Opinion issued April 13, 2023
In The
Court of Appeals
For The
First District of Texas
————————————
NO. 01-20-00055-CV
———————————
AMERICAN MIDSTREAM (ALABAMA INTRASTATE), LLC,
Appellant/Counter-Appellee
V.
RAINBOW ENERGY MARKETING CORPORATION, Appellee/Counter-
Appellant
On Appeal from the 157th District Court
Harris County, Texas
Trial Court Case No. 2017-24591
OPINION
Appellee Rainbow Energy Marketing Corporation (Rainbow) sued appellant
American Midstream (Alabama Intrastate), LCC, (AMID) for breach of contract,
repudiation, fraud, and negligent misrepresentation relating to a natural gas
transportation contract. AMID counter-sued Rainbow for breach of contract.
Following a bench trial, the trial court found in favor of Rainbow on its claims, and
Rainbow elected to recover on its breach of contract claim. The trial court rendered
judgment awarding Rainbow $6,145,215.89 as actual damages, plus pre-judgment
interest, costs, and post-judgment interest. In five issues, AMID contends that
(1) the evidence was insufficient to support the trial court’s findings on Rainbow’s
tort claims; (2) the evidence was insufficient to support the trial court’s findings on
Rainbow’s breach of contract and repudiation claims; (3) even if the trial court’s
liability findings stand, Rainbow’s damages are unrecoverable; (4) AMID is
entitled to recover on its own counterclaim for breach of contract against Rainbow;
and (5) in the alternative, AMID is entitled to have the case remanded for a new
trial. Rainbow contends, in its sole issue, that the trial court erred in denying its
request for attorney’s fees.
We conclude that the evidence was sufficient to support the trial court’s
findings on the breach of contract claim, and therefore do not address the
remaining tort claims. We further conclude that the evidence was sufficient to
support the trial court’s award of damages, and we conclude that the trial court did
not err in denying Rainbow’s claim for attorney’s fees.
Accordingly, we affirm.
2
Background
This lawsuit arises out of a contract between Rainbow—a natural gas trading
company—and AMID—a natural gas transportation company that owns the
Magnolia pipeline. The parties refer to this contract as the MAG-0005. Effective
March 1, 2015, AMID agreed to provide firm balancing services and transportation
of certain quantities of natural gas to Rainbow. In return, Rainbow agreed to pay a
demand charge or “firm transportation rate” of more than $1 million per year,
regardless of the services it actually used. As the trial court found here, “In the
natural gas industry, pipelines offer service that is either firm or interruptible. A
pipeline can curtail or decline to provide firm service only if specifically
authorized by the contract. A pipeline can curtail or decline to provide interruptible
service for any reason.”1
AMID, however, faced difficulties in performing under the MAG-0005. Its
relationship with the connecting Transco pipeline complicated its performance, and
on several occasions between January 2016 and January 2017, AMID limited or
curtailed Rainbow’s use of the balancing services provided for by the MAG-0005.
1
See also “Natural gas power plants purchase fuel using different types of
contracts,” U.S. Energy Information Admin.,
https://www.eia.gov/todayinenergy/detail.php?id=35112 (Feb. 27, 2018, last
visited March 29, 2023) (stating that “firm” contracts provide agreed-upon
capacity at higher priority for transport and “cannot be curtailed . . . except under
unforeseeable circumstances,” while “interruptible” contracts are lower-priority
and may be stopped or curtailed if firm contract holders use all available capacity
or for other reasons).
3
Rainbow nevertheless continued paying the demand charges. Rainbow had
negotiated the MAG-0005 as a firm contract so that it could increase the amount of
gas it could supply to its customers. It needed to know that AMID’s performance
under the MAG-0005 would be reliable so that Rainbow, in turn, could be sure to
have the gas supply and transportation capacity to meet its own obligations to its
customers. Rainbow worked with AMID to determine if the difficulties with the
MAG-0005 could be resolved.
Ultimately, in December 2016, AMID informed Rainbow that it would no
longer be able to use the full capacity provided for in the MAG-0005 over
consecutive days, that the contract would be treated as interruptible rather than
firm, and that AMID had to limit service to Rainbow to “stay under the radar” with
Transco. On February 1, 2017, Rainbow sent written notice to AMID terminating
the MAG-0005.
In April 2017, Rainbow sued AMID, asserting that AMID breached the
MAG-0005. Rainbow also alleged causes of action for fraud, fraudulent
inducement, and negligent misrepresentation based on AMID’s knowing or
reckless representations that it had sufficient capacity in its pipeline to guarantee
20,000 MMBtu of gas per day in balancing services and representing that
Rainbow’s right to use AMID’s system would be “firm,” when, in fact, it could not
perform. AMID filed a counterclaim alleging that Rainbow breached the MAG-
4
0005 by failing to pay the transportation rate, also referred to as a demand charge,
and by failing to comply with other billing and payment terms and that Rainbow
wrongfully terminated the contract.
The trial court conducted a bench trial on Rainbow’s claims for breach of
contract, repudiation, fraud and negligent misrepresentation as well as AMID’s
counterclaim for wrongful termination of the contract. The testimony, documents,
and other evidence was voluminous.
A. Rainbow Trades Natural Gas
Rainbow’s president Stacy Tschider testified regarding Rainbow’s general
business model, putting into context the MAG-0005 and its negotiation,
performance by the parties, and consequences of its breach. Rainbow is a natural
gas trading company in the business of supplying customers with natural gas since
1994. Rainbow’s business model included a strategy of making “forward sales,” or
commitments to provide a particular quantity of gas at a specified location and date
in the future, especially during the winter months. These contracts were typically
negotiated and signed during the summer months. Rainbow would then enter other
agreements to purchase gas at various locations to satisfy the sales contracts,
including making “baseload” purchases—purchases scheduled in advance—plus
daily trades and buys.
