December 4 2008
DA 06-0774
IN THE SUPREME COURT OF THE STATE OF MONTANA
2008 MT 407
CLARK FORK COALITION, ROCK CREEK
ALLIANCE, INC., CABINET RESOURCE
GROUP, INC., MONTANA ENVIRONMENTAL
INFORMATION CENTER, INC., AND TROUT UNLIMITED,
Plaintiffs and Appellants,
v.
MONTANA DEPARTMENT OF ENVIRONMENTAL QUALITY,
Defendant and Appellee.
APPEAL FROM: District Court of the First Judicial District,
In and For the County of Lewis And Clark, Cause No. BDV 2002-70
Honorable Jeffrey M. Sherlock, Presiding Judge
COUNSEL OF RECORD:
For Appellants:
Jack R. Tuholske (argued), Attorney at Law, Missoula, Montana
Matt Clifford (argued), Attorney at Law, Missoula, Montana
David K. W. Wilson, Jr, Attorney at Law, Helena, Montana
For Appellee:
Claudia L. Massman (argued), Special Assistant Attorney General, Helena,
Montana
Argued and Submitted: November 7, 2007
Decided: December 4, 2008
Filed:
__________________________________________
Clerk
Justice John Warner delivered the Opinion of the Court.
¶1 In 2001, the Montana Department of Environmental Quality (DEQ) issued a Montana
Pollution Discharge Elimination System (MPDES) permit to Revett Silver Company
authorizing Revett to discharge water into the Clark Fork River from its proposed mine, the
Rock Creek Mine. The Appellants, four organizations with interests in protecting the Clark
Fork River (collectively, the Coalition), brought suit against DEQ alleging, inter alia, that
the MPDES permit issued to Revett violated the Montana Water Quality Act (WQA). The
Coalition now appeals from an order of the First Judicial District, Lewis and Clark County,
granting summary judgment to DEQ and holding that the MPDES permit issued to Revett for
its proposed Outfall 001 does not violate the WQA.
ISSUES
¶2 We consolidate and restate the issues presented as follows:
¶3 1. Should this Court give deference to DEQ’s interpretation of Admin. R. M.
17.30.715 in determining whether a proposed action will result in nonsignificant changes in
water quality?
¶4 2. Does Admin. R. M. 17.30.715, as interpreted by DEQ and applied in this case,
violate the nondegradation provisions of the Montana Water Quality Act?
FACTUAL AND PROCEDURAL BACKGROUND
¶5 Revett Silver Company, formerly Sterling Mining Company, has proposed
construction of the Rock Creek Mine, a silver/copper mine to be located in the Cabinet
Mountains of northwestern Montana adjacent to the Cabinet Mountain Wilderness Area.
Revett proposes to bore an adit, or horizontal mine shaft, for approximately three miles under
the Cabinet Mountains where it will extract ore and transport it through the adit to a mill for
2
processing. The mine’s production life is anticipated to be thirty to thirty-seven years. Once
the adit is completed, it will begin discharging water. According to the DEQ’s analysis, the
discharge of water will continue for years after the mine closes and it may well be perpetual.
The discharged water is expected to contain arsenic, ammonia, nitrate-nitrogen, and heavy
metals among other pollutants, which will exceed allowable water quality standards if the
discharged water is not treated to remove contaminants.
¶6 The Clark Fork River lies southwest of the proposed mine, and Revett has proposed
discharging the water from the mine into the river. Revett proposes to first transport the
water to a treatment plant and, after nearly all of the pollutants are removed, put the treated
water into the Clark Fork River using a diffuser which would disburse the water across the
width of the river.
¶7 Prior to permitting Revett to conduct mining activities, DEQ prepared an
Environmental Impact Statement (EIS) and a supplemental EIS. DEQ also required Revett
to apply for an MPDES permit that would allow the discharge of water into the Clark Fork
River.
¶8 On December 1, 2001, DEQ issued a Record of Decision (ROD), based on the EIS,
which established the preferred alternative for the Rock Creek Mine and announced the
decision that the MPDES permit would be issued as the proposed discharge of water into the
Clark Fork River was deemed nonsignificant.
¶9 Under the permit as approved, either the Outfall 001 adit, which remains at issue in
this case, would be plugged, or the water would continue to be discharged to the Clark Fork
River. The ROD concedes that it is uncertain whether it is possible to plug the adit, and, if it
3
cannot be plugged, it is unknown how long the discharge would continue after the mine is
closed. Thus, on-going monitoring and treatment would be required to ensure that the water
quality meets the necessary standards. The discharged water will require treatment until it
stops coming out of the mountains or meets water quality standards without treatment,
whenever, or if ever, that may occur. Therefore, the EIS assumes, and the ROD requires, that
treatment continue in perpetuity.
