NM Reg Landfill v. NM Environ Dept

 1   This memorandum opinion was not selected for publication in the New Mexico Reports. Please see
 2   Rule 12-405 NMRA for restrictions on the citation of unpublished memorandum opinions. Please
 3   also note that this electronic memorandum opinion may contain computer-generated errors or other
 4   deviations from the official paper version filed by the Court of Appeals and does not include the
 5   filing date.
 6        IN THE COURT OF APPEALS OF THE STATE OF NEW MEXICO

 7 NORTHEASTERN NEW MEXICO
 8 REGIONAL LANDFILL, L.L.C.,

 9          Plaintiff-Appellant/Cross-Appellee,

10 v.                                                    NO. 28,236 consolidated with 28,229

11 THE NEW MEXICO ENVIRONMENT
12 DEPARTMENT,

13          Defendant-Appellee/Cross-Appellee

14 and

15   SOPHIA MARTINEZ, FELIPE GARCIA,
16   BETTY MEDINA, AND THE CONCERNED
17   CITIZENS OF WAGON MOUND AND
18   MORA COUNTY,

19          Defendants-Appellees/Cross-Appellants

20 APPEAL FROM THE SECRETARY OF THE                                            NEW       MEXICO
21 ENVIRONMENT DEPARTMENT
22 Ron Curry, Secretary of the New Mexico Environment

23   Hinkle, Hensley, Shanor & Martin, LLP
24   Thomas M. Hnasko
25   Gary W. Larson
26   Dulcinea Z. Hanuschak
27   Santa Fe, NM

28 for Appellant/Cross-Appellee
29 Northeastern New Mexico Regional
1 Landfill, L.L.C.




                     2
 1 New Mexico Environment Department
 2 Charles F. Noble
 3 Santa Fe, NM

 4 for Appellee/Cross-Appellee
 5 New Mexico Environment Department

 6   Holland & Hart, LLP
 7   Robert J. Sutphin, Jr.
 8   Larry J. Montaño
 9   Kristina Martinez
10   Santa Fe, NM

11   for Appellees/Cross-Appellants
12   Sophia Martinez, Felipe Garcia,
13   Betty Medina and the Concerned Citizens
14   of Wagon Mound and Mora County

15                            MEMORANDUM OPINION

16 FRY, Judge.

17         Appellant Northeastern New Mexico Regional Landfill, L.L.C. (NENMRL) and

18 Cross-Appellant Concerned Citizens of Wagon Mound and Mora County (Concerned

19 Citizens) appeal from an administrative order of the Secretary of the New Mexico

20 Environment Department (NMED) renewing NENMRL’s existing municipal solid

21 waste permit for an additional ten-year period and also granting in part certain permit

22 modifications requested by NENMRL.             This consolidated case requires us to

23 specifically address the Secretary’s decision with respect to two of NENMRL’s

24 requested permit modifications. In the main appeal, NENMRL challenges the


                                              3
 1 Secretary’s denial of a requested permit modification to handle and dispose of certain

 2 nonhazardous special wastes at the landfill. In the cross-appeal, Concerned Citizens

 3 contests the Secretary’s decision to grant a permit modification to NENMRL for the

 4 acceptance of municipal solid waste via railroad transport. We affirm.

 5 BACKGROUND

 6        These consolidated appeals concern an existing solid waste facility that is

 7 privately owned by NENMRL and located in Mora County, approximately six miles

 8 north of Wagon Mound, New Mexico. NMED first issued a permit to NENMRL for

 9 the acceptance of municipal solid waste at the facility in 1997. Since operations

10 began, the facility has been operated by Herzog Environmental, Inc. (Herzog), a third

11 party not directly involved in this case.

12        At issue in this case is NENMRL’s application for permit renewal and

13 modification that was submitted on October 15, 2005, to the Solid Waste Bureau of

14 NMED pursuant to the Solid Waste Act (the Act), NMSA 1978, §§ 74-9-1 to -43

15 (1990, as amended through 2001), and its implementing regulations, 20.9.1 NMAC

16 (recompiled 11/27/01). In the application, NENMRL requested that its existing permit

17 for the acceptance and disposal of municipal solid waste be renewed for an additional

18 ten-year period. NENMRL also sought several permit modifications in its application,

19 as follows: (1) authorization to handle and dispose of certain nonhazardous special


                                               4
 1 wastes at its facility, (2) authorization to accept deliveries of waste via rail transport,

 2 (3) expansion of the boundary of the landfill for purposes of developing a rail transfer

 3 area, (4) modification of the slope of the final cover of waste disposal areas, and (5)

 4 authorization to accept hand loads of solid waste from the public. Significantly, this

 5 was NENMRL’s third application for a permit modification to accept nonhazardous

 6 special wastes at its facility. The previous two applications had been denied and were

 7 the subject of previous appeals to this Court.

 8        The 2005 application was deemed administratively and technically complete

 9 by the Solid Waste Bureau (hereinafter “Solid Waste Bureau” or “Bureau”) on May

10 11, 2007. Subsequently, at the direction of the Secretary of NMED, a five-day public

11 hearing was conducted before a hearing officer on August 20-24, 2007, in Wagon

12 Mound, New Mexico. At the hearing, the hearing officer heard testimony from

13 representatives of NENMRL, the Solid Waste Bureau, Concerned Citizens, and

14 members of the public. Concerned Citizens, an organization composed largely of

15 community residents, was an intervening party that opposed the granting of

16 NENMRL’s permit application.

17        At the conclusion of the hearing, the hearing officer allowed all parties to

18 submit written closing arguments as well as proposed findings of fact and conclusions

19 of law. Subsequently, on the basis of the hearing and the parties’ written arguments,


                                                5
 1 the hearing officer submitted a report to the Secretary for his consideration, in which

 2 she summarized the evidence and testimony elicited at the hearing and offered

 3 proposed findings of fact and conclusions of law regarding NENMRL’s permit

 4 application. The hearing officer recommended that NENMRL’s existing municipal

 5 solid waste permit be renewed for an additional ten-year period. With regard to

 6 NENMRL’s proposed permit modifications, the hearing officer recommended that the

 7 Secretary grant all requested permit modifications, with the exception of the

 8 modification for the acceptance of nonhazardous special wastes. The hearing officer

 9 also recommended a number of permit conditions, including several that were directed

10 to the modification that authorized the acceptance of waste via rail transport.

11        On December 17, 2007, the Secretary issued a final order, in which he adopted

12 the hearing officer’s report in its entirety. In accordance with the hearing officer’s

13 report, the Secretary renewed NENMRL’s existing permit for an additional ten-year

14 period and granted all of its requested permit modifications, with the sole exception

15 of the modification for the handling and disposal of nonhazardous special wastes.

16 Additionally, the Secretary adopted all permit conditions recommended by the hearing

17 officer. These appeals followed.

18        In the main appeal, NENMRL challenges the Secretary’s denial of the special

19 waste permit modification, with NMED and Concerned Citizens arguing in response


                                              6
 1 that the Secretary did not err in denying this particular modification. In the cross-

 2 appeal, Concerned Citizens challenges the Secretary’s decision to grant the permit

 3 modification allowing NENMRL to accept wastes via rail transport, with NENMRL

 4 and NMED arguing in response that the Secretary did not err in granting this

 5 modification. The appeals were consolidated for our review and we address each

 6 appeal in turn below.

 7 DISCUSSION

 8 A.     STANDARD OF REVIEW

 9        Before we address the merits of the parties’ arguments, we provide the standard

10 of review and address the applicable regulatory framework for our review. This Court

11 has jurisdiction over the appeal of an administrative action taken pursuant to the Act

12 under Section 74-9-30(A). We may set aside the Secretary’s final order regarding

13 permit issuance only if the decision is “(1) arbitrary, capricious or an abuse of

14 discretion; (2) not supported by substantial evidence in the record; or (3) otherwise not

15 in accordance with law.” Section 74-9-30(B). In reviewing an administrative decision

16 for arbitrary and capricious conduct, “we review the whole record to ascertain whether

17 there has been unreasoned action without proper consideration or disregard of the

18 facts and circumstances.” Paule v. Santa Fe Cnty Bd. of Cnty. Comm’rs, 2005-NMSC-

19 021, ¶ 30, 138 N.M. 82, 117 P.3d 240 (internal quotation marks and citation omitted);


                                               7
 1 see Colonias Dev. Council v. Rhino Envtl. Servs. Inc., 2005-NMSC-024, ¶ 13, 138

 2 N.M. 133, 117 P.3d 939 (stating that an administrative decision is arbitrary and

 3 capricious if it is “unreasonable or without a rational basis”). In addition, when we

 4 review an administrative decision for substantial evidence, we “apply whole record

 5 review, meaning that we examine all of the evidence in the record, not just the

 6 evidence that supports the decision.” Pickett Ranch, LLC v. Curry, 2006-NMCA-082,

 7 ¶ 5, 140 N.M. 49, 139 P.3d 209 (internal quotation marks omitted). “The reviewing

 8 court needs to find evidence that is credible in light of the whole record and that is

 9 sufficient for a reasonable mind to accept as adequate to support the conclusion

10 reached by the agency.” Snyder Ranches, Inc. v. Oil Conservation Comm’n, 110 N.M.

11 637, 639, 798 P.2d 587, 589 (1990) (internal quotation marks and citation omitted).

12 To the extent that the parties raise questions of statutory interpretation, we apply de

13 novo review. Pickett Ranch, 2006-NMCA-082, ¶ 5. However, we will give deference

14 to an agency’s interpretation of its own ambiguous regulations. Id.