5
In addition to its purchase of the gas itself, Rainbow also entered contracts
for transportation rights to move the purchased gas to its customers. Transportation
of natural gas involves the receipt of the gas by the company providing the
transportation, the movement of gas through the transporter’s pipeline system, and
the delivery of gas by the transporter for the shipper’s account. Rainbow entered
both “firm” and “interruptible” transportation contracts with various pipelines.
Rainbow also used contacts in the industry to purchase “recallable” excess
capacity, which is excess capacity that shippers were frequently required by
industry regulations to have available (and thus might need to “recall” or put back
into use) but would not actually need to use on any given day.
To facilitate these transportation transactions, a shipper like Rainbow would
make a “nomination,” or a request for service under a specific contract, indicating
the specific date, quantities, and receipt and delivery locations. Rainbow typically
made these nominations to transport gas from one location to another in pairs. It
would make a nomination for the point where gas entered a particular pipeline and
another for where it exits. Nominations are subsequently “confirmed” by the
transporter. For the most part, pipelines keep nominations into and out of their
system in balance to maintain the proper operational pressure on the pipeline.
Transportation services thus can include both storage services and balancing
services, which essentially allow a customer to either “pull” gas that it will owe
6
back to the pipeline or “park” gas that the pipeline will owe back the customer at a
future time so that the customer can balance gas supply with actual demand.
Tschider testified that Rainbow has “contracts with hundreds of companies
throughout the United States” and other parts of North America. He stated that
“reliability” was the most important concern in meeting customers’ needs, and
Rainbow’s extensive business network helped the company have “the tools in
place to be able to facilitate [its] transactions.” Rainbow does business with over
one-hundred companies and utilities, and, over the years, Rainbow has entered
hundreds of contracts with companies like Duke Energy and Shell.
Tschider explained that Rainbow had entered thousands of forward sales
contracts as both a buyer and a seller, depending on the circumstances. Tschider
stated that this type of contract allowed the company to understand in advance the
cost of the purchase, the cost for transportation, and the price at which to sell the
gas to make a profit. Forward sales contracts allowed “supply certainty,” which
helped Rainbow provide reliability to its business partners and customers. Tschider
further testified that Rainbow preferred to use firm, as opposed to interruptible,
contracts. Thus, it engaged in what he called “back-to-back transactions,” meaning
that “[Rainbow has] very, very little risk associated with that transaction.
Everything is matched. I’m buying firm, I’m transporting firm, and I’m selling
firm.” Tschider testified that Rainbow did this type of deal “all the time.”
7
B. AMID Owns the Magnolia Pipeline
AMID is one of the transportation companies that Rainbow used to transport
natural gas to its customers. Formed in 2009, AMID owns, operates, and develops
numerous midstream energy assets, including natural gas pipelines, gathering
systems, processing plants, and storage facilities. One of the pipelines owned by
AMID is the Magnolia pipeline, a small natural gas pipeline located in Alabama
that connects to the larger Transco pipeline. The Transco pipeline connects Texas
to Pennsylvania and is divided into zones. Because of its location, the Magnolia
pipeline has strategic significance in moving natural gas into colder northern states.
There is a constraint point, where gas transportation bottlenecks in times of peak
demand, at station 85 of the Transco pipeline, just west of the Magnolia-Transco
Interconnect. The Magnolia also serves to connect other pipeline systems, such as
the Tennessee Gas pipeline and the Southcross pipeline, to the Transco pipeline.
Numerous parties, regulations, and agreements govern interactions between
AMID’s Magnolia pipeline and the Transco pipeline. The Federal Energy
Regulatory Commission (FERC) regulates, among other things, interstate
transmission of natural gas. As part of its oversight, FERC requires natural gas
companies to file tariffs, or compilations of all the effective rate schedules and
copies of each form or service agreement. See, e.g., 18 C.F.R. § 154.2(b) (defining
“FERC Gas Tariff”). The rate schedule in the tariffs includes “a statement of a rate
8
or charge for a particular classification of transportation or sale of natural gas”
subject to FERC’s jurisdiction and “all terms, conditions, classifications, practices,
rules, and regulations affecting such rate or charge.” Id. § 154.2(e). In addition to
the regulations provided by federal and state entities, interactions between the
Magnolia and the Transco are subject to the terms of private agreements like the
Operational Balancing Agreement (OBA) between AMID and The Williams
Companies, the owner of the Transco pipeline.
C. Rainbow Contracted with AMID for Transportation Services
Rainbow originally became interested in using the Magnolia pipeline to
transport gas from the Tennessee pipeline to the Southcross pipeline, and then to
the Magnolia and on to Rainbow’s ultimate customers. AMID and Rainbow
entered into their first agreement for Rainbow to transport natural gas on AMID’s
Magnolia pipeline in 2014 and renewed through 2018, including while this
underlying litigation was on-going. This contract, the MAG-0001, provided for
firm transportation of 25,000 MMBtus of natural gas to be moved though the
Magnolia pipeline system.
Rainbow realized that its current customers had even more demand than it
could supply using the MAG-0001. Because of the potential for backlog or
constriction on the Transco at station 85, near the Mississippi-Alabama border, and
the possibility of acquiring cheaper gas in the part of the south that falls within
9
Transco’s “Zone 4” and entering into additional forward sale contracts with
customers in colder locales along the east coast in “Zone 5,” Rainbow became
interested in an additional contract with AMID to provide balancing services.
