filed:


                      __________________________________________
                                        Clerk
Justice W. William Leaphart delivered the Opinion of the Court.

¶1    Plaintiff LHC, Inc., filed a construction lien against defendant Roberto Alvarez

and defendant First National Bank of Montana, Inc. The Bank was later dismissed

pursuant to the stipulation of the parties. LHC, a concrete and gravel supplier, had

supplied concrete to John Young, d/b/a D Bar J Logging, Inc., and D Bar J Asphalt

(Young), a contractor employed by Alvarez to do paving work. Young failed to pay

LHC the total due for the supplied material. LHC then filed a construction lien against

Alvarez’s property. Alvarez admitted that concrete supplied by LHC was used in the

construction of its mini-storage facility, but disputed the dates and amount supplied, as

well as the validity of the construction lien. After a bench trial, the District Court

enforced the construction lien and awarded prejudgment interest as well as attorney fees

and costs. Alvarez appeals from the judgment. We affirm.

¶2    Alvarez raises four issues on appeal:

¶3    I.   Did the court err when it considered deliveries outside of the timeline

established in LHC’s construction lien?

¶4    II. Did the court err in finding that LHC’s concrete was delivered to Alvarez’s

mini-storage facility on August 11, 12 and 13?

¶5    III. Did the court err in awarding prejudgment interest?

¶6    IV. Did the court err in awarding attorney fees?

                                   BACKGROUND

¶7    In 2003, Alvarez engaged Young to perform paving services in connection with

the construction of a mini-storage facility. Young purchased concrete and other materials

                                          2
from LHC for use at the Alvarez property. At the time, Young had outstanding debts to

LHC from past projects unrelated to the work he was doing for Alvarez.

¶8    LHC delivered concrete to the Alvarez property from August 5 to 8, 2003, as

recorded in invoice 6521 (in the amount of $20,119). Invoice 24470 is for concrete

delivered to the Alvarez property on August 14, 2003 (in the amount of $400.50).

Invoice 6576 is, according to LHC’s records, for delivery on August 11, 12, and 13, 2003

(in the amount of $3356.10). The fourth invoice, 6612, is for flowboys and water trucks

delivered on July 29 and 30 and August 5, 7, and 8, 2003 (in the amount of $4,475).

¶9    LHC did not maintain separate accounts for Young’s different projects. At the

time Young began purchasing materials for use on Alvarez’s property, he had an

outstanding balance of between $28,000 and $29,000 with LHC. When Young made

payments to LHC, LHC applied those payments to Young’s oldest outstanding invoices.

¶10   Alvarez paid Young a total of about $60,000 for his work. On August 25, 2003,

Young paid LHC $30,000. Only about $4,000 of this went to the Alvarez invoices. The

rest went to other job invoices incurred prior to the Alvarez project. On October 9, 2003,

Young paid LHC $10,000. LHC directed portions of this payment to invoices incurred

by Young after the Alvarez project.

¶11   On November 10, 2003, LHC filed a construction lien on Alvarez’s property. The

lien stated that the balance remaining unpaid was $16,568, together with interest and

costs. Additionally, the lien stated that the “materials were first furnished on August 9,

2003, and were last furnished on August 14, 2003.” On September 7, 2004, Alvarez filed

a complaint against LHC. On October 1, 2004, LHC filed a separate claim against

                                        3
Alvarez. The two cases were consolidated. After a bench trial, the court found for LHC,

granting judgment on the lien in the amount of $24,241.40, including $5,945 in attorney

fees, $620 in costs, and $3,474.82 in prejudgment interest from the date of the filing of

the lien.

¶12    Alvarez appeals the District Court’s enforcement of the lien as well as its grant of

attorney fees and prejudgment interest.

                               STANDARD OF REVIEW

¶13    We review conclusions of law, including statutory interpretation, de novo. James

Talcott Const. v. P & D, 2006 MT 188, ¶ 26, 333 Mont. 107, ¶ 26, 141 P.3d 1200, ¶ 26.

¶14    We review findings of fact to determine whether the findings are clearly erroneous

using a three-part test. First, we review the record to determine if the findings are

supported by substantial evidence; second, if the findings are supported by substantial

evidence, we will determine if the trial court has misapprehended the effect of the

evidence; and third, if substantial evidence exists and the effect of the evidence has not

been misapprehended, the Court may still conclude that a finding is clearly erroneous

when a review of the record leaves the Court with the definite and firm conviction that a

mistake has been made. James Talcott Const., ¶ 26 (citations omitted).

¶15    We review a district court’s award of prejudgment interest de novo. James Talcott

Const., ¶ 28 (citations omitted).

¶16    We review a district court’s order granting or denying attorney fees and costs to

determine whether the court abused its discretion. James Talcott Const., ¶ 27 (citations

omitted).

