This action of contract was transferred for trial to the Central District Court of Worcester by order of a Justice of the Superior Court under the provisions of G.L. c. 231, § 102 e. There was a finding for the defendant and the plaintiffs claiming to be aggrieved by the denial of certain of their requests for rulings of law requested a report.
From the report, as amplified, it appears that in December of 1963, the defendant, (builder)
The contract provided that the “builder guarantees dry cellar for one (1) year after completion”. There was evidence of water in the cellar at both trials. The plaintiffs, in the present action, claim a breach of this provision. There was also evidence that the plaintiffs prevented full performance of the contract by the builder by “locking him out”.
The trial judge in his special findings of fact, said: “I rule that the plaintiffs having prevented the defendant (builder) from finishing the house it does not lie in their mouths to say the cellar condition which they allege does exist would have existed had defendant been permitted to complete his contract”.
This ultimate finding, or ruling, determines the rights of the parties. The plaintiffs having breached the contract cannot now attempt to take advantage of one of its provisions.
The trial judge also ruled that the issue in the present case had been litigated in the previous action and was therefore res adjudicata. Because of our holding as stated above we need not decide the correctness of this ruling.
The report is to be dismissed.