Tschider and other Rainbow representatives testified that obtaining additional
capacity and balancing services would allow Rainbow additional flexibility to
enter into more forward sales contracts with customers along the Transco pipeline.
D. Rainbow and AMID Executed the MAG-0005
To obtain this additional flexibility that would result from a balancing
agreement with AMID, Tim Moreino with Rainbow negotiated with George
Matthews from AMID what the parties’ referred to in emails as an “FT [Firm
Transportation] Balancing Agreement.” Matthews emailed Rainbow with the
summation of their negotiations, writing that the agreement included a provision to
“[l]imit the number of days going short to Transco in the beginning of the month to
no more than 4 days at 20,000/day,” and that the “[m]aximum long/short on any
given day is 20,000 MMBtu.” Matthews further stated that, “if Transco ever says
nominations and physical flow don’t match and they need to, parties [must] take
corrective action to make them match.” He likewise agreed that “the agreement is
FT [Firm Transportation] but if our hand is forced it can be curtailed.”
AMID and Rainbow formalized this agreement and executed the MAG-0005
in 2015. The MAG-0005 provided that Rainbow could “transport” up to 20,000
10
MMBtu of natural gas each day on the Magnolia pipeline. The MAG-0005
identified the Magnolia-Transco Interconnect as both the primary receipt point and
the delivery point.
Significantly, the MAG-0005 relieved Rainbow of the obligation to balance
its receipts and deliveries on a daily basis under certain circumstances, thus
providing what the parties described as “balancing services” or “park and loan”
services. This meant that, subject to some limitations, Rainbow could make a daily
delivery nomination of up to 20,000 MMBtu without a corresponding receipt
nomination, and vice-versa, as long as all of its deliveries and receipts reconciled
or balanced at the end of the month.
The dispute between Rainbow and AMID focused on these balancing
services. Section 9.1 of the MAG-0005 provided relevant details:
Receipts and Deliveries of Gas. Except as otherwise provided for
herein, for the purposes of Section 8 of the SOC,2 Shipper [Rainbow]
shall not be obligated to balance receipts and deliveries of gas on a
daily basis unless, on or for any Day, either Transporter [AMID] or
Shipper is requested or required by an upstream or downstream party
to balance receipts and deliveries of gas attributable to Shipper. If
Transporter is requested or required by an upstream or downstream
party to balance receipts or deliveries of gas that are attributable to
Shipper, Transporter may cease receiving gas from or delivering gas
to or for Shipper until the upstream or downstream party no longer
2
“SOC” referred to the statement of terms and conditions incorporated by reference
for firm transportation on AMID’s system. FERC requires that these terms be filed
with it. The SOC, among other things, specifies the priority for how AMID will
curtail service if necessary—“make up gas” first, the interruptible service, then
firm service.
11
requests or requires Transporter to balance receipts and deliveries of
Shipper’s gas.
Section 9.2 provided that any imbalances would be corrected on a monthly basis:
Monthly Balancing. Notwithstanding Section 9.1, Shipper will use its
best commercial efforts to balance receipts and deliveries of gas on a
monthly basis so that, at the end of any Month, Shipper has no gas
imbalances on Transporter’s System.
Section 9.3 further limited Rainbow’s nominations “during the first ten (10) Days
of a Month to no more than four (4) consecutive days during which, on any Day,
[Rainbow] has nominated receipts of gas into [AMID’s] system without
nominating Equivalent Quantities of gas out of [AMID’s] system.”
In return for Rainbow’s right to nominate up to 20,000 MMBtu of gas on
AMID’s Magnolia pipeline each day, Rainbow agreed to pay a “demand rate” of
$.014 per MMBtu of natural gas allowed under the contract regardless of the
amount of capacity it actually used. This translates to $2,800 per day or $1,022,000
per year.
The MAG-0005’s effective date was March 1, 2015. Tschider testified that,
prior to entering into new forward sales contracts that would rely, in part, on the
MAG-0005, Rainbow wanted to be sure that AMID would perform reliably.
Tschider stated that Rainbow did not want to enter into forward sales contracts
with customers without verifying that it would be able to meet demand because
Rainbow would otherwise be exposed to financial and reputational losses.
12
Rainbow’s expert, William Coorsh, likewise testified that, in terms of Rainbow’s
overall business strategy, the MAG-0005 contract was intended to serve as a sort
of “insurance policy,” providing additional options for increasing its supply to its
customers, particularly on days of high demand. Coorsh stated that the MAG-0005
could only be useful if AMID’s performance was reliable because the “ultimate
risk” in entering into forward sales is “the inability to perform.” Thus, Rainbow
needed to address the issue of supply certainty.
Rainbow began to use the MAG-0005 to make daily trades, rather than
immediately expanding its forward sales commitments. However, during the first
winter that the MAG-0005 was in effect, AMID limited service to Rainbow under
the contract.
On January 8, 2016, AMID advised Rainbow to limit imbalances more
strictly than was required by the terms of the MAG-0005. AMID limited
Rainbow’s nomination for January 11, 2016, telling it not to pull more than 1319
MMBtu of gas on January 11 because an Operational Flow Order (OFO) from
Transco was in effect. AMID later advised Rainbow that the OFO did not affect
Rainbow’s ability to use the MAG-0005, but because of the timing of these
communications, Rainbow lost the opportunity to use the MAG-0005 to support its
daily trades. Rainbow nominated only 1,116 MMBtu of gas for January 11. AMID
confirmed that reduced nomination in full.
13
On January 22, 2016, AMID again told Rainbow it could not use the MAG-
0005 to pull any gas on January 23 and 24. Rainbow was otherwise able to use the
MAG-0005 and made 17 more out-of-balance nominations in January 2016, which
were confirmed in full by AMID.