¶10 When the ROD was issued, DEQ granted Revett an MPDES permit which authorizes
discharge of treated waste water into the Clark Fork River at five different outfall points.
Only the outfall designated as Outfall 001 remains at issue in this litigation. Outfall 001
would consist mainly of ground water discharged from the three mile long mine adit,
domestic waste water, and storm water, as well as a smaller amount of water used to process
ore. The discharges from Outfall 001 are projected to range from 4 to 2,300 gallons per
minute. The MPDES permit was issued on the presumption that the ground water discharges
will be perpetual and cannot be stopped once Revett bores the adit and begins mining.
¶11 The WQA generally requires DEQ to conduct a nondegradation review prior to
issuing an MPDES permit. Nondegradation review is a rigorous process designed to
examine the various alternatives available to complete a specific proposed project that will
diminish water quality. The review examines social costs as well as economic costs
involved in a project. It also considers whether a particular project is necessary and
advisable.
¶12 Section 75-5-301(5)(c), MCA, provides that the Board of Environmental Review
(BER) shall establish criteria for determining whether a proposed activity will result in
4
nonsignificant changes in water quality. If a proposed activity is determined to involve only
nonsignificant changes, nondegradation review is not required.
¶13 The statutory criteria the legislature has required BER to consider in deciding whether
a proposed discharge of water is nonsignificant include: an examination of the potential for
harm to human health; the quantity and the strength of the pollutant; the length of time the
degradation will occur; and the character of the pollutant. Section 75-5-301(5)(c), MCA. To
comply with its statutory mandate to establish criteria for determining whether a proposal
will result in only nonsignificant changes in water quality, BER adopted Admin. R. M.
17.30.715.
¶14 Applying Admin. R. M. 17.30.715, DEQ determined that Revett’s proposed
discharges would result in nonsignificant degradation of the Clark Fork River. Therefore,
DEQ issued the MPDES permit to Revett without conducting non-degradation review.
¶15 DEQ based its conclusion that the discharge would not cause significant degradation
to the Clark Fork River on the information gathered in the EIS, which says that the water
coming from the mine can and will be treated so that pollutants are removed before the water
is discharged into the river. The EIS and the ROD also call for the construction of an
evaluation adit, which will allow further evaluation of the expected levels of water pollution.
This will allow for further decisions concerning the necessary water treatment required if the
main ore adit is completed.
¶16 A complete mine closure plan has not yet been formulated. The EIS indicates that a
closure plan will be formulated if and when the mine is opened and more information
becomes available. However, the ROD upon which the MPDES permit was issued
5
incorporates an initial mine closure plan, which assumes Revett will be required to treat the
mine water in perpetuity.
¶17 On March 21, 2002, the Coalition filed an amended complaint challenging issuance of
the MPDES permit. The complaint also alleged violations of the WQA and the Montana
Constitution; those allegations were subsequently dismissed by stipulation and are not at
issue here.
¶18 On August 11, 2005, the Coalition moved for partial summary judgment regarding
three of the permitted outfalls, including Outfall 001. The Coalition argued that the MPDES
permit for Outfall 001 was improper because, in determining that the proposed discharge was
nonsignificant, and thus issuing the permit without conducting a nondegradation review,
DEQ did not adequately consider the length of time the proposed discharge would last. On
March 24, 2006, the District Court denied the Coalition’s motion for summary judgment as
to Outfall 001 and granted DEQ’s motion for summary judgment concluding that it had
correctly issued the MPDES permit on Outfall 001. On October 9, 2006, pursuant to
stipulation, the District Court dismissed the remaining claims and entered a final judgment
that the MPDES permit for Outfall 001 did not violate the WQA. The Coalition filed a
timely appeal of the judgment.
STANDARDS OF REVIEW
¶19 Summary judgment is appropriate when there are no material facts in dispute and the
movant is entitled to judgment as a matter of law. We review de novo a district court’s
ruling on a summary judgment motion, applying the same criteria as the district court. Mont.
Trout Unlimited v. Mont. Dept. of Nat. Resources & Conserv., 2006 MT 72, ¶ 17, 331 Mont.
6
483, ¶ 17, 133 P.3d 224, ¶ 17. We review the district court’s conclusions of law to determine
if they were correct. Mont. Trout Unlimited, ¶ 17. In this case, there are no material facts at
issue. While DEQ does not concede that the discharge of water from Outfall 001 containing
high levels of pollutants will be perpetual, it does not dispute that the EIS and ROD assume
that this will be the case. The MPDES permit was issued on such assumption.