15        As for the regulatory framework, the parties have stipulated that the applicable

16 regulations are those found in the 2001 version of the Solid Waste Management

17 Regulations, which were provided to this Court by the parties. 20.9.1 NMAC. The

18 parties have also stipulated that the 2001 version is a recompilation of the 1995

19 version of the Solid Waste Management Regulations. 20.9.1 NMAC (10/27/95)


                                              8
 1 Although the parties agree that the 2001 version of the regulations was applicable at

 2 the time of the administrative proceedings below, we note that the administrative

 3 record in this case contains citations to both the 1995 and 2001 regulations. However,

 4 we clarify that our analysis is based on the 2001 version, and we have considered the

 5 parties’ arguments in the context of this version only. Our analysis also includes

 6 references to the 2001 version of NMED’s Permitting Procedures. See 20.1.4 NMAC

 7 (recompiled 11/27/01), available at the New Mexico Administrative Code,

 8 http://www.nmcpr.state.nm.us/nmac/parts/title20/20.001.0004.htm.

 9 B.     MAIN APPEAL

10        In the main appeal, we address the Secretary’s decision to deny NENMRL a

11 permit modification to handle and dispose of nonhazardous special wastes at its

12 facility. NENMRL challenges a number of the Secretary’s findings and conclusions

13 concerning the denial of this particular permit modification, asserting that the

14 Secretary either abused his discretion, acted arbitrarily and capriciously, or made

15 findings that were not supported by substantial evidence. We address each of the six

16 contested findings and/or conclusions in turn below.




                                             9
 1 1.     The Secretary’s Conclusion That NENMRL Failed to Provide Specific
 2        Estimates of the Anticipated Amount and Frequency of Disposal of Special
 3        Wastes

 4        NENMRL argues that the Secretary erroneously concluded that its permit

 5 application “failed to provide [required] specific estimates of the anticipated amount

 6 and frequency of disposal” for the special wastes that it proposed to accept at its

 7 facility through the requested special waste permit modification. The Secretary

 8 specifically determined that this was a violation of 20.9.1.200(F)(2) NMAC

 9 (recompiled 11/27/01), which requires applicants seeking to accept special wastes at

10 a landfill facility to include information in their applications regarding “the anticipated

11 amount and frequency of disposal of the wastes.”

12        In making this determination, the Secretary relied in part on findings he had

13 made in support of the 2004 denial of NENMRL’s second application for a special

14 waste permit. In that previous denial, the Secretary specifically found that NENMRL

15 had failed to give any estimates despite the fact that it had historical data upon which

16 to base such estimates. Historical data was available because NENMRL had been

17 authorized to and actually accepted special wastes at its facility from August 2000,

18 when the Secretary approved its first application for a special waste permit, until

19 November 2002, when this Court overturned the granting of that permit in Martinez

20 v. Maggiore, 2003-NMCA-043, 133 N.M. 472, 64 P.3d 499. Essentially, the


                                               10
 1 Secretary’s 2004 order determined that NENMRL’s failure to give special waste

 2 estimates based on actual figures from the above time period indicated a failure to

 3 comply with the regulatory requirements of 20.9.1.200(F)(2) NMAC. Turning to the

 4 October 12, 2005, permit application at issue in this case, the Secretary entered a

 5 finding that NENMRL had again failed to correct the application deficiency noted in

 6 his 2004 final order. In other words, the Secretary found that NENMRL had once

 7 again failed to provide estimates of the anticipated amounts and frequency of disposal

 8 of nonhazardous special wastes.

 9        On appeal, NENMRL challenges the Secretary’s finding and argues that its

10 application actually provided “detailed special waste estimates and delivery

11 frequencies, based on data from the [time] period when it operated with a special

12 waste permit.” NENMRL contends that it used the historical data as a baseline to

13 quantify the “anticipated amounts of the special wastes it reasonably expected to

14 receive over the ten-year life of a new modified permit.” NENMRL further points out

15 that representatives from the Solid Waste Bureau of NMED agreed with its approach.

16 Accordingly, NENMRL argues that the Secretary’s disregard for the “unrebutted

17 evidence” it submitted regarding special waste estimates was arbitrary, capricious, and

18 an abuse of discretion.




                                             11
 1        In determining whether the Secretary abused his discretion or acted arbitrarily

 2 and capriciously in concluding that the special waste estimates provided by NENMRL

 3 failed to comply with the requirements of 20.9.1.200(F)(2) NMAC, we “review the

 4 record to determine whether there has been unreasoned action without proper

 5 consideration in disregard for the facts and circumstances.” Perkins v. Dep’t of

 6 Human Servs., 106 N.M. 651, 655, 748 P.2d 24, 28 (Ct. App. 1987). “[A]n agency’s

 7 action is arbitrary and capricious if it provides no rational connection between the

 8 facts found and the choices made, or entirely omits consideration of relevant factors

 9 or important aspects of the problem at hand.” Atlixco Coalition v. Maggiore, 1998-

10 NMCA-134, ¶ 24, 125 N.M. 786, 965 P.2d 370. Likewise, “[w]here there is room for

11 two opinions, the [agency’s] action is not arbitrary or capricious if exercised honestly

12 and upon due consideration, even though another conclusion might have been

13 reached.” Perkins, 106 N.M. at 655, 748 P.2d at 28. Finally, an agency abuses its

14 discretion if it fails to proceed in the manner required by law, or if the agency’s final

15 order is not supported by the findings, or if the findings were not supported by the

16 evidence put forth before the agency. See id.

17        We begin our analysis by summarizing the data submitted by NENMRL

18 regarding the anticipated amounts and frequency of special waste that it proposed to

19 accept at its facility, as provided in its application or elicited through testimony from


                                              12
 1 NENMRL representatives at the public hearing. The primary source for NENMRL’s

 2 estimates was a data table that NENMRL included in its application and subsequently

 3 presented as an exhibit during the public hearing. The data table essentially provided

 4 an estimate in tons per year for six different types of special wastes for which

 5 NENMRL was requesting a special waste permit modification: petroleum

 6 contaminated waste, WWTP sludge, asbestos waste, industrial waste, nonhazardous

 7 chemical/commercial product, and killing plant offal. As a baseline for initial tons per

 8 year for each of the six special wastes, NENMRL used historical figures from the time

 9 period between 2000-2002 in which it had actually accepted special wastes. From

10 there, NENMRL calculated and applied a fifteen percent annual incremental increase

11 for each type of special waste listed in the table. The table projected anticipated

12 volumes through 2017, which corresponded to the ten-year permit renewal time period

13 that NENMRL had requested in its application. In addition to the six types of special

14 wastes included in the data table, NENMRL provided an anticipated volume for ash-

15 contaminated wastes. The anticipated volume for ash was calculated by taking the

16 maximum capacity for the ash pit at the facility and dividing that number by the ten-

17 year permit renewal term.

18        With regard to anticipated frequencies, NENMRL stated in its application that

19 it “has the capacity to handle up to approximately 5,000 tons per day (tpd) of both


                                              13
 1 municipal solid waste and special wastes for a short duration” and that “the average

 2 daily tonnage over a 365 day period is not anticipated to exceed 1,000 tpd of

 3 municipal solid waste and special waste.” In addition, at the public hearing,

 4 NENMRL’s general manager explained that “a fair assessment” of anticipated

 5 frequencies “would be to take the actual tonnage [listed in the table] divided by 52

 6 [weeks], and then that would give . . . a weekly average of the frequency of . . . the

 7 volume coming in.”

 8        NENMRL contends that the above estimates for anticipated volumes and

 9 frequency were “based on actual experience and projections within the solid waste

10 industry” and that the fifteen percent per year incremental increase was a

11 “commercially reasonable increment[]” to apply.         Testimony from NENMRL

12 representatives at the public hearing used similar language to describe the estimates.

13 Specifically, NENMRL’s general manager testified that the data table represented an

14 accurate and reasonable estimate, but that the receipt of special wastes could vary

15 because it is primarily an event-driven circumstance (e.g., fires); likewise, another

16 NENMRL technical witness testified that the fifteen percent increase was reasonable

17 based on his past experience.

18        The Solid Waste Bureau’s position at the hearing did not differ significantly

19 from NENMRL’s position. The Bureau took the position that NENMRL’s special


                                             14
 1 waste estimates “were adequate to meet the regulatory requirements” of

 2 20.9.1.200(F)(2) NMAC and were “reasonable and represent[ed] the best efforts of

 3 [NENMRL] to foresee future receipt of special wastes.” However, the Bureau’s

 4 representative testified that its recommendations were subject to review by the

 5 Secretary and that the Secretary would make the final decision regarding the requested

 6 permit and any modifications based on the application and information presented at

 7 the hearing.

 8        In contrast, Concerned Citizens argued below that NENMRL’s estimates were

 9 not in compliance with regulatory requirements. One of Concerned Citizens’

10 technical witnesses, Paul Robinson, testified that NENMRL had given no basis for the

11 anticipated volumes aside from a “straight arithmetic projection” of fifteen percent,

12 which was not based on “any special waste generation or handling need or market of

13 any kind.” He opined that NENMRL had failed to submit evidence that the fifteen

14 percent figure reflected a “likely rate of growth” or that it reflected any actual

15 knowledge regarding waste streams and the solid waste market in New Mexico. He

16 further testified that NENMRL’s calculations had not taken into account actual

17 inquiries from potential customers as a means of more specifically calculating

18 volumes based on actual market need. Robinson also expressed concerns with the

19 anticipated frequency numbers provided by NENMRL, testifying that these numbers


                                             15
 1 were not realistic in light of NENMRL’s historical frequency of 130 to 150 tons per

 2 day and the presence of other landfills in Northern New Mexico. Robinson concluded

 3 that the application deficiency noted by the Secretary in his 2004 final order regarding

 4 special waste estimates had not been rectified in NENMRL’s current application.