E. AMID is Subject to an Operational Balancing Agreement with Transco
AMID argued that, beginning in January 2016, its performance under the
MAG-0005 was impacted by its relationship with Transco. Interactions between
the Magnolia pipeline and the Transco pipeline are subject to an Operational
Balancing Agreement (OBA), in which the parties agreed to specific procedures
for balancing between nominated (or scheduled) levels of service and actual
quantities moving through the Transco pipeline from the identified delivery and
receipt points. The OBA obligates AMID, as the OBA party, to resolve imbalances
created at the Magnolia-Transco interconnect. These imbalances arise due to
differences in quantities of natural gas scheduled through the interconnect and the
gas actually measured as delivered at the interconnect.
Relevant here, the OBA provides:
The Parties intend that the quantity of gas actually delivered and
received each day at each Location will equal the Scheduled
Quantities for that Location. All Scheduled Quantities at each
Location will be deemed to have been received and/or delivered under
the applicable shipper agreements. Any imbalance created, when the
actual physical flow is different than the Scheduled Quantities, will be
the “Operational Imbalance,” which will be the responsibility of the
Parties to eliminate pursuant to this Agreement.
14
There is only one “Location” identified in the OBA—the Transco-Magnolia
Interconnect. The OBA further provided that “Operational Imbalances shall be
resolved” pursuant to the provisions of the Transco’s FERC Gas Tariff, “provided
that the final resolution of the OBA Imbalance shall be determined pursuant to
Exhibit 2 hereto.”
Section 16(b) of the OBA provides that Transco could limit imbalances at
the Magnolia-Transco interconnect if (1) imbalances exceeded 5% of total
nominations at the interconnect and (2) those imbalances created operational
concerns. Exhibit 2 contained specific provisions for resolving operational
imbalances depending upon whether the operational imbalance was within or
exceeded the 5% cumulative limit.
Transco’s FERC Gas Tariff, specifying the general rules and rates for
service, provided that, because the interconnect of the Transco and Magnolia
pipelines was subject to an OBA, that document governed the transactions between
the two pipelines. The tariff further provides that Transco can issue Operational
Flow Orders, or OFOs. An OFO is a notice issued by the pipeline requiring
shippers to balance their gas supply with their customers’ usage or risk incurring
noncompliance charges. OFOs help a pipeline protect the operational integrity of
the pipeline by restricting service or requiring affirmative action by the shipper to
address imbalances or other operational concerns. Transco’s FERC tariff provides:
15
In order to alleviate operating conditions which may threaten the
integrity of [Transco’s] pipeline system, it may be necessary for
[Transco] to issue Operational Flow Orders (OFOs) to effectuate
adjustments in Buyer’s daily receipts or deliveries over a reasonable
period of time to maintain a current or cumulative balance between
Buyer’s receipts and deliveries in accordance with the terms of
Seller’s transportation rate schedules (Imbalance OFO), or to ensure
that gas quantities are received and delivered by Buyer where
scheduled (Scheduling OFO). Before issuing an OFO, Seller will
attempt to remedy those operating conditions through requests for
voluntary action provided, however, exigent circumstances may exist
which require immediate issuance of an OFO.
AMID presented evidence that, starting in January 2016, Transco began
policing imbalances at the Magnolia-Transco interconnect more strictly than it had
been in previous years. AMID showed that the number of OFOs issued by Transco
increased after it executed the MAG-0005, from four OFOs in the last half of 2015
to twenty in 2017. These OFOs, which AMID introduced into evidence at trial,
were “Imbalance OFOs.” The OFOs also had a line for designating whether “OBA
parties”—parties like AMID, which had an OBA with Transco—were subject to a
particular OFO. All of the OFOs introduced into evidence stated that OBA parties
like AMID were not subject to the OFO. Furthermore, neither AMID nor Rainbow
was named in any of the OFOs or otherwise directed to take action.
Additionally, Rainbow had its own agreement with Transco—a pooling
agreement that required Rainbow to balance its receipts and deliveries on Transco.
16
F. Rainbow and AMID Performed Under the MAG-0005
Based on the two refusals of service by AMID on January 8 and January 22,
2016, Rainbow decided not to enter into any monthly contracts for February or
March 2016. It continued to use the MAG-0005 to support daily trades while the
parties worked out the details of performing under the MAG-0005 in light of
AMID’s obligations under its OBA with Transco.
On February 11, 2016, despite having previously confirmed a nomination to
pull gas using the MAG-0005, AMID curtailed one of Rainbow’s nominations,
cutting Rainbow’s nomination to zero. AMID presented evidence that Transco
again had an OFO in place, but that flow order stated that parties with an OBA in
place, parties like AMID, were not subject to the order. AMID also presented
evidence that the Southcross pipeline was experiencing issues. Rainbow presented
evidence that, following this February 11 curtailment, it lost money because it had
to purchase gas at significantly higher prices to satisfy its obligations to its
customers for that day.
This difficulty prompted Tim Moreino with Rainbow to discuss the situation
with George Matthews, AMID’s director of producer services who had negotiated
the MAG-0005 on AMID’s behalf. In a phone call on February 18, 2016,
Matthews acknowledged that AMID had “screwed up” by curtailing Rainbow’s
February 11 nomination, but he stated that AMID hoped to improve its
17
performance going forward. Moreino asked whether AMID had set up a formal
“park and loan” rate with FERC, and Matthews said no. Matthews explained,
“[W]e do these kind of things like we do with you guys on the balancing deal . . .
as buy/sells, typically. But we also refer to them oftentimes internally as park and
loans. Even though that’s not really what they are.” Matthews stated that, rather
than a formal park and loan service, AMID intended to meet its balancing
obligations to Rainbow by “swinging and balancing on OBAs.”