¶20 An agency’s interpretation of its rule is afforded great weight, and the court should
defer to that interpretation unless it is plainly inconsistent with the spirit of the rule. The
agency's interpretation of the rule will be sustained so long as it lies within the range of
reasonable interpretation permitted by the wording. Kirchner v. Mont. Dept. Pub. Health &
Human Servs., 2005 MT 202, ¶ 18, 328 Mont. 203, ¶ 18, 119 P.3d 82, ¶ 18; Juro’s United
Drug v. Mont. DPHHS, 2004 MT 117, ¶ 12, 321 Mont. 167, ¶ 12, 90 P.3d 388, ¶ 12; Easy v.
Mont. DNRC, 231 Mont. 306, 309, 752 P.2d 746, 748 (1988). Conversely, of course, neither
this Court nor the district court must defer to an incorrect agency decision. Juro’s, ¶ 12;
Grouse Mountain Assocs. v. Mont. Dept. of Pub. Serv. Reg., 284 Mont. 65, 69, 943 P.2d 971,
973 (1997).
¶21 We review an agency decision not classified as a contested case under the Montana
Administrative Procedure Act1 to determine whether the decision was “arbitrary, capricious,
unlawful, or not supported by substantial evidence.” Johansen v. State, 1999 MT 187, ¶ 11,
295 Mont. 339, ¶ 11, 983 P.2d 962, ¶ 11. In reviewing an agency decision to determine if it
survives the arbitrary and capricious standard, we consider whether the decision was “based
7
on a consideration of the relevant factors and whether there has been a clear error of
judgment.” North Fork Pres. Assn. v. Dept. of State Lands, 238 Mont. 451, 465, 778 P.2d
862, 871 (1989) (quoting Marsh v. Or. Nat. Resources Council, 490 U.S. 360, 378, 109 S.
Ct. 1851, 1861 (1989)). While our review of agency decisions is generally narrow, we will
not “automatically defer to the agency ‘without carefully reviewing the record and satisfying
themselves that the agency has made a reasoned decision.’” Friends of the Wild Swan v.
DNRC, 2000 MT 209, ¶ 28, 301 Mont. 1, ¶ 28, 6 P.3d 972, ¶ 28 (quoting Marsh, 490 U.S. at
378, 109 S. Ct. at 1861) (hereinafter Friends of the Wild Swan I).
DISCUSSION
¶22 Issue 1: Should this Court give deference to DEQ’s interpretation of Admin. R. M.
17.30.715 in determining whether a proposed action will result in nonsignificant changes in
water quality?
¶23 Conceding that there is no Montana authority on point, the Coalition urges this Court
to adopt a new standard of review for environmental matters in which no deference is given
to DEQ’s interpretation of rules adopted by BER, including Admin. R. M. 17.30.715. The
Coalition argues that, because the Court held in Montana Environmental Information Center
v. Mont. DEQ, 1999 MT 248, 296 Mont. 207, 988 P.2d 1236 (hereinafter MEIC),
environmental rights stated in Article II, Section 3 and Article IX, Section 1 of the Montana
1
“Contested cases” involve adjudicatory proceedings for a determination of legal rights, duties, or
privileges of a party. Section 2-4-102(4), MCA. The decision to issue the MPDES permit in this
8
Constitution are fundamental rights, any statute or rule implicating the environment must be
subjected to a strict scrutiny analysis by the courts. MEIC, ¶ 63. Thus, argues the Coalition,
no deference can be given to DEQ’s interpretation of Admin. R. M. 17.30.715.
¶24 In MEIC, the Court held, to the extent § 75-5-317(2)(j), MCA (1995), arbitrarily
excluded certain activities from nondegradation review without regard to the nature or
volume of the substances being discharged, it violated environmental rights guaranteed by
Article II, Section 3 and Article IX, Section 1 of the Montana Constitution. The Court
specifically limited its holding to § 75-5-317(2)(j), MCA (1995), as applied to the facts in
MEIC. MEIC, ¶ 80. The Coalition, in essence, argues that the courts must examine the
environmental decisions of DEQ without granting deference to DEQ’s expertise and
experience in the protection of the environment under legislative guidelines.
¶25 In this case, the Coalition asks this Court to mis-apply MEIC. The coalition has
neither challenged the constitutionality of § 75-5-301(5)(c), MCA, or Admin. R. M.
17.30.715 nor alleged that BER or DEQ excluded from review the nature or volume of the
substances Revett proposes to discharge into the Clark Fork River.
¶26 In this action, the Coalition seeks to have this Court reverse the District Court and
hold that the discharge from Outfall 001 must undergo full nondegradation review because
of the assumed perpetual nature of the discharge. The Coalition argues in the alternative that
DEQ erroneously interpreted Admin. R. M. 17.30.715, and that its decision to issue an
MPDES permit to Revett was arbitrary and capricious. Therefore, in this instance, the Court
is asked to examine whether DEQ’s interpretation of Admin. R. M. 17.30.715 is correct, and
instance does not fall within the category of contested cases.