 5        Thus, the Secretary was presented at the hearing with two distinct

 6 opinions—from NENMRL and Concerned Citizens—regarding the adequacy of the

 7 anticipated volumes and frequency of disposal of special wastes provided by

 8 NENMRL in its application.         Accordingly, whether the amounts provided by

 9 NENMRL complied with 20.9.1.200(F)(2) NMAC was ultimately a question of fact

10 for the Secretary, one that we think necessarily required agency expertise to resolve.

11 On issues such as this “where specialized technical or scientific knowledge is

12 involved, we will give great deference to an agency’s factual findings.” Pickett

13 Ranch, 2006-NMCA-082, ¶ 49; see Regents of the Univ. of N.M. v. N.M. Fed’n of

14 Teachers, 1998-NMSC-020, ¶ 17, 125 N.M. 401, 962 P.2d 1236 (stating that “[i]f the

15 court is addressing a question of fact, the court will accord greater deference to the

16 agency’s determination, especially if the factual issues concern matters in which the

17 agency has specialized expertise” (internal quotation marks and citation omitted)).

18        We conclude that the Secretary did not act arbitrarily or capriciously in

19 determining that the special waste estimates provided by NENMRL failed to comply


                                              16
 1 with regulatory requirements. In his final order, the Secretary concluded that

 2 NENMRL’s “estimates are vague and appear to be based on a straight-line projection

 3 of special waste amounts with no description of frequency of special waste disposal.”

 4 In light of the evidence before the Secretary, this finding was supported by substantial

 5 evidence based on the arguments submitted by Concerned Citizens to the hearing

 6 officer. Robinson’s testimony alone provided substantial evidence on which the

 7 hearing officer and the Secretary could have permissibly concluded that the estimates

 8 provided by NENMRL were not specific enough to meet the regulatory requirements.

 9 See Albuquerque Bernalillo Cnty. Water Util. Auth. v. NMPRC, 2010-NMSC-013, ¶

10 18, 148 N.M. 21, 229 P.3d 494 (stating that “[s]ubstantial evidence on the record as

11 a whole is evidence demonstrating the reasonableness of an agency’s decision, and

12 [courts] neither reweigh the evidence nor replace the fact finder’s conclusions with

13 [the court’s] own” (internal quotation marks and citation omitted)). Given the

14 Secretary’s expertise in this area and the substantial evidence present in the record, we

15 defer to the Secretary’s factual findings on this issue.

16        Moreover, NENMRL fails to give record support for its assertion that the

17 fifteen percent incremental increase it used was “commercially reasonable” and

18 “based on actual experience and projections within the solid waste industry.” Our

19 review of the record shows that NENMRL’s application did not provide any reason


                                              17
 1 at all for its use of a fifteen percent annual increase in its calculations. We cannot say

 2 that the Secretary’s decision was arbitrary and capricious simply because he reached

 3 a different conclusion than the one provided by NENMRL. See N.M. Mining Ass’n

 4 v. Water Quality Control Comm’n, 2007-NMCA-084, ¶ 29, 142 N.M. 200, 164 P.3d

 5 81 (“Even if a different conclusion might have been reached from the facts, the choice

 6 made [by an administrative agency] is not arbitrary or capricious if exercised honestly

 7 and upon due consideration.” (alteration omitted) (internal quotation marks and

 8 citation omitted)).

 9 2.     The Secretary’s Finding That NENMRL Failed to Provide Adequate
10        Individual Notice to Interested Parties

11        NENMRL next challenges the Secretary’s finding that it failed to provide

12 adequate individual notice to adjacent landowners and other interested parties

13 regarding the “quantity, rate, type , as well as the origin of the [special] waste” it was

14 proposing to accept at the landfill, in violation of agency regulations in effect at the

15 time. As we understand NENMRL’s argument, it contends that in finding that

16 regulatory notice requirements were not met, the Secretary also made an “unstated

17 finding” that the interested parties’ procedural due process rights were violated.

18 Relying on this unstated finding, NENMRL appears to argue that even if there was a

19 purported deficiency in the individual notice letters, the procedural due process rights




                                               18
 1 of the interested parties were not violated and, therefore, the Secretary erroneously

 2 denied the special waste permit on the basis of inadequate notice.

 3        NENMRL’s argument is premised on a contention that this Court differentiated

 4 between statutory notice requirements and procedural due process in Martinez, 2003-

 5 NMCA-043, ¶ 13. On the basis of this asserted difference, NENMRL argues only that

 6 the interested parties’ due process rights were protected without challenging the

 7 Secretary’s express finding that the individual notice letters failed to meet notice

 8 requirements.

 9        We are unpersuaded by NENMRL’s argument for two reasons. First, we have

10 found no evidence in the record, nor has NENMRL pointed to any, showing that the

11 Secretary or the hearing officer made any findings regarding possible due process

12 violations on the basis of the notice provided by NENMRL during the permitting

13 process. Rather, the hearing officer’s report concluded only that the notice failed to

14 meet regulatory requirements without referring to any possible due process issues.

15 Accordingly, we are hesitant to attribute an implicit finding to the Secretary regarding

16 due process in the absence of an express finding. Cf. Atlixco, 1998-NMCA-134, ¶¶ 20,

17 21 (stating that “the reviewing court may not supply a reasoned basis for the agency’s

18 action that the agency itself has not given” and that “the [s]ecretary’s decision stands




                                              19
 1 or falls on its express findings and reasoning” (alteration omitted) (internal quotation

 2 marks and citation omitted)).

 3        Second, we disagree with NENMRL’s characterization of Martinez as

 4 establishing that a due process analysis is required in cases where the sufficiency of

 5 notice is at issue. In Martinez, we reversed the grant of a special waste permit to

 6 NENMRL for the same facility at issue here on the basis of a failure to substantially

 7 comply with statutory notice requirements. 2003-NMCA-043, ¶ 13. We determined

 8 that NENMRL’s failure to publish notice of its permit application in two separate

 9 locations within local newspapers was a violation of statutory notice requirements

10 under the Act. Id. ¶¶ 7-9. We then relied on Nesbit v. City of Albuquerque, 91 N.M.

11 455, 575 P.2d 1340 (1977), to hold that NENMRL’s failure to substantially comply

12 with statutory notice requirements rendered all subsequent administrative proceedings

13 invalid, thereby requiring reversal of the Secretary’s decision in those proceedings to

14 grant a special waste permit to the facility. Martinez, 2003-NMCA-043, ¶ 13. We

15 remanded the case for new proceedings to take place after proper notice was provided

16 regarding the requested special waste modification. Id.

17        Contrary to NENMRL’s position, Martinez never explicitly discussed due

18 process, and the opinion did not address the interplay between statutory notice

19 violations and due process. In fact, this Court declined to address a standing argument


                                              20
 1 raised in Martinez because it “confuse[d the a]ppellants’ due process right to

 2 individual notice with . . . [the] statutory requirement of notice to the general public

 3 [of a waste permit application].” 2003-NMCA-043, ¶ 15. We further stated that

 4 NENMRL’s failure to meet statutory notice requirements in that case could not be

 5 “rendered harmless as a matter of law by the fact that [the a]ppellants and a number

 6 of other residents of the area attended the hearing and expressed their lay concerns.”

 7 Id. ¶ 17. Thus, to the extent that NENMRL makes due process arguments on appeal

 8 in this case—that the interested parties had actual knowledge of the hearing and that

 9 individual notice letters were not misleading or prejudicial—we are not persuaded.

10 These actions, even if they were substantiated by the record, would not render

11 harmless the failure of NENMRL to meet regulatory notice requirements. This is

12 consistent with the underlying policy rationale behind Martinez—that the failure to

13 comply with statutory and/or regulatory notice requirements is a serious deficiency

14 in the permitting process requiring stark consequences because it effectively precludes

15 the right of interested parties to meaningfully participate in the hearing process and

16 to insure that their concerns regarding proposed permit modifications are heard. Id.

17 ¶¶ 15, 18-19; see Colonias, 2005-NMSC-024, ¶¶ 21-22 (discussing Martinez and the

18 legislative policy favoring the public’s right to participate meaningfully in a landfill

19 permitting process).


                                              21
 1        Martinez does not stand for the principle that meeting the interested parties’ due

 2 process rights under the circumstances presented in this case would act as a cure for

 3 a statutory/regulatory notice violation. As an aside, we recognize that our reliance on

 4 Nesbit in Martinez could have been construed as a signal to NENMRL in this case that

 5 procedural due process is a consideration in cases where notice concerns are raised in

 6 administrative proceedings. See Nesbit, 91 N.M. at 459, 575 P.2d at 1344 (stating that

 7 the failure to comply with statutory notice procedures in zoning ordinance

 8 proceedings was a violation of “due process of law . . . and [that] no subsequent act

 9 could correct the defect”); see also Eldorado at Santa Fe, Inc. v. Cook, 113 N.M. 33,

10 36, 822 P.2d 672, 675 (Ct. App. 1991) (relying on Nesbit to hold that the failure to

11 give proper statutory notice of an administrative permitting proceeding was a due

12 process violation), abrogated on other grounds by Goodloe v. Bookout,

13 1999-NMCA-061, 127 N.M. 327, 980 P.2d 652. However, these cases only serve to

14 establish the importance of meeting notice requirements under a statute or its

15 implementing regulations and the consequence for failing to do so. It stands to reason

16 that if this Court can reverse the grant of a special waste permit on the basis of

17 statutory notice violations, as we did in Martinez, there is no error on the part of the

18 Secretary in denying a special waste permit in this case on the same basis, irrespective

19 of any of the flexible procedural due process considerations NENMRL has asserted


                                              22
 1 in this case. See also II Richard J. Pierce, Jr., Administrative Law Treatise § 9.1, at

 2 736 (5th ed. 2010) (“Once an agency adopts a set of procedures by rule, the agency

 3 must comply with its own procedural rules even if the procedures adopted by the

 4 agency exceed those independently required by due process.”).