Moreino pointed out the problems with AMID’s curtailment of its
nomination and asked Matthews about the future of the balancing agreement now
that Transco was “paying more attention to the flows and the OBAs.” Matthews
responded that AMID cut Rainbow’s nomination after they tried to reduce other
ways but were “still out of whack and [Transco] pushed,” resulting in AMID
curtailing the entirety of Rainbow’s nomination that day. Matthews told Moreino
that this was done because “[w]e don’t want the attention, we don’t want the
scrutiny [from Transco].” Matthews told Moreino that Transco “effectively
threatened . . . to put an OFO in for our point [and] we don’t want that.”
Ultimately, Matthews indicated that “everything is fine” and that the curtailment in
February “was an anomaly.” Matthews stated that AMID was working toward
building better relationships with the people at Transco.
18
Tschider likewise testified that, following the problems in the winter of
2016, his team from Rainbow met with Matthews from AMID. Similar to
Moreino’s testimony, Tschider testified that Rainbow told AMID, “You guys are
treating this as an interruptible contract and that’s not what we signed up for. The
contract is a forward balancing contract.” According to Tschider, Matthews
informed Rainbow that AMID would “correct this” and “make it right.” Matthews
also testified that AMID always intended to provide the services it committed to in
the MAG-0005 “[t]hrough a combination of history, historical imbalances that
[AMID] had successfully run across the Transco interconnect and through the
OBA.” Matthews agreed that AMID could have satisfied its obligations to
Rainbow through other methods like buying or selling additional gas from third
parties, but AMID never considered doing so.
Messages exchanged between schedulers at AMID and Rainbow indicated
that the parties continued interacting and that Rainbow made nominations under
the MAG-0005 through the summer of 2016. Rainbow did not always use its full
20,000 MMBtu capacity, consistent with Rainbow’s intention to use the MAG-
0005 as an “insurance policy” or additional tool to secure the supply needed for its
customers.
Nevertheless, Rainbow identified eight occasions on which AMID’s
scheduler, Ed Formell, told Rainbow its full 20,000 MMBtu was not available. For
19
example, on May 13, 2016, Rainbow’s scheduler asked AMID, “[F]or the weekend
can we put in 15k / day from Transco[?]” Formell responded, “No, 10 is about the
max I can take into me right now.” Tschider testified that, because Rainbow was
not able to use the full 20,000 MMBtu reliably through the summer of 2016,
Rainbow could not commit to the additional forward sales contracts that it had
anticipated when executing the MAG-0005. Rainbow used the MAG-0005 to
support daily trade only.
In the fall of 2016, AMID again told Rainbow to limit imbalances on three
occasions: (1) on November 22, 2016, AMID notified Rainbow that balancing
services available were limited to 15,000 MMBtu; (2) on December 6, 2016,
Transco issued a critical operations alert, and AMID notified Rainbow that its
nomination could be no more than 3,000 MMBtu out of balance, resulting in
Rainbow making no nomination at all for December 7, 2016; and (3) on December
15, 2016, when Transco issued an OFO and AMID notified Rainbow that it could
use only 10,000 MMBtu of balancing services, resulting in Rainbow submitting a
nomination for 3,466 MMBtu of out-of-balance capacity the next day, which
AMID confirmed in full. Rainbow submitted 29 other out-of-balance nominations
that winter, all of which were confirmed in full.
To address the ongoing concerns regarding AMID’s inconsistent
performance, Rainbow arranged another phone call on December 7, 2016, for the
20
parties to discuss the effect of Transco’s ongoing restrictions on their continued
performance under the MAG-0005. During this call, AMID’s Patricia De La Rosa,
who supervised scheduling on the Magnolia pipeline, stated that Transco “started
to call [AMID] out” more frequently and that AMID “would like to keep our
imbalance under the radar with Transco, as much as possible.” She expressed a
belief that AMID “still had some flexibility” under the terms of its OBA with
Transco, but that “[t]he quantity on any given day is what’s going to really be a bit
more, you know, stringent.” Formell further stated, “To be honest, . . . 20,000
probably isn’t going to be the number anymore.” De La Rosa stated during this
phone call that the MAG-0005 was interruptible, rather than firm, and that
Rainbow could not use the full Maximum Daily Quantity identified in the MAG-
0005 on three consecutive days.
Rainbow continued to negotiate with AMID regarding the performance
according to the terms of the MAG-0005, identifying its concern as being that its
scheduler “has not been able to utilize all 20,000dth on called days, the volume has
been 10,000dth.”3 A series of communications indicated that the parties were
attempting to agree to some amendments that would allow the parties to continue
performing. Rainbow made its last nominations in January 2017 while these
negotiations were ongoing.
3
MMBtu is roughly equivalent to a decatherm (dth), and both are used
interchangeably by the parties as measure of units of natural gas.
21
No resolution occurred, however, and on February 1, 2017, Rainbow Energy
sent notice to AMID that it was terminating the MAG-0005. It ceased making its
monthly demand payments and did not make any additional nominations under the
MAG-0005.
G. Rainbow Presented its Damages Model
In addition to the above evidence relevant to its breach of contract and fraud
claims, Rainbow presented evidence of the damages it sustained because of
AMID’s unreliable performance under the MAG-0005. Rainbow supported its
damages evidence with testimony from Stacy Tschider, damages expert William
Coorsh, and Rainbow employee Richard Phelan, among other evidence.