                                          4
                                       DISCUSSION

¶17    I. Did the court err when it considered deliveries outside of the timeline

established in LHC’s construction lien?

¶18    Alvarez contends that the court should not have granted judgment for payments

made outside of the dates listed in LHC’s construction lien. The lien states that it is for

materials furnished between August 9 and August 14, 2003. Section 71-3-535(3)(g)(i)

and (ii), MCA, requires that a lien state the dates materials were furnished. Thus,

according to Alvarez, the claimed lien should not be enforced for the amounts

documented in invoice 6521 (August 5 to 8) and invoice 6612 (July 29 and 30 and

August 5, 7 and 8), because these invoices are for delivery dates not stated in the lien.

¶19    The District Court, however, refused to consider this argument because Alvarez

raised it for the first time in his post-trial findings of fact and conclusions of law. Alvarez

disputes this and asserts that he argued the issue in his pretrial order by stating: “[t]he

LHC Lien was filed without right whatsoever.”             Similarly, Alvarez stated in the

complaint that “[t]he LHC lien is without right whatsoever.”

¶20    It is well-established that we will not address issues on appeal that were not

properly raised in the district court. Nason v. Leistiko, 1998 MT 217, ¶ 11, 290 Mont.

460, ¶ 11, 963 P.2d 1279, ¶ 11 (citations omitted). We concluded in Marsh v. Overland,

and reaffirmed in Nason, that where a party fails to raise an issue in the pleadings, does

not present argument on the issue during the hearing on the merits of the case, does not

move to amend the pleadings to conform to any evidence presented and raises the issue

for the first time in a post-hearing memorandum that the district court does not address in

                                           5
its order, the issue has not been timely raised and may not be raised on appeal. Nason,

¶ 18 (citing Marsh v. Overland, 274 Mont. 21, 29, 905 P.2d 1088, 1093 (1995)).

¶21    Here, Alvarez’s general assertion, in his complaint and in the pretrial order, that

the lien was filed “without right whatsoever,” failed to specifically raise the argument

that delivery dates not listed in the lien should not be enforced. Other than his general

statement that the lien was without right, Alvarez did not raise the issue in the pleadings,

did not amend the pleadings to include the issue, and did not raise the issue at trial.

Finally, the District Court refused to consider Alvarez’s argument. As Alvarez failed to

timely raise the issue in the district court, we decline to address it on appeal.

¶22    II.   Did the court err in finding that LHC’s concrete was delivered to

Alvarez’s mini-storage facility on August 11, 12 and 13?

¶23    Alvarez also argues that LHC failed to prove that concrete was delivered to

Alvarez’s property on August 11, 12 and 13, as claimed in the lien. LHC’s sole evidence

that delivery occurred on these dates was invoice 6576 and the corresponding scale

tickets. Only one employee, Carol Phillips, LHC’s controller, testified regarding invoice

6576. She testified that she did not know who provided the information on the invoice

and scale tickets, in particular the dates and the location. She further testified that the

material was not hauled by an LHC truck, that she did not know who hauled the material

and that she had no independent knowledge of where the material was delivered, other

than what was written on the invoice and scale tickets. Finally, Alvarez testified that no

materials were delivered after August 8.



                                           6
¶24    Alvarez is correct that § 71-3-524, MCA, requires that materials be supplied with

the intent that they be incorporated into an improvement on the property to which the lien

attaches and that the materials actually are incorporated into the improvement. Further,

the delivery of materials to the site of the improvement, whether by the lien claimant or

another, creates a presumption that the materials were incorporated. Section 71-3-524(2),

MCA.

¶25    Here, based on invoice 6576 and the corresponding scale tickets, which were

submitted without objection and explained by Phillips, the District Court determined that

materials were delivered, on August 11, 12 and 13, to Alvarez’s property and

subsequently used in the construction of the mini-storage facility. Despite Alvarez’s

contention otherwise, the evidence presented to the court was substantial. Once a proper

foundation has been laid, a court may rely on business records as evidence that an event

took place. Here, Alvarez did not object to the admission of the invoice or scale tickets

and admitted that the proper foundation was laid. Both the invoice and scale tickets state

that on August 11, 12 and 13, asphalt was delivered to “ASHRD STG.” As Alvarez’s

mini-storage facility is located on Ash Road, these documents indicate that materials

were delivered to Alvarez’s property on August 11, 12 and 13. The District Court’s

corresponding determination was thus not clearly erroneous.

¶26    III. Did the court err in awarding prejudgment interest?

¶27    Alvarez argues that prejudgment interest is not appropriate under § 27-1-211,

MCA, because the court rejected LHC’s accounting and reduced the lien from $16,568 to

$14,201.58. Thus, according to Alvarez, the amount was not certain.