 5        Accordingly, we decline to review the Secretary’s order for possible error as to

 6 an “unstated” procedural due process violation, and we remain unconvinced that any

 7 determination on appeal by this Court that procedural due process was not violated

 8 would overcome the Secretary’s determination that NENMRL failed to meet

 9 regulatory notice requirements. Because NENMRL has not argued that the Secretary

10 erred in determining that the individual notice letters failed to comply with regulatory

11 notice requirements regarding the special waste permit modification, we do not disturb

12 that finding on appeal.

13 3.     The Secretary’s Findings Regarding NENMRL’s History of
14        Noncompliance with Existing Permit Conditions and Applicable
15        Regulations

16        NENMRL also challenges the Secretary’s denial of the special waste permit

17 modification on the basis of the following conclusions regarding its compliance

18 history: that (1) it “ha[d] a history of failing to submit reports and failing to comply

19 with conditions previously imposed by the [NMED] Solid Waste Bureau,” as required

20 by 20.9.1.200(L)(16) NMAC; (2) it had a “history of violations issued by the [NMED]


                                              23
 1 Air Quality Bureau”; and (3) it failed to include in its permit application a full

 2 discussion of its history of violations. NENMRL argues that in reaching these

 3 conclusions, the Secretary also made an unstated conclusion that NENMRL’s

 4 compliance history indicated a willful disregard for New Mexico’s environmental

 5 laws, in direct violation of Section 74-9-24(B)(5). NENMRL claims that it has not

 6 exhibited a willful disregard for environmental laws because its only compliance-

 7 related issues have been “de minimis inspection infractions” and the filing of reports

 8 to a mis-identified individual at the Air Quality Bureau.

 9        Before reaching the merits of NENMRL’s arguments, we first address the

10 parties’ dispute regarding the applicable standard governing this issue. NENMRL

11 argues that we should apply the statutory-based willful disregard standard due to the

12 Secretary’s “presumed” yet “unstated” conclusion that NENMRL has exhibited a

13 willful disregard for state environmental laws. However, NMED and Concerned

14 Citizens disagree that the Secretary applied a willful disregard standard below;

15 instead, they argue that we need only consider the solid waste regulations and the

16 discretionary grounds for denying a permit included in the regulations. Specifically,

17 they refer us to 20.9.1.200(L)(16) NMAC, which provides a number of circumstances

18 under which the Secretary has “cause” to deny a permit application. In relevant part,

19 NMED points to two circumstances that were cited by the Secretary in one of the


                                             24
 1 contested conclusions above: “(a) noncompliance by the permittee with any condition

 2 of the permit” and “(d) the applicant’s failure to demonstrate a knowledge and ability

 3 to operate a facility in accordance with [the regulations] or a history of

 4 non[]compliance with environmental regulations or statutes at other facilities.”

 5 20.9.1.200(L)(16)(a), (d) NMAC.

 6        We conclude that we need only look to the regulatory framework in our

 7 analysis of the parties’ arguments concerning the Secretary’s compliance-related

 8 conclusions. We do so primarily because NENMRL has failed to point to any express

 9 finding of fact or conclusion of law in the Secretary’s final order explicitly stating that

10 NENMRL has exhibited a willful disregard for environmental laws. To the contrary,

11 NENMRL itself acknowledged in its briefing that it considered this an “unstated” and

12 “presumed” conclusion only. We decline to attribute a conclusion to the Secretary

13 that was not expressly raised in the final order. See Atlixco, 1998-NMCA-134, ¶ 20

14 (“When the Legislature specifically directs the [s]ecretary to state the reasons for an

15 administrative action, the reviewing court may not supply a reasoned basis for the

16 agency’s action that the agency itself has not given.” (internal quotation marks and

17 citation omitted)). Although NENMRL claims in its reply brief that the final order

18 refers to the “willful disregard” standard as a standard applicable to the permitting

19 proceedings, this reference is made in a section describing the Secretary’s general


                                               25
 1 powers under the Act and does not appear in any specific findings of fact or

 2 conclusions of law reached by the Secretary as to NENMRL’s compliance history.

 3 The Secretary’s relevant findings and conclusions concerning compliance rely upon

 4 and cite to the regulations only. Accordingly, because there is no indication that the

 5 Secretary expressly considered or applied a “willful disregard” standard, we review

 6 the conclusions at issue here under the discretionary grounds set forth in the solid

 7 waste regulations that give the Secretary cause to deny a permit application. See

 8 20.9.1.200(L)(16) NMAC.

 9        We have previously set out the following standard for reviewing the Secretary’s

10 denial of a permit application based on the grounds provided in 20.9.1.200(L)(16)

11 NMAC.       We decide “whether the Secretary abused his discretion or acted

12 unreasonably” in concluding that a permit applicant’s past compliance problems were

13 “severe enough to warrant a discretionary denial of the new permit.” Pickett Ranch,

14 2006-NMCA-082, ¶ 36. In other words, because “the Secretary is in the best position

15 to determine what constitutes . . . a history of non[]compliance sufficient to warrant

16 the discretionary denial of a permit,” we will affirm the Secretary’s decision as long

17 as it is supported by substantial evidence and is not unreasonable or an abuse of

18 discretion. Id. ¶ 37 (internal quotation marks omitted). We do not reweigh the facts

19 in evaluating the Secretary’s exercise of his discretion. Id. In addition, because the


                                             26
 1 “Secretary is . . . in the best position to consider more global policy concerns that

 2 might weigh against or in favor of granting a permit,” we will consider any policy

 3 considerations taken into account by the Secretary in our review. Id. ¶ 44.

 4 a.     Air Quality Bureau Notice of Violation

 5        With this framework in mind, we first address NENMRL’s arguments directed

 6 to the Secretary’s conclusion that NENMRL had a history of violations issued by the

 7 NMED Air Quality Bureau. This conclusion was based on the Secretary’s finding of

 8 fact that on August 12, 2004, NENMRL received a notice of violation (NOV) from

 9 the Air Quality Bureau due to its failure to submit “monitoring activities [reports,] . . .

10 annual emission reports[,] . . . and compliance certification reports” within the

11 permitted time frames set by statute. The Secretary also entered findings that the

12 NOV was settled with a monetary penalty of $17,280 and that NENMRL had failed

13 to include any information pertaining to this settlement in its permit application.

14 NENMRL argues that the reports were actually timely filed but incorrectly submitted

15 to the wrong administrative contact at the Air Quality Bureau. It contends that the Air

16 Quality Bureau verified that this was the case and, as a result, it had not required any

17 corrective actions on the part of NENMRL.

18        We are unpersuaded by NENMRL’s position because several aspects of the

19 administrative record support the Secretary’s conclusion that an NOV was issued due


                                               27
 1 to NENMRL’s failure to timely file reports with the Air Quality Bureau. First,

 2 NENMRL admitted in its permit application that the reports were filed late: “[the

 3 NOV was] in regards to late reporting of monitoring activities (due in April and

 4 October each year), Annual NMDC emission reports (due in October), and

 5 Compliance Certification reports (due in October). These reports were submitted;

 6 however, not by the due dates.” (Emphasis added.) Second, the NOV letter issued by

 7 the Air Quality Bureau to NENMRL also confirmed the late submission of the reports;

 8 significantly, the letter stated that eight different reports from calendar years 2002 and

 9 2003 had been submitted anywhere from 113 to 309 days late to the Air Quality

10 Bureau.     Third, the Solid Waste Bureau chief testified that she spoke to a

11 representative from the Air Quality Bureau during the course of her review of

12 NENMRL’s application and that the representative had confirmed the late submission

13 of reports as well as the subsequent case settlement. Thus, based on the foregoing, it

14 appears that substantial evidence existed to support the Secretary’s conclusion that

15 NENMRL had a history of violations with the Air Quality Bureau.

16        To the extent that NENMRL argues that the Air Quality Bureau verified that

17 the reports were timely submitted but sent to the wrong individual at the Air Quality

18 Bureau, we are unpersuaded. As support for this argument, NENMRL relies on

19 testimony elicited at the public hearing from the landfill’s general manager. While


                                               28
 1 discussing the NOV, NENMRL’s general manager testified that the landfill had

 2 “misfiled some reports over the previous couple years” and that the reports had been

 3 “submitted to someone within the Department instead of the director of the [Air

 4 Quality] Bureau[,] as [required by] the [landfill’s] permit.” However, aside from this

 5 testimony, there was no evidence in the record from the Air Quality Bureau itself

 6 confirming that the reports were sent to the wrong individual. The NOV letter, which

 7 was the only purported document in the administrative record from the Air Quality

 8 Bureau itself, made no mention of the reports being submitted to the wrong individual.

 9 Thus, we conclude that it was not unreasonable or an abuse of discretion for the

10 Secretary to disregard the testimony from NENMRL’s general manager in light of the

11 other evidence previously mentioned supporting the history of reporting violations.

12 Substantial evidence existed in the record upon which the Secretary could have based

13 his conclusion that NENMRL has a history of violations from the Air Quality Bureau.