9
whether its application of that regulation is arbitrary and capricious. Such an examination
does not require the application of one of the three levels of scrutiny applied to statutes on
constitutional challenge.
¶27 The decisions for the Court in this case fall squarely within the established standards
noted in ¶¶ 19, 20 above. This Court defers to an agency’s interpretation of one of its
regulations, unless such interpretation is plainly inconsistent with the spirit of the regulation.
The agency’s interpretation of a regulation “will be sustained so long as it lies within the
range of reasonable interpretation permitted by the wording.” Kirchner, ¶ 18. However, we
will not defer to an incorrect agency decision. Juro’s, ¶ 12. Likewise, in examining whether
an agency decision applying a regulation was arbitrary or capricious, the courts consider
whether the decision was based on a consideration of the relevant factors and whether there
has been a clear error of judgment. The inquiry must be searching and careful, but the
ultimate standard of review is a narrow one. The courts do not substitute their judgment for
that of the agency by determining whether its decision was correct. Rather, the courts
examine the decision to determine if it was made on sufficient information, or whether the
decision was so at odds with the information gathered that it could be characterized as
arbitrary or the product of caprice. North Fork Pres. Assn., 238 Mont. at 465, 778 P.2d at
871.
¶28 Considering the Coalition’s as applied challenges to DEQ’s decision to issue Revett
an MPDES permit for Outfall 001 pursuant to § 75-5-301(5)(c), MCA, and Admin. R. M.
17.30.715, we decline to adopt new standards for review of agency decisions which concern
environmental matters.
10
¶29 Issue Two: Does Admin. R. M. 17.30.715, as interpreted by DEQ and applied in this
case, violate the nondegradation provisions of the Montana Water Quality Act?
¶30 The federal Clean Water Act (CWA) mandates that states manage water pollution in
two ways. First, states must control the discharge of pollutants into waters of the United
States through a permitting process. 33 U.S.C. § 1342. In Montana, the DEQ administers
this requirement of the CWA by use of a permitting system which results in the issuance or
denial of an MPDES permit such as the one at issue here.
¶31 Second, in addition to issuing permits controlling discharges, states are required to
establish water quality standards to prevent degradation of waters and protect the designated
uses of the water. 33 U.S.C. § 1313(c). The United States Environmental Protection Agency
(EPA) has established three different tiers of water quality, and each tier must meet a specific
set of antidegradation standards. 40 C.F.R. § 131.12. The Clark Fork River, at issue here, is
classified as Tier 2. Tier 2 waters are considered high quality waters. States must maintain
Tier 2 water at a level that supports propagation of fish, shellfish, and wildlife and recreation
in and on the water unless lower water quality is necessary to accommodate important
economic or social development. 40 C.F.R. § 131.12(a)(2).
¶32 Montana has implemented the federal nondegradation policy by enacting the Montana
WQA. See § 75-3-301, MCA, et seq. Under Montana law, the DEQ cannot authorize
degradation of Tier 2 waters such as the Clark Fork River unless, in the nondegradation
review process, the party proposing the degradation demonstrates, by a preponderance of
evidence:
11
(a) degradation is necessary because there are no economically,
environmentally, and technologically feasible modifications to the proposed
project that would result in no degradation;
(b) the proposed project will result in important economic or social
development and that the benefit of the development exceeds the costs to
society of allowing degradation of high-quality waters;
(c) existing and anticipated use of state waters will be fully protected; and
(d) the least degrading water quality protection practices determined by the
department to be economically, environmentally, and technologically feasible
will be fully implemented by the applicant prior to and during the proposed
activity.
Section 75-5-303(3), MCA. Nondegradation review would require Revett’s proposed
discharges to meet significantly higher standards to justify construction of the mine. Also,
nondegradation review would require the proposed mine to undergo greater public scrutiny
than is required by the MPDES permit at issue here.
¶33 Montana law establishes two exceptions to the rule that proposals to discharge into
Tier 2 waters must undergo nondegradation review under § 75-5-303, MCA. First, the
Montana legislature has established categories of activities that are statutorily exempt from
nondegradation review. Section 75-5-317, MCA. No statutory exemptions apply here.
Second, the 1993 Montana legislature authorized the Montana Bureau of Environmental
Review (BER) to establish criteria to determine whether a particular activity will cause only
nonsignificant changes in water quality. Section 75-5-301(5)(c), MCA. The legislature
directed that:
These criteria must be established in a manner that generally:
(i) equates significance with the potential for harm to human health, a
beneficial use, or the environment;
(ii) considers both the quantity and the strength of the pollutant;
(iii) considers the length of time the degradation will occur;
(iv) considers the character of the pollutant so that greater significance is
associated with carcinogens and toxins that bioaccumulate or biomagnify and
12
lesser significance is associated with substances that are less harmful or less
persistent.
Section 75-5-301(5)(c), MCA.