Rainbow asserted that, but for AMID’s failure to treat the MAG-0005 as a
firm contract, it would have used the MAG-0005 as a tool to make additional sales
to its customers. Thus, AMID’s failure to perform resulted in lost profits to
Rainbow. Specifically, Rainbow presented evidence that, if AMID had performed
reliably, as if the MAG-0005 were firm, it would have made larger daily trades in
January 2016 and then would have entered into larger or additional forward sales
contracts to its already-existing customers. It would have used the MAG-0005 for
the term of the contract as a source of gas on days of high pricing.
Both Tschider and Coorsh testified that Rainbow agreed to the terms of the
MAG-0005, including the demand charges of $2,800 per day regardless of
22
Rainbow’s actual usage, because it would provide Rainbow with the capacity to
reliably enter additional or larger forward sales contract with Rainbow’s
established customers. Coorsh in particular testified that the value of the MAG-
0005 was as an “insurance policy”—firm capacity that Rainbow would have
available when needed to meet obligations to its customers—rather than for daily
use. Coorsh stated that “the more conservative approach to take” with a firm
contract like the MAG-0005 was to enter into forward-sales contracts to sell the
gas, rather than using it for daily trades, because “the cash flow is certain, the
volumes to be delivered are certain.” Coorsh testified that the certainty of supply at
the Magnolia-Transco interconnect provided for in the MAG-0005 should have
given Rainbow the additional tools it needed to increase its forward sales.
Tschider, Coorsh, and Phelan all testified that reliability of performance was
the key feature that both Rainbow and its customers relied upon. If AMID did not
perform reliably, Rainbow could not enter into forward sales contracts by
depending on the supply that the MAG-0005 was intended to provide. Coorsh
testified that a contract that was negotiated to be firm but was treated as
interruptible presented a very risky situation in which Rainbow would be exposed
to the inability to deliver the agreed-upon quantities of gas to its own customers,
which put it at risk for financial losses and reputational damage.
23
Thus, Coorsh and others testified that Rainbow’s damages resulted, not from
any one day on which AMID failed to provide service, but from AMID’s failure to
treat the MAG-0005 as a firm contract. Coorsh stated that the commercial effect of
AMID’s curtailment of Rainbow’s nominations was “devastating” because “[i]t
shows doubt.” The problems that could arise for Rainbow if AMID failed to
perform after Rainbow had already entered into firm, forward sales agreements
included “reputation damage, financial consequences, in an extremely high-priced
environment, perhaps financial bankruptcy.” Coorsh stated, “[I]f there is doubt, the
whole strategy falls apart.”
Coorsh testified that it was reasonable for Rainbow to look to the totality of
AMID’s performance, or lack thereof, under the MAG-0005 in determining its
damages. He stated that a company like Rainbow would not make major decisions
about contracts and business strategies focusing “on just one thing.” It would,
instead, focus on its knowledge of the marketplace and its customers, where and
how it would supply gas to those customers and “a multitude of other things.” He
stated, “To isolate it to particular days and say that this is what the damages are
under the totality of the contract just isn’t right. The totality of the damages are
based on what [Rainbow] could have done over the entire term.”
Coorsh and Tschider both testified that AMID’s breaches destroyed the
benefit of the bargain in its entirety. Rainbow already had the MAG-0001 for
24
transportation services, and it entered into the MAG-0005 balancing agreement so
that it could increase the reliability of its supply so that it could increase its forward
sales. If Rainbow could not get the firm service at the quantity agreed to, then it
could not get the benefit of the MAG-0005.
The damages model presented by Rainbow set out in detail the sales that
Rainbow would have made if it could have used the MAG-0005 as negotiated. The
figures for quantities of gas sold and for the anticipated revenue and costs were
based on real transactions for revenue, business with its current customers, and
representations for potential business that it lost as a benefit of the bargain due to
AMID’s breach of the MAG-0005. It used publicly-reported index prices to
establish the prices of gas and other costs during the months for which it claimed
lost profits, spanning over the winter months from 2016 to 2018.
Coorsh explained that Rainbow’s damages model determined the lost
revenue components using “actual forward transactions that were executed by
Rainbow” in conjunction with the MAG-0001 contract. Coorsh testified that,
despite the forward sales executed based on the MAG-0001, Rainbow “had more
demand from buyers than [it] could satisfy” and it “very clearly . . . had the ability
to enter into other forward sales” at the same average price as the actually executed
sales under the MAG-0001. Phelan likewise testified about Rainbow’s business
involvement with companies like Macquarie Energy LLC, Shell Energy North
25
America, and Duke Energy. Phelan testified, for example, that when Rainbow
negotiated its contracts between November 2016 and March 2017, Duke was
looking for quantities between 10,000 and 20,000, but Rainbow only had the firm
capacity to guarantee 7,500. Duke “needed to lock in their winter supply during the
summer,” so Duke agreed to the reduced amount with Rainbow and looked to
other suppliers to meet its remaining gas supply needs for “[t]heir power plant [in]
Transco Zone 5.” Tschider also testified regarding additional demand that Rainbow
could have met using forward sales.
Using the month of November 2016 as an example, Coorsh explained the
details of Rainbow’s damages model. He testified that the average forward sales
price “in conjunction with sales associated with the MAG-0001 was approximately
$1.416, maybe $1.42, something like that. And in the model, they conservatively
used $1.40 [as the average value for the sales that were lost under the MAG-
0005].” Coorsh further explained the method used for determining the cost side of
the model. He stated that the index prices that were used on the cost side of the
model came from “Platts Gas Daily prices” that reflected the actual transactional
prices in contracts that Rainbow would have been able to enter into with
counterparties to buy gas to supply to its customers. Coorsh testified that “[t]he
publisher [of the Platts Gas Daily] surveys the market. They have transparency into
the market and they survey deals that are done at fixed prices and subsequently
26
publish their index.” The model calculated the cost that Rainbow would have
incurred to satisfy its forward contracts by determining what Rainbow would have
paid in the daily market. Other related expenses, such as fuel, usage, and transport
costs were based on established measures such as Transco’s tariff or actual deals
that Rainbow had been able to execute using other assets like the MAG-0001.