14 b.     History of Noncompliance with Existing Permit Conditions and the Failure
15        to Submit Reports to the Solid Waste Bureau

16        Next, NENMRL argues that the Secretary erroneously concluded that the

17 landfill had a history of noncompliance with existing permit conditions and a history

18 of failing to submit reports to the Solid Waste Bureau. These conclusions were based

19 on the Secretary’s finding that, although NENMRL had not been issued any

20 administrative compliance orders or penalties related to compliance matters, the Solid

                                             29
 1 Waste Bureau had issued two letters of inspection to the landfill for failure to comply

 2 with regulations and/or existing permit conditions. The first inspection letter was

 3 issued due to the failure to control run-off water on site, and the second letter related

 4 to NENMRL’s failure to provide its vadose zone detection monitoring records to the

 5 Solid Waste Bureau. The Secretary also entered a finding that once the vadose

 6 monitoring records were provided, the Solid Waste Bureau discovered that NENMRL

 7 had not undertaken water level measurements for over three years. On appeal,

 8 NENMRL contends that the inspection letters were simply “de minimis infractions”

 9 or “trifles” which NENMRL promptly corrected “to the satisfaction of the [Solid

10 Waste] Bureau.”

11        We conclude that the contested findings above are supported by substantial

12 evidence. NENMRL included in its application eleven inspection reports issued by

13 the Solid Waste Bureau, ranging from calendar years 1998 to 2004. Three of these

14 reports raised regulatory violations such as the presence of litter and ponding of water.

15 The application also included the first letter of inspection concerning run-off water

16 that was relied upon by the Secretary in the contested findings of fact above. Although

17 NENMRL argues that it responded to this inspection letter “to the satisfaction of the

18 [Solid Waste] Bureau,” our review of the application and hearing testimony fails to

19 substantiate this contention. Aside from the letter sent by NENMRL to the Solid


                                              30
 1 Waste Bureau asserting that the inspection letter had been issued in error, we did not

 2 find any response from the Solid Waste Bureau acknowledging any error. In addition,

 3 Concerned Citizens provided, as an exhibit at the hearing, a number of additional

 4 inspection reports that listed a variety of other issues, as follows: litter in leachate

 5 collection ponds, water run-on and ponding issues, failure to control run-on and run-

 6 off water on site, and a failure to provide records of vadose zone detection monitoring

 7 upon request. The last two issues resulted in the letters of inspection that the

 8 Secretary referenced in his findings of fact above. Finally, there was testimony at the

 9 hearing from the Solid Waste Bureau chief and employees, which confirmed the

10 letters of inspection. Thus, based on the foregoing, we conclude that there was

11 substantial evidence supporting the Secretary’s conclusion that NENMRL had a

12 history of noncompliance with regulations and conditions imposed in its existing

13 permit.

14        NENMRL essentially urges this Court to reweigh the facts relied on by the

15 Secretary to reach his conclusions regarding the landfill’s compliance history and

16 determine instead that the violations addressed above were only trifles with no

17 environmental consequences. However, as we have previously stated, “in the absence

18 of a showing of unreasonableness, we will defer to the [Secretary’s] interpretation of

19 what constitutes a history of non[]compliance severe enough to warrant the


                                              31
 1 discretionary denial of a permit.” Pickett Ranch, 2006-NMCA-082, ¶ 43 (internal

 2 quotation marks omitted). NENMRL has not demonstrated that the Secretary abused

 3 his discretion or acted unreasonably in determining that the landfill had a history of

 4 noncompliance. We defer to the Secretary’s determination that the violations were

 5 severe enough to merit the denial of the special waste permit. Moreover, “not only

 6 is the Secretary in the best position to consider what level of past non[]compliance

 7 with the regulations is sufficient to warrant permit denial, . . . the Secretary is also in

 8 the best position to consider more global policy concerns that might weigh against or

 9 in favor of granting a permit.” Id. ¶ 44. Here, the Secretary considered testimony

10 from the Solid Waste Bureau chief that the Bureau relies largely on self-reporting by

11 landfill facilities regarding compliance-related matters because the Bureau has limited

12 resources to conduct frequent inspections and to more directly enforce the regulations.

13 The chief further testified that she had concerns and reservations regarding the

14 issuance of the special waste permit due to the landfill’s poor history of self-reporting.

15 The Secretary weighed NENMRL’s past failures to self-report, as evidenced by the

16 NOV issued by the Air Quality Bureau and the failure to submit vadose zone

17 monitoring records, against the concern that self-reporting is even more critical where

18 special waste is concerned, given its unique handling requirements. Given the

19 Secretary’s position, we defer to his determination that the violations were severe


                                               32
 1 enough to deny the special waste permit modification in light of the reporting

 2 concerns that were raised.

 3 c.     NENMRL’s Failure to Fully Disclose Its History of Violations in the
 4        Permit Application

 5        We briefly address NENMRL’s argument that the Secretary erroneously

 6 determined that the permit application contained an incomplete history of its

 7 violations. Our review of the permit application confirms the Secretary’s findings that

 8 the application: (1) failed to include any information regarding the settlement reached

 9 between the Air Quality Bureau and the landfill, and (2) failed to include the letter of

10 inspection issued by the Solid Waste Bureau regarding vadose zone monitoring

11 records. Although NENMRL argues that it was not required to include the vadose

12 zone letter of inspection because it was issued months after the application was

13 submitted, we note that the application was not deemed complete until a year later on

14 May 11, 2007. Thus, NENMRL had the opportunity to supplement its application

15 with any missing compliance-related documents, and we think that this was its burden

16 under the regulations. See 20.9.1.200(L)(20) NMAC (stating that a permit renewal

17 application shall address the compliance history of the applicant); see also

18 20.1.4.400(A)(1) NMAC (stating that the applicant has the burden of proof as to

19 whether a permit should be issued and that this burden does not shift).




                                              33
 1        In summary, based on our review of the record, we hold that the Secretary’s

 2 decision to deny the special waste permit modification on the basis of NENMRL’s

 3 compliance history was supported by substantial evidence and was neither

 4 unreasonable nor an abuse of discretion.

 5 4.     Issuance of the Secretary’s Final Order on the Same Date as the Hearing
 6        Officer’s Report

 7        NENMRL argues that the Secretary failed to undertake a meaningful review of

 8 the administrative record and the hearing officer’s report prior to issuing the final

 9 order denying the special waste permit modification. NENMRL contends that the fact

10 the final order was issued on the same date as the hearing officer’s report indicates

11 that the Secretary failed to give individualized attention to the voluminous

12 administrative record before him. NENMRL further alleges that had the Secretary

13 undertaken meaningful review of the record prior to rendering a decision, he would

14 have encountered evidence demonstrating that NENMRL had “exceeded the statutory

15 and regulatory requirements for a special waste permit, and that the [h]earing

16 [o]fficer’s [r]eport itself was internally inconsistent.”

17        The burden is on NENMRL to present affirmative evidence to support its claim

18 that the Secretary failed to consider the evidentiary record prior to issuing the final

19 order. See Albuquerque Bernalillo Cnty. Water Util. Auth., 2010-NMSC-013, ¶ 35;

20 Pickett Ranch, 2006-NMCA-082, ¶ 56. “Mere allegation that the [Secretary] did not

                                              34
 1 consider the entire record is insufficient.” Albuquerque Bernalillo Cnty. Water Util.

 2 Auth., 2010-NMSC-013, ¶ 35 (alterations omitted) (internal quotation marks and

 3 citation omitted).

 4        We conclude that NENMRL has failed to meet its burden. NENMRL has not

 5 claimed that the filing date of the final order violates any applicable regulatory

 6 provisions that set forth the filing deadlines for such an order. We presume therefore

 7 that the final order was filed in accordance with all applicable deadlines. See

 8 20.9.1.200(L)(12) NMAC (requiring the Secretary to issue or deny a permit

 9 application within 180 days after the application is deemed complete); 20.1.4.500(D)

10 NMAC (requiring the Secretary to file a final order within thirty days of the filing of

11 the hearing officer’s report or, if applicable, the date of any subsequent

12 comment/argument period following issuance of the hearing officer’s report).

13        Although the final order adopted the hearing officer’s report in its entirety, there

14 is no evidence indicating that the Secretary did not conduct meaningful review of that

15 report or the administrative record prior to issuing the order. To the contrary, the final

16 order includes a statement that the Secretary “considered the administrative record in

17 its entirety, including the [p]roposed [f]indings . . . submitted by the [parties]… and

18 the [h]earing [o]fficer’s [r]eport and [p]roposed [f]indings” prior to rendering a

19 decision. We are not persuaded that the issuance of the order on the same date as the


                                               35
 1 hearing officer’s report negates this express statement by the Secretary or that it

 2 somehow implies that the Secretary failed to consider the entire record, including any

 3 alleged evidence supporting NENMRL’s application.

 4        Furthermore, we observe that the administrative record, with the sole exception

 5 of the hearing officer’s report, was filed and docketed with the hearing clerk of the

 6 NMED prior to December 17, 2007, the date of the final order. In relevant part, the

 7 transcripts from the five-day hearing were filed on October 3, 2007, and the parties’

 8 closing arguments and proposed findings of fact were filed on November 13, 2007.

 9 Thus, the Secretary had the opportunity to review the record prior to reaching his

10 decision and, in the absence of any contrary evidence establishing that he failed to do

11 so, we will not presume any irregularity in his actions. See State ex rel. Reynolds v.

12 Aamodt, 111 N.M. 4, 6, 800 P.2d 1061, 1063 (1990) (“On review of the acts or orders

13 of administrative bodies, the courts will presume, among other things, that the

14 administrative action is correct and that the orders and decisions of the administrative

15 body are valid and reasonable; presumptions will not be indulged against the

16 regularity of the administrative agency’s action.” (internal quotation marks and

17 citation omitted)). Accordingly, we hold that the Secretary did not act arbitrarily or

18 capriciously in this regard.