¶34 Pursuant to this statute, the BER promulgated Admin. R. M. 17.30.715 to determine
whether a proposed activity results in a nonsignificant discharge. Admin. R. M.
17.30.715(1) provides in part:
These criteria consider the quantity and strength of the pollutant, the length of
time the changes will occur, and the character of the pollutant. Except as
provided in (2), changes in existing surface or ground water quality resulting
from the activities that meet all the criteria listed below are nonsignificant, and
are not required to undergo review under 75-5-303, MCA . . . .
The regulation goes on to list the pollutant levels that DEQ must consider when determining
if a proposed activity is nonsignificant. An activity must comply with the criteria in Admin.
R. M. 17.30.715(1) to be considered nonsignificant. If a proposed activity will degrade
water quality by introducing pollutants beyond the levels established in the regulation, the
activity is significant and must undergo nondegradation review before DEQ may issue an
MPDES permit. Conversely, if an activity will not result in degradation of water quality, the
activity may be considered nonsignificant and the permit issued.
¶35 Even though a proposal for discharge complies with Admin. R. M. 17.30.715(1), the
regulation also gives DEQ discretion to determine the proposed activity is nonetheless
significant based on the factors listed in Admin. R. M. 17.30.715(2). These discretionary
criteria include “any other information deemed relevant by the department and that relates to
the criteria” listed in subsection (1). Admin. R. M. 17.30.715(2)(g).
13
¶36 DEQ argued in the District Court, based on the information in the EIS, the proposed
discharge at Outfall 001 would not introduce pollutants exceeding the levels established in
Admin. R. M. 17.30.715(1) into the Clark Fork River. In reaching this conclusion, DEQ
presumed waste water would discharge perpetually and also that such water would be treated
perpetually. If these assumptions are correct, the proposed discharge would never result in
any degradation of the Clark Fork River and there is no need to conduct a nondegradation
review. The District Court, in denying the Coalition’s motion for summary judgment,
reasoned that, because the proposed discharge from Outfall 001 would meet applicable water
quality standards for an indefinite time, DEQ adequately considered the length of time it
would occur. The District Court entered summary judgment in favor of DEQ based on this
reasoning.
¶37 DEQ states on appeal that the ROD considers the length of time the proposed
discharge from Outfall 001 will continue, as required by Admin. R. M. 17.30.715(1), by
assuming that it will be perpetual. DEQ then posits, since the proposal asserts the water
discharged from Outfall 001 will also be treated perpetually, it will never contain pollutants
exceeding established levels. Thus, the discharge is nonsignificant.
¶38 DEQ interprets Admin. R. M. 17.30.715(2)(g), which provides that it has discretion to
consider any other information which relates to the criteria in sub-division (1) of the
regulation, as limited in application to those few instances where the specific criteria in sub-
division (1) fail to account for site-specific conditions or newly acquired information. Based
on this interpretation, DEQ refused to exercise its discretion under sub-section (2)(g) of
Admin. R. M. 17.30.715 to consider independently of Revett’s proposal that the polluted
14
water discharged from Outfall 001: (a) cannot be stopped; (b) will likely discharge up to 3.3
million gallons of water per day into the Clark Fork River; and (c) will require treatment in
perpetuity.
¶39 While this Court generally gives respectful consideration to an agency’s interpretation
of its regulations, Mont. Power Co. v. Mont. Public Serv. Commn., 2001 MT 102, ¶ 25, 305
Mont. 260, ¶ 25, 26 P.3d 91, ¶ 25, we conclude that DEQ’s interpretation of Admin. R. M.
17.30.715(2) is incorrect. It is not within the range of reasonable interpretation permitted by
the regulation’s wording and is plainly inconsistent with the spirit of the rule.
¶40 The pollutant levels permitted under Admin. R. M. 17.30.715(1) do incorporate a
consideration of the length of time a discharge will continue. Therefore, the time element of
a discharge is implicitly considered as required by § 75-5-301(5)(c)(iii), MCA. However,
DEQ’s interpretation of sub-section (2) of the regulation, to the effect that it may not
independently consider the relevant facts that the discharge cannot be stopped and will
require perpetual treatment, is inconsistent with the spirit of the rule and contrary to the
wording of both § 75-5-301(5)(c)(iii), MCA, and Admin. R. M. 17.30.715(1), (2).
¶41 A regulation is to be read in its entirety. See Friends of the Wild Swan v. Mont. DEQ,
2005 MT 351, ¶ 16, 330 Mont. 186, ¶ 16, 127 P.3d 394, ¶ 16 (hereinafter Friends of the Wild
Swan II). Sub-division (2) of Admin. R. M. 17.30.715 provides:
Notwithstanding compliance with the criteria of (1), the department may
determine that the change in water quality resulting from an activity which
meets the criteria in (1) is degradation based upon the following:
. . .