Rainbow then determined the expected profits by subtracting the costs from the
revenues.
Coorsh testified that the damages model was “conservative” in selecting the
rates it used to calculate expected revenue and costs. The model was also
conservative in that it sought lost profits only for the winter months (January-
March and November-December of 2016 and 2017, and January through March of
2018). Coorsh further testified that the model “takes into account what I would call
mitigated damages, what actually happened. And secondly, it takes into account
the demand charge that was due to Magnolia.” The damages model accounted for
the profits that Rainbow was able to realize using the MAG-0005 to make daily
trades. The damages model thus included Rainbow’s actual revenues based on, in
Coorsh’s words, “making the best of a bad situation.”
Phelan also testified that Rainbow accounted for the demand charges as part
of its costs. Phelan stated that Rainbow was not seeking return of the demand
charges paid in 2015. Instead, Rainbow took the demand charges “post the breach
27
all the way to the last payment that [Rainbow] made” and included that expense in
the damages model “showing what [Rainbow] would have actually paid for that
product had we had it.” Then, in determining the total damages, Rainbow included
a “credit for demand charges paid post-breach” of $996,800. The total damages
provided for in Rainbow’s damages model were $6,686,143.79.
H. Trial Court Found in Favor of Rainbow and Signed the Final Judgment
The trial court found that the MAG-005 “concerns firm balancing services
AMID would provide to Rainbow on AMID’s Magnolia System.” The trial court
outlined the material terms:
(a) AMID would provide Rainbow with a firm balancing service of up
to 20,000 MMBtu/day—meaning Rainbow could make a delivery
nomination of up to 20,000 MMBtu each day without a corresponding
receipt nomination and vice-versa, allowing Rainbow to “pull” gas
(have gas deemed delivered into Transco at the Magnolia-Transco
Interconnect) or “park” gas (have gas deemed delivered into Magnolia
at the Magnolia-Transco Interconnect);
(b) Rainbow was required to balance receipts and deliveries only on a
monthly basis;
(c) Rainbow could not use the MAG-0005 to park gas or pull gas on
four consecutive days in the first ten days of each month;
(d) Rainbow could not use the MAG-0005 in such a way that it
created an imbalance between receipts and deliveries on Transco (or
Southcross) and Transco (or Southcross) requested or required
Rainbow and/or AMID to not create such an imbalance;
(e) AMID was excused from performing if Transco (or Southcross)
requested or required AMID to balance physical flow and scheduled
28
receipts or deliveries at the Magnolia-Transco (or Southcross-
Magnolia) Interconnect; and
(f) Rainbow was required to pay demand charges to AMID in the
amount of $2,800/day.
The trial court further found that as a result of the December 7, 2016
conference call—during which Patricia De La Rosa, AMID’s scheduling
supervisor, told Rainbow that it could not pull 20,000 MMBtu over three
consecutive days, that the MAG-0005 was interruptible, and that AMID needed to
limit service to Rainbow in order to “stay under the radar” with Transco—
Rainbow “could not reasonably rely upon the MAG-0005 as a reliable source of
natural gas.” Rainbow informed AMID on December 21, 2016, via email between
Tim Moreino and George Matthews, that AMID had failed to provide the promised
20,000 MMBtu of gas, in breach of the MAG-0005. Rainbow ceased performance
after January 13, 2017, and on February 1, 2017, Rainbow sent AMID a letter
terminating the MAG-0005. The trial court concluded that De La Rosa’s
statements on December 7 constituted a repudiation by AMID that Rainbow
accepted “by providing notice of default on December 21, 2016, ceasing service
after January 13, 2017, and terminating the MAG-0005 on February 1, 2017.”
Relevant to damages, the trial court found that “[i]t was foreseeable to
AMID that Rainbow would use the MAG-0005 to supply forward contracts with
its customers after Rainbow was able to confirm the reliability of the MAG-0005”
29
and that “Rainbow would not be able to use the MAG-0005 to supply forward
contracts if it was not reliable on days that Rainbow tested the MAG-0005.” The
trial court concluded that “AMID’s refusals to provide service constituted a
material breach of MAG-0005 and effectively made the firm balance service
interruptible, destroying the benefit of the bargain for Rainbow.” The trial court
further concluded that “AMID’s material breach proximately and foreseeably
damaged Rainbow by making it impossible for Rainbow to reliably enter into
forward sales with customers—under which Rainbow would have earned profits.”
The trial court concluded that “Rainbow mitigated its damages by not entering into
forward sales contract with its customers using MAG-0005” because Rainbow
“would have suffered lost profits, cover costs, and reputational damage” had it
entered into contracts and AMID failed to perform. “Rainbow also mitigated its
damages by entering into daily trades using balancing services provided by MAG-
0005 on days that it was able to confirm that balancing services were available.”
The trial court found that Rainbow’s damages model accurately accounted
for all costs and net profits that Rainbow would have realized had AMID
performed. It concluded, “Rainbow’s damages, as reflected in the Damages Model
were a natural, probable, and foreseeable result of AMID’s breach and of AMID’s
fraud. Such damages were foreseeable to AMID at the time the parties entered
MAG-0005 as the probable, natural result of its breach.”