                                              36
 1 5.     The Secretary’s Conclusion That NENMRL Failed to Address or Respond
 2        to Legitimate Public Concerns Regarding the Special Waste Permit
 3        Modification

 4        NENMRL challenges the Secretary’s denial of the special waste permit

 5 modification on the basis that NENMRL “failed to address or respond to legitimate

 6 concerns raised by the public regarding ordinary concerns of adverse societal impact,

 7 social well-being and quality of life in the community” as specifically tied to the

 8 effects of such a modification.      NENMRL argues that: (1) the administrative

 9 proceedings exceeded the public participation requirements established by our

10 Supreme Court in Colonias; (2) it adequately addressed public concerns throughout

11 the entire permitting process; and (3) the Secretary’s final order failed to identify a

12 nexus, as required under Colonias, between the public concerns raised at the hearing

13 and the applicable solid waste regulations.

14        Because NENMRL’s arguments on this issue center around Colonias, we begin

15 by describing the circumstances of that case and our Supreme Court’s holding there.

16 Colonias involved a permit application filed with NMED for a new landfill operation

17 to be located in Chaparral, New Mexico, an unincorporated community that already

18 had four waste disposal facilities located in its near vicinity. 2005-NMSC-024, ¶¶ 2,

19 9. During a public hearing concerning the permit application, an NMED-appointed

20 hearing officer heard testimony from the applicant and various technical witnesses;


                                             37
 1 she also took comments and testimony from over 300 members of the general public,

 2 the vast majority of whom testified in opposition to the building of another landfill in

 3 Chaparral. Id. ¶¶ 3-4. Despite this overwhelming public opposition, the hearing

 4 officer recommended and the Secretary granted a permit for a ten-year period after

 5 determining that the application complied with all technical requirements listed in the

 6 solid waste regulations. Id. ¶ 6. A nonprofit community organization appealed the

 7 Secretary’s decision, arguing that the hearing officer and, in turn, the Secretary, had

 8 erroneously refused to consider the public’s non-technical testimony regarding quality

 9 of life concerns and the adverse effects of proliferation of landfills on their community

10 in reaching the final decision. Id. ¶¶ 7-9. The appellant argued that it was error for

11 the Secretary to approve a landfill permit solely based on whether the permit

12 application complied with technical requirements established by the Act and its

13 implementing regulations. Id. ¶ 10.

14        The Supreme Court reversed the Secretary’s decision, holding that public

15 participation is a critical and meaningful aspect of the permitting process, as

16 established by the Legislature through the applicable statutory and regulatory

17 schemes. Id. ¶ 24. Therefore, the Court held that the Secretary should consider public

18 concerns about “adverse impacts on social well-being and quality of life” in reaching

19 a decision regarding a permit application and that he must also determine whether the


                                              38
 1 “lay concerns [expressed by the general public] relate to violations of the . . . Act and

 2 its regulations.” Id. The Court further reasoned that although the Secretary “must

 3 allow testimony regarding the impact of a landfill on a community’s quality of life,

 4 . . . the [Secretary’s] authority to address such concerns requires a nexus to a

 5 regulation.” Id. ¶ 29. Applying this holding to the facts of the case, the Supreme

 6 Court held that “the Secretary abused his discretion by limiting the scope of testimony

 7 during the public hearing and [by] interpreting the Department’s role as confined to

 8 technical oversight.” Id. ¶ 27. The Court then determined that a nexus existed

 9 between the public concerns raised at the hearing and applicable solid waste

10 regulations:

11        [W]e do find that quality of life concerns expressed during the hearing
12        bear a relationship to environmental regulations the [s]ecretary is
13        charged with administering. Although both parties refer to the issues on
14        appeal in a wide variety of ways, including “social impact,”
15        “sociological concerns,” “social well-being,” and “environmental
16        justice,” we believe there are legitimate concerns at the core of [the
17        appellant’s] claim that are within the purview of the [s]ecretary’s
18        oversight role. Contrary to the Department’s position, the impact on the
19        community from a specific environmental act, the proliferation of
20        landfills, appears highly relevant to the permit process.

21 Id. ¶ 30. The Court reasoned that if the concerns expressed at the hearing regarding

22 proliferation of landfills had “an identified effect on the community’s development

23 and social well-being, it [was] not an amorphous general welfare issue, but an

24 environmental problem” and, therefore, the lay testimony regarding proliferation was

                                              39
 1 “relevant within the context of environmental protection[s] promised in the . . . Act

 2 and its regulations.” Id. ¶ 32. The Court reversed the granting of the permit and

 3 remanded the case to the Secretary “to consider whether evidence of the harmful

 4 effects from the cumulative impact of industrial development rises to the level of a

 5 public nuisance or potential hazard to public health, welfare or the environment. Id.

 6 ¶ 34.

 7         We address NENMRL’s arguments in the context of the Colonias decision.

 8 NENMRL contends that the administrative permitting process in this case exceeded

 9 the public participation requirements set forth in Colonias on two grounds. First,

10 NENMRL argues that its application and the testimony from NENMRL technical

11 witnesses at the hearing “unquestionably satisfie[d] the non-proliferation requirements

12 approved by the Supreme Court in [Colonias]” and subsequently adopted in the 2007

13 version of the solid waste regulations. Second, NENMRL asserts that it “satisfied

14 [Colonias] by voluntarily facilitating meaningful public participation in the permitting

15 process.” As to the first ground, we are unpersuaded by NENMRL’s argument

16 because the issue before the Supreme Court in Colonias was not the approval of non-

17 proliferation requirements but, rather, whether the Secretary had erred in refusing to

18 consider the lay concerns raised by the general public, which in that case happened

19 to center around the proliferation of industrial sites. 2005-NMSC-024, ¶¶ 11-12. The


                                              40
 1 Colonias decision did not create a baseline rule requiring permit applicants to address

 2 non-proliferation requirements.      Thus, NENMRL’s position that it met non-

 3 proliferation requirements established by the 2007 version of the solid waste

 4 regulations is misplaced. We also are not convinced that NENMRL’s second

 5 argument—that it voluntarily facilitated “meaningful public participation in the

 6 permitting process”—has sufficient relevancy. There is no real question in this case

 7 that the hearing officer in fact allowed public participation at the hearing, as

 8 envisioned by Colonias. The parties do not dispute any aspect of the hearing officer’s

 9 decision to allow lay testimony at the hearing; rather, the parties dispute the

10 Secretary’s subsequent decision to include the lay concerns as a specific basis for the

11 denial of special waste permit modification. Moreover, even if we were to address

12 NENMRL’s argument, we conclude that it failed to facilitate meaningful public

13 participation in the permitting process, as evidenced by the Secretary’s determination,

14 which we have affirmed on appeal, that NENMRL failed to comply with individual

15 notice requirements set forth in the solid waste regulations.

16        We turn then to address the only dispositive question on this issue: whether the

17 Secretary was permitted under Colonias to address the public concerns raised at the

18 hearing in his final order as an additional basis for his denial of the special waste

19 permit modification. We conclude that it was not error. Unlike the circumstances in


                                             41
 1 Colonias, where the application at issue had met all technical requirements under the

 2 solid waste regulations, the Secretary determined in this case that NENMRL’s

 3 application failed to meet several technical requirements with respect to the special

 4 waste permit modification. In relevant part, these included the failure to meet

 5 regulatory requirements concerning individual notice as to the origin and source of

 6 special wastes; the lack of specific estimates for anticipated volumes and frequency

 7 of special waste disposal in the application; failure to submit inspection reports and

 8 a poor compliance history with existing permit conditions. Our review of the lay

 9 comments and testimony given at the hearing confirms the Secretary’s view that the

10 majority of concerns raised at the public hearing pertained to the special waste permit

11 modification and reiterated the technical deficiencies in NENMRL’s application. The

12 Secretary identified the following nexus between the public’s concerns and the

13 regulatory requirements:

14        [T]he majority of the concern about the special waste permit was of the
15        unknown factors such as the specific content of the special waste, the
16        source of the special waste, how special waste would be handled, the
17        identity and the qualifications of individuals expected to handle the
18        special waste, and how specific types and amounts of special waste
19        might impact the local environment, health and quality of life[.]

20 Contrary to NENMRL’s position that the Secretary failed to identify a nexus between

21 the concerns and actual regulatory requirements, we think the above accurately

22 reflects a nexus between the public concerns raised at the hearing and regulatory

                                             42
 1 requirements. See, e.g., 20.9.1.200(F)(1)-(3) NMAC (requiring a permit application

 2 to include, among others, “a complete description of the types of wastes to be

 3 accepted[,]” “the anticipated amount and frequency of disposal of the wastes[,]” and

 4 “the method of disposal”).

 5        In a final effort to counter the public concerns raised by the Secretary in his

 6 final order, NENMRL asserts that testimony from its technical witnesses adequately

 7 addressed all public concerns. However, our role as the reviewing court is not to

 8 reweigh the facts and evidence before the Secretary. See Tallman v. ABF (Arkansas

 9 Best Freight), 108 N.M. 124, 127-28, 767 P.2d 363, 366-67 (Ct. App. 1988) (noting

10 that even under whole record review, “[a] reviewing court may not reweigh the

11 evidence,” but should only determine whether, in light of the whole record, the result

12 reached is reasonable), modified on other grounds by Delgado v. Phelps Dodge Chino,

13 Inc., 2001-NMSC-034, ¶ 27, 131 N.M. 272, 34 P.3d 1148. The burden of persuasion

14 was on NENMRL below, and the Secretary was in the best position to weigh the

15 testimony and evidence submitted by NENMRL against the technical requirements

16 and any concerns raised by the public that bore a nexus to the solid waste regulations.

17        Based on the foregoing, we conclude that the Secretary considered the public

18 concerns raised at the hearing in accordance with Colonias and that it was not

19 improper for him to rely on community concerns as an additional basis for denying


                                             43
 1 the permit modification for special wastes. See Colonias, 2005-NMSC-024, ¶ 26

 2 (emphasizing that “community concerns can affect the [s]ecretary’s decision to deny

 3 a permit or impose conditions on one”).