15
(g) any other information deemed relevant to the department and that relates
to the criteria in (1).
BER recognized when it adopted sub-division (2) that situations arise where the criteria in
Admin. R. M. 17.30.715(1) would be inadequate to protect against degradation. As the BER
stated when the regulation went into effect:
It is unlikely that a set of criteria for nonsignificance can be developed that
would sufficiently fulfill the goal of preventing degradation in every instance.
Given that implementation of the policy under the rules has yet to be tested, it
is important that the [DEQ] have discretion to make a determination of
significance independent of the criteria in [17.30.715(1)].
15 Mont. Admin. Register 2209 (Aug. 11, 1994).
¶42 Sub-division (2)(g) of Admin. R. M. 17.30.715 vests in DEQ the discretion to
carefully examine and consider, independently of sub-division (1) of the regulation, whether
a proposed activity such as the Rock Creek Mine can safely be deemed nonsignificant. In
promulgating Admin. R. M. 17.30.715, BER intended DEQ exercise its discretion granted by
sub-division (2) to re-evaluate a decision made under sub-division (1) in order to fulfill the
goal of preventing degradation in every instance.
¶43 Failure of a district court to exercise discretion is itself an abuse of discretion. State v.
Weaver, 276 Mont. 505, 509, 917 P.2d 437, 440 (1996); see also Columbia Falls Elem. Sch.
Dist. No. 6 v. State, 2005 MT 69, ¶ 48, 326 Mont. 304, ¶ 48, 109 P.3d 257, ¶ 48 (Nelson, J.,
concurring) (stating that a choice not to act is an act itself). Likewise, when an agency,
because of a misinterpretation of its rule, does not exercise its discretion it abuses its
discretion. In other words, an agency, “vested with discretion, abuses that discretion when it
behaves as if it has no other choice than the one it has taken, as well as when it makes a
16
decision for which there is not adequate support.” Bennington Housing Authority v. Bush,
933 A.2d 207, ¶ 12 (Vermont, 2007); Litterer v. Judge, 644 N.W.2d 357, 362 (Iowa, 2002);
See Charles H. Koch, 3 Administrative Law and Practice § 10.6 [3] (2d ed., West 1997)
(“Failure to exercise discretion might be an abuse of discretion.”); 73A C.J.S. Public
Administrative Law and Procedure § 416 (2004) (“An agency that has authority to act but
fails to exercise that authority based upon a false belief that there is no such authority abuses
its discretion.”). DEQ’s misinterpretation of Admin. R. M. 17.30.715(2) resulted in the
agency’s refusal to consider, independent of the criteria in sub-division (1), that Revett’s
proposed discharge of polluted water cannot be stopped and will be perpetual. Under the
facts of this case, DEQ’s failure to exercise the discretion granted by Admin. R. M.
17.30.715(2), resulted in an arbitrary and capricious decision that the discharge from Outfall
001 will always be nonsignificant.
¶44 The very examples DEQ presented to the Court in support of its erroneous
interpretation of Admin. R. M. 17.30.715(1), (2) illustrate its error. DEQ points out that a
municipal water treatment plant may last forever and that a sub-division’s sewage treatment
plant may be required forever. Both require MPDES permits, which can be revoked if
pollution occurs. Also, the water will require perpetual treatment. Because the water will
always be treated, any discharge will be nonsignificant under Admin. R. M. 17.30.715. DEQ
argues these same facts apply in this instance. What DEQ ignores is that, in these examples,
someone who is available will always need the water from the treatment plant or a permit
from DEQ to discharge sewage. If whoever needs the water or sewage plant does not clean
up the water as required, DEQ can revoke the MPDES permit and shut the plant down.
17
However, in the case of Outfall 001, it is a given that the mine will close in a few years,
Revett will be gone, and the polluted discharge will continue and cannot be shut off. An
independent determination under Admin. R. M. 17.30.715(2)(g) of the significance of the
polluted discharge from Outfall 001, after the mine has closed, Revett is gone, and the
MPDES permit becomes meaningless is obviously a most excellent idea.2 It is an arbitrary
and capricious decision not to make such an independent examination.
¶45 DEQ alternatively argues that the proposed discharge from Outfall 001 is
nonsignificant because Revett is required to provide a bond which will guarantee that funds
are available to treat the polluted water as long as necessary. In this regard, the EIS states
that it is unlikely the mine discharge would ever meet applicable standards and that treatment
in perpetuity would require continued operation and maintenance of the water treatment
facility, as well as the pipeline between the mine and the point of discharge. The EIS then
makes the observation that the project would require sufficient bonding to cover the need for
long-term water treatment. The ROD requires that a reclamation bond for costs associated
with wastewater treatment be posted by Revett and maintained at a level adequate for DEQ
and the U.S. Forest Service to implement reclamation plans. It goes on to say that the range
of the required bond for post-mining wastewater treatment is estimated to be between
$14,381,518 and $44,423,628, depending on how long treatment may be required.