                                        7
¶28    Section 27-1-211, MCA, provides:

       Every person who is entitled to recover damages certain or capable of being
       made certain by calculation and the right to recover [is vested] upon a
       particular day is entitled also to recover interest thereon from that day . . . .

¶29    The three criteria which must be satisfied for an award of prejudgment interest are:

(1) an underlying monetary obligation; (2) the amount of recovery must be certain or

capable of being made certain by calculation; and (3) the right to recover must vest on a

particular day. James Talcott Const., ¶ 40. However, “the fact that a claim is disputed

does not make it uncertain,” as long as the damage amount is reduced to certainty on a

particular day. Safeco Ins. Co. v. Lovely Agency, 215 Mont. 420, 425, 697 P.2d 1354,

1357 (1985) (citations omitted). Additionally, the proper accrual date for the calculation

of interest on a construction lien is the date the lien is filed. James Talcott Const., ¶ 39

(citations omitted).

¶30    Here, the underlying monetary obligation was the balance remaining for materials

provided to Alvarez’s property. LHC’s calculations differed from the court’s regarding

the $10,000 payment made by Young on October 9, 2003. LHC credited a portion of the

$10,000 to invoices incurred by Young while working on projects undertaken subsequent

to the Alvarez project. The court, however, found that LHC’s accounting was “contrary

to its stated accounting practice,” and therefore applied the full $10,000 to the Alvarez

account. Consequently, the court determined that the balance remaining for materials

provided to Alvarez’s property was $14,201.58, less than the amount calculated by LHC.

¶31    While the court’s conclusion differed from the original figure listed by LHC in its

lien, the amount was still capable of being made certain by calculation. Further, the right

                                           8
to recover vested on November 10, 2003, when the lien was filed.          Thus, the court

correctly awarded prejudgment interest pursuant to § 27-1-211, MCA.

¶32   IV. Did the court err in awarding attorney fees?

¶33   Alvarez does not dispute the court’s authority to award attorney fees for the

enforcement of a construction lien. Instead, Alvarez contends that LHC should only

recover attorney fees in proportion to the percentage of its claimed lien that the court

enforced.

¶34   LHC responds that the court properly awarded attorney fees because § 71-3-

124(1), MCA, provides for the award of attorney fees in an action to foreclose a lien.

Additionally, LHC provided the court with an affidavit in support of the reasonableness

of its attorney fees. Alvarez, however, replies that § 71-3-124(1), MCA, only allows

attorney fees for a claimant “whose lien is established.”       As the court found that

$14,201.58 was due, as opposed to the $16,568 claimed in LHC’s lien, LHC, according

to Alvarez, should only receive 86 percent of its attorney fees, in proportion to the ratio

of LHC’s success to the amount claimed in the lien.

¶35   “The fact that [the claimant] did not receive the entire amount of his claim does

not alter” the award of attorney fees mandated by § 71-3-124, MCA. Donnes v. Orlando,

221 Mont. 356, 362, 720 P.2d 233, 237 (1986). While § 71-3-124, MCA, does require a

claimant’s lien be established in order for attorney fees to be awarded, and, in fact,

awards attorney fees to a defendant where a lien is not established, the statute does not

require a proportional reduction in attorney fees where judgment is for a lesser amount



                                         9
than was claimed in the lien. The District Court thus did not abuse its discretion in

awarding attorney fees.

                                       CONCLUSION

¶36      We uphold the District Court’s enforcement of LHC’s construction lien against

Alvarez’s property as well as its award of prejudgment interest and attorney fees and

costs.

                                                   /S/ W. WILLIAM LEAPHART

We concur:

/S/ PATRICIA COTTER
/S/ BRIAN MORRIS
/S/ JIM RICE




Justice James C. Nelson concurs.

¶37      I reluctantly concur in the Court’s decision.

¶38      As the Court notes in ¶ 18 of the Opinion, the lien states that the materials were

furnished between August 9 and August 14, 2003. Two invoices admitted in evidence

indisputably cover materials and services outside the times claimed in the lien.

Specifically, invoice 6521, in the amount of $20,119.00, is for concrete delivered from

August 5 to August 8, and invoice 6612, in the amount of $4,475.00, is for flowboys and

water trucks delivered on July 29 and 30 and August 5, 7, and 8. Facially, these two

invoices are for materials and services delivered prior to the times covered by the lien.

The lien is, therefore, deficient on its face under § 71-3-535(3)(g)(i) and (ii), MCA.


                                           10
Unfortunately, because Alvarez did not properly raise this argument in the District Court,

that court was and this now Court is in the position of having to enforce a facially

deficient construction lien.

¶39    For this reason, I would specifically limit our decision to the facts of this case. To

that extent, I concur.


                                          /S/ JAMES C. NELSON




                                         11