 4 6.     The Secretary’s Conclusions Regarding Herzog and Its Employees

 5        NENMRL challenges the Secretary’s findings regarding Herzog, the operator

 6 of the landfill, and its employees. NENMRL asserts that the Secretary acted contrary

 7 to law in concluding that: (1) the Solid Waste Bureau failed to investigate Herzog and

 8 its compliance history, despite concerns raised by the community; (2) NENMRL

 9 failed to submit a disclosure statement for a particular Herzog employee, who was the

10 only individual certified to handle asbestos, a specific type of special waste; and (3)

11 NENMRL was highly dependent on Herzog’s expertise in the handling of special

12 waste. NENMRL contends that neither the Act nor its implementing regulations

13 require NENMRL, as the permit applicant, or the Solid Waste Bureau to investigate

14 and/or obtain disclosure statements from third-party operators and their employees.

15 Accordingly, it argues that the Secretary acted contrary to law and imposed ultra vires

16 requirements in his findings of fact and conclusions regarding Herzog and its

17 employees.

18        Our resolution of this issue turns on a question of statutory interpretation. We

19 must determine whether the Act or its implementing regulations require applicants


                                             44
 1 and/or the Solid Waste Bureau to investigate or obtain disclosure statements for third-

 2 party operators as part of the application process. NENMRL’s primary argument is

 3 that the Secretary erroneously determined that these actions were required under the

 4 Act and the solid waste regulations.

 5        Interpretation of a statute is a question of law, which we review de novo on

 6 appeal. In re Camino Real Envtl. Ctr., Inc., 2010-NMCA-057, ¶ 12, 148 N.M. 776,

 7 242 P.3d 343. When presented with a question of statutory interpretation, we rely on

 8 the following general principles:

 9        (1) the plain language of the statute is the primary indicator of legislative
10        intent; (2) we will not read into a statute language which is not there,
11        particularly if it makes sense as written; (3) we will give persuasive
12        weight to long-standing administrative constructions of statutes by the
13        agencies charged with administering them; and (4) when several sections
14        of a statute are involved, they must be read together so that all parts are
15        given effect.

16 Id. Likewise, we observe that “[t]he canons of statutory construction guide our

17 interpretation of administrative regulations.” Albuquerque Bernalillo Cnty. Water

18 Util. Auth., 2010-NMSC-013, ¶ 51. Finally, “[a]lthough we are not bound by an

19 agency's interpretation of statutes and rules because it is the function of the courts to

20 interpret the law, we afford administrative agencies considerable discretion to carry

21 out the purposes of their enabling legislation, and we give deference to an agency’s

22 interpretation of its own regulations.” Phelps Dodge Tyrone, Inc. v. N.M. Water


                                               45
 1 Quality Control Comm’n, 2006-NMCA-115, ¶ 25, 140 N.M. 464, 143 P.3d 502

 2 (internal quotation marks and citations omitted).

 3        Section 74-9-21(A) of the Act covers the disclosure and investigatory

 4 requirements applicable to a landfill permit application. It states that “[e]very

 5 applicant for a permit shall file a disclosure statement with the information required

 6 by and on a form developed by [NMED] at the same time he files his application for

 7 a permit.” Section 74-9-21(A) (emphasis added). The section further states that the

 8 Secretary “may also request information . . . regarding any person who will be or

 9 could reasonably be expected to be involved in management activities of the solid

10 waste facility or any person who has a controlling interest in any permittee.” Section

11 74-9-21(B) (emphasis added). In relevant part, Section 74-9-3 of the Act, which

12 provides definitions for terms used, does not include a definition for “applicant” or for

13 “operator.” Section 74-9-3. Finally, we observe that the Act gives the Secretary the

14 authority to deny a permit application “if he has reasonable cause to believe that any

15 person required to be listed on the application . . . has[] refused to disclose or failed

16 to disclose the information required under . . . Section 74-9-21.” Section 74-9-

17 24(B)(2).

18        As for the solid waste regulations, they require that that “[a]ny person seeking

19 a permit” file an application which includes, among other items, “a disclosure


                                              46
 1 statement consistent with Section 74-9-21 of [the Act].” 20.9.1.200(A)(2)(f) NMAC.

 2 The regulations also include an extensive definition section. 20.9.1.7 NMAC.

 3 Although no definition for applicant is included, the word “operator” is defined as the

 4 “person(s) responsible for the overall operation of all or any portion of a solid waste

 5 facility,” and the word “owner” is defined as the “person(s) who owns the facility or

 6 part of a solid waste facility.” 20.9.1.7(BC), (BD).

 7        We begin by describing the basis for the Secretary’s interpretation of Section

 8 74-9-21 of the Act and the above regulations. In her report, the hearing officer

 9 recommended and the Secretary adopted a conclusion of law stating that NENMRL

10 had failed to provide a disclosure statement for a particular Herzog employee. The

11 hearing officer further determined that the Bureau failed to exercise its “discretionary

12 authority” under Section 74-9-21(B) to investigate Herzog, given its role as an entity

13 “who will be or could reasonably be expected to be involved in management activities

14 of the solid waste facility.” On the basis of this determination, the Secretary adopted

15 an additional conclusion of law that the Bureau “failed to investigate the background

16 of Herzog . . . and its compliance history.” NENMRL challenges both of these

17 conclusions.

18        Applying our rules of statutory interpretation, we hold that the Secretary

19 erroneously concluded that Section 74-9-21(A) of the Act required NENMRL to


                                              47
 1 submit disclosure statements for Herzog employees. Under the plain meaning rule,

 2 we find the language: “[e]very applicant for a permit shall file a disclosure statement

 3 . . . at the same time he files his application for a permit” in Section 74-9-21(A) to be

 4 clear and unambiguous. (Emphasis added.) See Sims v. Sims, 1996-NMSC-078, ¶ 17,

 5 122 N.M. 618, 930 P.2d 153 (stating that the plain meaning rule requires a court to

 6 give effect to the statute’s language and refrain from further interpretation when the

 7 language is clear and unambiguous). Although the word “applicant” is not separately

 8 defined in the Act, the plain language of Section 74-9-21(A) unambiguously considers

 9 an applicant to be an individual who “files his application for a permit.” Cf. Blacks

10 Law Dictionary 115 (9th ed. 2009) (defining “applicant” as “[o]ne who requests

11 something”). Here, it is undisputed that NENMRL was the only entity to file an

12 application for a permit with NMED, and thus, the Legislature’s use of the word

13 “shall” in 74-9-21(A) imposed a mandatory requirement only on NENMRL to submit

14 a disclosure statement along with its application. This mandatory requirement could

15 not have been imposed on Herzog or its employees because Herzog did not file the

16 permit application at issue in this case.

17        In addition, we read all provisions under Section 74-9-21 together to ascertain

18 the Legislature’s intent regarding disclosure statements. Medina v. Holguin, 2008-

19 NMCA-161, ¶ 14, 145 N.M. 303, 197 P.3d 1085 (“Based on the statutory canon of


                                               48
 1 construction, noscitur a sociis, a court must look to the neighboring words in a statute

 2 to construe contextual meaning.”). In so doing, we conclude that the Legislature

 3 included another provision in the Act, Section 74-9-21(B), to address disclosure

 4 requirements and investigations of individuals other than the applicant. The following

 5 language in Section 74-9-21(B)—stating that the Secretary “may also request

 6 information . . . regarding any person who will be or could reasonably be expected to

 7 be involved in management activities of the solid waste facility”—unambiguously

 8 gives NMED and the Solid Waste Bureau discretionary authority to investigate others

 9 who may be intimately involved in a landfill operation. Thus, it is clear that the

10 Legislature intended a mandatory disclosure requirement for applicants only but gave

11 discretion to the Solid Waste Bureau to also investigate and seek disclosure

12 requirements for operators and landfill managers such as Herzog. We conclude that

13 the failure of the Solid Waste Bureau to exercise its discretionary authority under

14 Section 74-9-21(B) could not be attributed to an applicant such as NENMRL as a

15 basis for permit denial.

16        Our interpretation of the Act is further supported by the regulations governing

17 permitting procedures for NMED. See 20.1.4 NMAC (setting forth procedural

18 regulations for public hearings before the Environment Department involving, among

19 others, permit issuance and renewal applications).          These regulations define


                                              49
 1 “‘[a]pplicant’” as “any person whose application for a permit, renewal or modification

 2 to a permit, or license is the subject of the proceeding.” 20.1.4.7(A)(3) NMAC.

 3        Based on the foregoing, we interpret Section 74-9-21 of the Act to require only

 4 those individuals who file a permit application to submit to the Act’s mandatory

 5 disclosure requirements. Accordingly, the Secretary’s conclusion that NENMRL

 6 failed to submit a disclosure statement for a particular Herzog employee was

 7 erroneous, as was the Secretary’s conclusion regarding the Solid Waste Bureau’s

 8 failure to investigate Herzog and its compliance history. However, because the

 9 Secretary’s denial of the special waste permit modification is amply supported by any

10 of the other reasons discussed in this opinion, we affirm the Secretary’s final order.

11 See Atlixco, 1998-NMCA-134, ¶ 28.




                                             50
 1 C.     CROSS-APPEAL

 2        In the cross-appeal, Concerned Citizens challenges the Secretary’s final order

 3 insofar as it grants NENMRL a permit modification for the acceptance of municipal

 4 solid waste via rail transport. At the public hearing, Concerned Citizens argued for

 5 the denial of this permit modification for two primary reasons. First, it argued that

 6 NENMRL had committed a prohibited act under the solid waste regulations by

 7 accepting waste by rail in the past from a rail company that was not registered with

 8 NMED, and that this activity occurred without a permit condition or modification

 9 authorizing such acceptance. Second, it asserted that NENMRL’s current permit

10 application was incomplete because its “anticipated commercial hauler of waste by

11 rail” was the same unregistered rail company; Concerned Citizens argued that

12 registration was required under the solid waste regulations. It asserted that the past

13 violation coupled with the present failure of NENMRL’s “anticipated commercial

14 hauler by rail” to register with NMED was adequate grounds for denying the permit

15 modification to accept waste by rail transport.