¶46 The EIS sets out DEQ’s estimates of the costs of running the proposed Anoxic
Biotreatment System and the Reverse Osmosis water treatment plant based on the design put
2
Revoking an MPDES permit for a closed mine does nothing to stem pollution. Enforcement
actions against an entity that is gone are unavailing.
18
forth by Revett’s predecessor, Sterling Mining Company. However, no information is given
on how these estimated costs, which were used to estimate the possible size of the necessary
reclamation bond, were arrived at. Likewise, the ROD contains no information on how the
estimated bond requirements were calculated. An exhibit to the ROD seems to state that the
estimated annual operating and maintenance costs of water treatment will be $1,200,000, but
there is no specific information regarding what was considered to arrive at this amount.
There is no indication in the EIS whether the proposed Anoxic Biotreatment and Reverse
Osmosis systems Revett plans to use to treat polluted wastewater can be maintained for a
substantial number of years, or in perpetuity. There is no analysis concerning whether or
when the treatment facilities will require complete replacement. Likewise, there is no
examination of other factors which might come into play when it is necessary to perpetually
clean a discharge of polluted water that cannot be stopped. There is no consideration of
whether it is possible to purchase a bond guaranteeing payment of perpetual treatment costs,
while it is known that the principal will close its mine and may become a shell corporation or
dissolve. And, there is no record of whether Revett is willing to post in advance the many
millions in cash required to pay for perpetual treatment. The ROD does not consider even
these obvious problems associated with opening Outfall 001.
¶47 An agency must take a “hard look” at the environmental impacts of a given project or
proposal. Ravalli Cty. Fish & Game Assn., Inc. v. Mont. Dept. of State Lands, 273 Mont.
371, 377, 903 P.2d 1362, 1367 (1995). Implicit in the requirement that an agency take a hard
look at the environmental consequences of its actions is the obligation to make an adequate
compilation of relevant information, to analyze it reasonably, and to consider all pertinent
19
data. Ravalli Cty. Fish & Game Assn., Inc., 273 Mont. at 381, 903 P.2d at 1369 (1995)
(citing Sierra Club v. U. S. Army Corps of Engrs., 701 F.2d 1011, 1029 (2nd Cir. 1983)).
Admittedly, court review of an agency decision, including an environmental decision, is
limited. Friends of the Wild Swan I, ¶ 28. Still, while a court is not to substitute its
judgment for that of the agency, the agency must examine the relevant data and articulate a
satisfactory explanation for its action, including a rational connection between the facts
found and the choice made. Motor Vehicle Mfrs. Assn. v. State Farm Mut. Auto. Ins. Co.,
463 U.S. 29, 43, 103 S. Ct. 2856, 2866 (1983). In other words, the Court looks closely at
whether the agency has taken a hard look at the question presented. The Court does not take
a hard look itself but requires that the agency does so. The Court focuses on the validity and
appropriateness of the administrative decision making process without intense scrutiny of the
decision itself. In this way, the Court examines the elements of the decision without
interfering with the administrative authority over the decision itself. Koch, 3 Administrative
Law and Practice at § 10.5.
¶48 An agency must supply a statement of reasons why potential impacts of a proposed
action such as Outfall 001 are nonsignificant. Ravalli Cty. Fish & Game Assn., Inc., 273
Mont. at 382, 903 P.2d at 1370. A simple statement that a perpetual discharge of polluted
water will always be treated is insufficient to justify a determination that an irreversible
discharge is nonsignificant. DEQ has misinterpreted its own regulation and has not taken a
hard look at what will be required to maintain the quality of the Clark Fork River after the
mine closes and Outfall 001 continues to discharge polluted water, perhaps forever. This
includes a failure to take an initial hard look at whether bonding can be a sufficient remedial
20
measure before deciding to issue an MPDES permit on the basis that a discharge is, and will
continue to be, nonsignificant.
CONCLUSION
¶49 We do not hold that the discharge from Outfall 001 cannot, under any circumstances,
be nonsignificant. It is possible that DEQ could, after a further consideration of all facets of
Revett’s plan, determine that the anticipated discharge from Outfall 001 is nonsignificant
under § 75-5-301, MCA, and Admin. R. M. 17.30.715. We do, however, conclude, because
DEQ has not made an independent examination of the length of time the proposed discharge
of polluted water will continue, as provided for in Admin. R. M. 17.30.715(2), and has not
taken a hard look at all of the consequences reasonably anticipated from boring an adit that
cannot be plugged, the agency made an arbitrary and capricious decision by issuing an
MPDES permit to Revett for Outfall 001.
¶50 The summary judgment in favor of DEQ is reversed and this case is remanded to the
District Court for entry of an order remanding consideration of Revett’s application for an
MPDES permit to DEQ for further proceedings in conformity herewith.
/S/ JOHN WARNER
We Concur:
/S/ JAMES C. NELSON
/S/ PATRICIA COTTER
/S/ W. WILLIAM LEAPHART
/S/ BRIAN MORRIS
21
Justice Jim Rice concurring in part and dissenting in part.
¶51 I concur with the Court’s resolution of Issue 1. Under Issue 2, I concur that Admin.
R. M. 17.30.715(1) incorporates a consideration of the length of time a discharge will
continue, and thus satisfies the requirement of § 75-5-301(5)(c)(iii), MCA, that such
regulatory criteria “generally” consider “length of time.” Opinion, ¶¶ 31, 38. I further agree
with the Court that DEQ has misinterpreted Admin. R. M. 17.30.715(2) by limiting the
application of that provision to instances where the specific criteria in sub-division (1) fail to
account for site-specific conditions or newly acquired information. Sub-division (2) of
Admin. R. M. 17.30.715 states that “Notwithstanding compliance with the criteria of (1), the
department may determine that the change in water quality . . . is degradation based
upon . . . any other information deemed relevant to the department. . . .” This language—the
department “may determine”—clearly grants the department full discretion to undertake
review under sub-division (2) regardless of the outcome under sub-division (1). Thus, DEQ
has made an error of law—the misinterpretation of a regulation.
¶52 I depart from the Court over the order it ultimately enters because, after properly
interpreting the regulation as granting DEQ discretion to act, and thereby correcting the
department’s error of law, the Court then takes upon itself the task of exercising the very
discretion which we have just explained belongs to DEQ, deciding that DEQ must act—it
must engage in nondegradation review under sub-division (2). However, the regulation
specifically provides that DEQ may act, and the Court has thus exercised discretion
belonging to DEQ.
22
¶53 The Court is doing what it says it will not do. Despite acknowledging that a court
should not substitute its judgment for that of an agency, the Court puts on its environmental
hat and does just that—reviews the facts and decides that the appropriate action is for DEQ
to undertake with regard to Outfall 001 is to proceed with nondegradation review. Whether
nondegradation review should be undertaken pursuant to sub-division (2) is a discretionary
decision for the agency to make. This Court can review the exercise of that discretion for
abuse if DEQ’s decision is later challenged on appeal, but we should not be making the
decision in the first instance.
¶54 The Court has exceeded its authority and acted contrary to the cases it cites. In
Weaver, we held the district court abused its discretion by failing to act upon a defendant’s
motion to withdraw his guilty pleas. State v. Weaver, 276 Mont. 505, 917 P.2d 437 (1996).
Rather than ruling on the motion ourselves, we sent the case back to the district court to
undertake its proper duty. Weaver, 276 Mont. at 509, 917 P.2d at 440. The Court cites to
language within Columbia Falls Elementary Sch. Dist. No. 6 v. State, 2005 MT 69, ¶ 44, 326
Mont. 304, ¶ 44, 109 P.3d 257, ¶ 44, about the failure to exercise discretion but, actually, that
decision illustrates the Court’s error. We held in Columbia Falls that the Legislature had
failed to act within its discretion to define “quality education.” Columbia Falls, ¶ 31. Rather
than stepping into the Legislature’s shoes and drafting the definition of “quality” ourselves,
we required the Legislature to define the term, as was its duty. Columbia Falls, ¶ 31.
Similarly, regarding agencies, we have held:
The reviewing court has the duty to determine whether the agency applied the
appropriate law and whether its findings of fact are sufficient to justify the
agency’s rulings. When the court determines that the agency’s findings are
23
insufficient or that the agency applied the wrong law, it may not use the
opportunity to usurp the agency’s role as the trier of fact.
Stewart v. Region II Child & Fam. Servs., 242 Mont. 88, 94, 788 P.2d 913, 917 (1990).
¶55 The briefing in this case explains that nondegradation review is an extensive process.
Requiring that process on our own, without the benefit of a factual record on that question
and without benefit of the agency’s expertise, is a shot in the dark. We should let the agency
exercise its discretion on that issue and act first, in accordance with the corrected
interpretation of the regulation we have provided. Fortunately, the Court bases its holding
requiring the Department to proceed under (2) “on the facts of this case,” ¶ 40, from which I
draw the conclusion that the Court is not requiring the Department to undertake review under
(2) in every case. From now on, apparently, the Department will be able to properly exercise
its discretion in that regard.
¶56 I concur and dissent.
/S/ JIM RICE
Chief Justice Karla M. Gray joining in the concurring and dissenting Opinion of Justice Rice.
/S/ KARLA M. GRAY
24