16        On appeal, Concerned Citizens contends that the Secretary failed to address

17 these arguments because he improperly disclaimed his jurisdiction over regulating the

18 transport of waste by rail.     Our review of the record does not support this

19 characterization of the Secretary’s determination. It appears that the Secretary


                                             51
 1 addressed Concerned Citizens’ arguments on their merits. Although the Secretary

 2 also went on to discuss NMED’s jurisdiction over rail transport, this discussion was

 3 not necessary to its rejection of Concerned Citizens’ arguments and, as a result, we

 4 need not address the jurisdictional issue. We explain.

 5        The hearing officer’s report, which was adopted in its entirety by the Secretary,

 6 rejected Concerned Citizens’ argument regarding NENMRL’s past violations for

 7 accepting waste by rail without prior authorization. He determined that NENMRL

 8 had “never received a notice of violation [for the] unauthorized and illegal acceptance

 9 of waste by rail.” He further concluded that “credible testimony” was presented at the

10 hearing to substantiate that during the time period NENMRL had accepted waste by

11 rail, the solid waste regulations applicable at that time had not required NENMRL “to

12 amend its transportation plan to include waste by rail.” As to Concerned Citizens’

13 argument that NENMRL’s permit application was incomplete due to the unregistered

14 status of its anticipated hauler of waste by rail, the hearing officer rejected this

15 argument and instead concluded that the application met all regulatory requirements

16 with regard to the permit modification for the acceptance of municipal solid waste by

17 rail. Necessarily implicit in this conclusion was a finding that the application was

18 complete and contained all information required in order to grant the permit

19 modification.    In other words, the hearing officer implicitly determined that


                                             52
 1 registration by the waste hauler was not required in the application.                  See

 2 20.9.1.200(L)(16)(b) NMAC (giving the Secretary cause to deny a permit application

 3 due to the applicant’s failure to “to disclose fully all relevant facts, or the permittee’s

 4 misrepresentation of any relevant facts at any time”).

 5        The hearing officer then went on to discuss NMED’s authority to limit the

 6 transportation of waste by rail, an issue contested by the parties. The Solid Waste

 7 Bureau took the position at the hearing that the Secretary had only limited jurisdiction

 8 over the transportation of waste by rail, while Concerned Citizens primarily argued

 9 that the Secretary must have jurisdiction over rail transportation of waste if the

10 Secretary has the authority to grant a permit modification to accept waste by rail.

11 Although the hearing officer acknowledged Concerned Citizens’ argument, he

12 determined that Concerned Citizens had failed to provide him with any legal authority

13 under which he could completely prevent the acceptance of waste by rail. In

14 accordance with the Bureau’s position, he then concluded that NMED “only ha[d]

15 jurisdiction over the waste handling practices associated with transferring the waste

16 from the railcars to the landfill operations.”

17        We conclude that the hearing officer properly disposed of Concerned Citizens’

18 arguments on their merits and that the discussion regarding jurisdiction was

19 immaterial to that disposition. Our analysis requires interpretation of the regulation


                                               53
 1 applicable to commercial haulers of waste, which we review de novo. See Rio Grande

 2 Chapter of the Sierra Club v. N.M. Mining Comm’n, 2003-NMSC-005, ¶ 13, 133

 3 N.M. 97, 61 P.3d 806 (stating that “it is the function of the courts to interpret the law,

 4 and courts are in no way bound by the agency’s legal interpretation” of agency

 5 regulations (internal quotation marks and citation omitted)).

 6        The relevant regulation provides:

 7              (1) Commercial haulers of solid waste shall register with the
 8        Department by December 31, 1994, or [thirty] days prior to operations,
 9        and shall submit the following information:

10                     (a)     the name, address, phone number of the applicant and
11        contact person;

12                     (b) the anticipated start up date, hours of operation, and
13        days of collection;

14                     (c) a list of types of storage containers required for
15        residences, commercial, institutional and industrial establishments to be
16        served;

17                      (d)    location of vehicle maintenance yard;

18                     (e)     certification of proper licensing for both the drivers
19        and vehicles;

20                      (f)    means of controlling and mitigating odors;

21                      (g) the transport distance from the nearest and farthest
22        points of collection to the solid waste facility;

23                      (h)    any transport transfer requirements;


                                               54
 1                       (i)    location of transfer station(s) to be used, if any;

 2                       (j)    the name and location of each and any solid waste
 3         facility to be used; and

 4                       (k) an outline of proposed training for drivers and crew
 5         to be able to differentiate between hazardous waste, special waste[,] and
 6         solid waste.

 7 20.9.1.200(N) NMAC (emphasis added).

 8         We rely on canons of statutory interpretation to guide our interpretation of the

 9 above regulation. Albuquerque Bernalillo Cnty. Water Util. Auth., 2010-NMSC-013,

10 ¶ 51. Under the plain meaning of this provision, registration by commercial haulers

11 is required “by December 31, 1994, or [thirty] days prior to operations.”

12 20.9.1.200(N)(1) NMAC. Significantly, the provision does not mention registration

13 in the context of the permitting process; rather, it plainly requires only that registration

14 must occur thirty days prior to operations starting at the landfill. Thus, the failure of

15 any of NENMRL’s anticipated commercial haulers to register before or during the

16 application process was not a violation of 20.9.1.200(N) NMAC because at that stage,

17 the requested operations had not started. Furthermore, the above provision does not

18 require any action on the part of a permittee or permit applicant, such as NENMRL,

19 with respect to a commercial hauler’s obligation to register with NMED. Likewise,

20 the regulatory provisions stating what information a permit applicant must include in

21 an application do not expressly mention that commercial hauler registration

                                                55
 1 information be included in the application. See 20.9.1.200(A) NMAC. Thus, we

 2 disagree with Concerned Citizens’ argument that the regulations mandate that the

 3 permit application include commercial hauler registration information.

 4        In addition, we agree with NMED’s argument that the failure of a commercial

 5 hauler to register was separate from and could not form the basis for denying

 6 NENMRL’s requested permit modification. Under the solid waste regulations, the

 7 Secretary has cause to deny a permit application if there is:

 8                     (a) noncompliance by the permittee with any condition
 9        of the permit or this Part;

10                     (b) the permittee’s failure in the application or during the
11        permit issuance process to disclose fully all relevant facts, or the
12        permittee’s misrepresentation of any relevant facts at any time;

13                     (c) a determination that the permitted activity endangers
14        public health, welfare or the environment;

15                      (d) the applicant's failure to demonstrate a knowledge
16        and ability to operate a facility in accordance with this Part or a history
17        of non[]compliance with environmental regulations or statutes at other
18        facilities;

19                     (e) modification of a facility without the approval of the
20        Secretary, or failure to obtain the approval for transfer of the permit.

21 20.9.1.200(L)(16) NMAC.         Concerned Citizens asserts that the failure of a

22 commercial hauler to register under 20.9.1.200(N) NMAC caused NENMRL to

23 violate sections (a) and (b) of the above provision. We are not persuaded. A


                                              56
 1 commercial hauler’s noncompliance with regulatory registration requirements does

 2 not equate to the permittee’s noncompliance with the regulations because, as we have

 3 previously stated, the permittee has no obligations under the regulatory provision

 4 requiring commercial haulers to register with NMED.            Moreover, we are not

 5 persuaded that the lack of registration information from NENMRL’s anticipated rail

 6 carrier in its application constituted NENMRL failure to “disclose fully all relevant

 7 facts” under 20.9.200(L)(16)(b) NMAC above. The Secretary was in the best position

 8 to determine whether NENMRL’s application included “all relevant facts” regarding

 9 the permit modification to accept waste by rail. Based on our interpretation that

10 commercial hauler registration is required “[thirty] days prior to operations” and not

11 specifically during the permitting process, we conclude that the Secretary did not err

12 in determining that the application disclosed all relevant facts needed for him to reach

13 a decision as to the permit application.

14        Concerned Citizens asserts in its reply brief that NMED’s and NENMRL’s

15 argument promoting the interpretation we have adopted cannot serve as the basis for

16 our decision in this case because it was never raised in the administrative proceedings.

17 However, “an appellee has no duty to preserve issues for review and may advance any

18 ground for affirmance on appeal.”          Cordova v. World Fin. Corp. of N.M.,




                                              57
 1 2009-NMSC-021, ¶ 18, 146 N.M. 256, 208 P.3d 901 (internal quotation marks and

 2 citation omitted).

 3        We hold that the commercial hauler requirements under the solid waste

 4 regulations are separate from the permitting process and, therefore, the failure of a

 5 commercial hauler to register does not render the application incomplete, nor does it

 6 constitute grounds for denying the application. We need not reach the issue of the

 7 Secretary’s jurisdiction over rail transport because any such determination is not

 8 dispositive on the two issues argued below by Concerned Citizens as grounds for

 9 denying the permit modification at issue. Accordingly, we affirm the Secretary’s

10 grant of a permit modification to NENMRL for the acceptance of municipal solid

11 waste via rail transport.

12 CONCLUSION

13        For the foregoing reasons, we affirm the Secretary’s final order.

14        IT IS SO ORDERED.



15
16                                        CYNTHIA A. FRY, Judge




                                            58
1 WE CONCUR:


2
3 LINDA M. VANZI, Judge



4
5 TIMOTHY L. GARCIA, Judge




                             59