30
Rainbow moved for entry of judgment, and AMID sought amended and
additional findings of fact and conclusions of law. These motions were heard by
the trial court on August 23, 2019. Regarding construing the MAG-0005, the trial
court stated: “I considered your experts. I considered the OBA. I considered the
FERC tariff. I considered all of these things that sort of created the foundation for
which MAG-0005 was entered.”
After this hearing, the trial court signed an amended conclusion of law that
set forth its interpretation of MAG-0005 Section 9.1. In its amended findings and
conclusions, the trial court stated,
In construing Section 9.1, the Court considered the entirety of the
MAG-0005 Agreement and objective evidence of the surrounding
facts and circumstances (including the OBA and Transco’s FERC
tariff) as an aid in the construction of the MAG-0005, and determined
that this was the only reasonable interpretation of Section 9.1. The
Court considered evidence of industry custom and usage, which was
supportive of the unambiguous meaning of the MAG-005, but did not
add to, delete from, or change the plain text of the MAG-0005 based
on such evidence.
The trial court also provided additional clarification regarding attorney’s fees,
stating that it would not award them to Rainbow because of AMID’s status as a
limited liability company .
The trial court rendered its Modified Final Judgment on November 22, 2019.
It awarded Rainbow $6,145,215.89 in “actual benefit-of-the-bargain damages for
Rainbow’s lost profits,” $449,097.42 in prejudgment interest, plus costs and post-
31
judgment interest. The trial court further ordered that AMID take nothing on its
counterclaim for breach of contract.
Standard of Review
In its first two issues, AMID argues that the evidence is insufficient to
support the trial court’s judgment. In an appeal from a bench trial, we review legal-
sufficiency challenges to the trial court’s findings of fact under the same standards
that are applied to review the evidence supporting a jury’s verdict. BMC Software
Belg., N.V. v. Marchand, 83 S.W.3d 789, 794 (Tex. 2002). Where, as here, the trial
court issued findings of fact and conclusions of law, the trial court’s findings of
fact have the same weight as a jury verdict. Merry Homes, Inc. v. Luu, 312 S.W.3d
938, 943 (Tex. App.—Houston [1st Dist.] 2010, no pet.).
An appellant who attacks the legal sufficiency of an adverse finding on an
issue on which he did not have the burden of proof must demonstrate on appeal
that no evidence supports the adverse finding. Exxon Corp. v. Emerald Oil & Gas,
Co., L.C., 348 S.W.3d 194, 215 (Tex. 2011). We consider the evidence in the light
most favorable to the challenged finding, crediting favorable evidence if a
reasonable fact finder could and disregarding contrary evidence unless a
reasonable fact finder could not. City of Keller v. Wilson, 168 S.W.3d 802, 822
(Tex. 2005). We will sustain a no-evidence challenge if the record shows: (1) a
complete absence of evidence of a vital fact, (2) the court is barred by the rules of
32
law or evidence from giving weight to the only evidence offered to prove a vital
fact, (3) the evidence offered to prove a vital fact is no more than a mere scintilla,
or (4) the evidence conclusively establishes the opposite of a vital fact. Id. at 810.
In reviewing the factual sufficiency of the evidence, we consider all of the
evidence in the record in a neutral light and set aside the fact findings only if it
they so contrary to the overwhelming weight of the evidence as to be clearly wrong
and unjust. See Cain v. Bain, 709 S.W.2d 175, 176 (Tex. 1986). When an appellant
challenges an adverse finding on an issue on which it did not have the burden of
proof at trial, we set aside the verdict only if the evidence supporting the finding is
so weak as to make the verdict clearly wrong and manifestly unjust. See id.;
Reliant Energy Servs., Inc. v. Cotton Valley Compression, L.L.C., 336 S.W.3d 764,
782 (Tex. App.—Houston [1st Dist.] 2011, no pet.).
We are mindful that the trial court, as fact finder, was the sole judge of the
credibility of the witnesses and the weight to be given their testimony. See City of
Keller, 168 S.W.3d at 819; McKeehan v. Wilmington Sav. Fund Soc’y, FSB, 554
S.W.3d 692, 698 (Tex. App.—Houston [1st Dist.] 2018, no pet.). The trial court
may choose to believe one witness and disbelieve another. See City of Keller, 168
S.W.3d at 819. It is the fact finder’s role to resolve conflicts in the evidence, and
we may not substitute our judgment for that of the fact finder. McKeehan, 554
S.W.3d at 698.
33
Breach of Contract
In its second issue, AMID contends that Rainbow’s breach of contract and
repudiation claim fails as a matter of law. AMID argues that, if the parties’ MAG-
0005 contract is applied as written, there is legally and factually insufficient
evidence that AMID breached or repudiated the contract. AMID also argues that it
was excused from performing after Rainbow elected to continue the contract
despite the purported breaches, but then changed its mind, terminated the contract,
and ceased its monthly payments.
A. Relevant Law
In construing a contract, we must give effect to the parties’ intentions, as
expressed in their agreement. Barrow-Shaver Res. Co. v. Carrizo Oil & Gas, Inc.,
590 S.W.3d 471, 479 (Tex. 2019). We look to the language of the parties’
agreement and give a contract’s language its plain, grammatical meaning unless it
“would clearly defeat the parties’ intentions.” Id. (quoting Anadarko Petroleum
Corp. v. Thompson, 94 S.W.3d 550, 554 (Tex. 2002)). “We construe contracts
under a de novo standard of review.” Id.
B. Construction of Section 9.1
Section 9.1 provides:
[Rainbow Energy] shall not be obligated to balance receipts and
deliveries of gas on a daily basis unless, on or for any Day, either
[AMID] or [Rainbow] is requested or required by an upstream or
downstream party to balance receipts and deliveries of gas attributable
34
to [Rainbow]. If [AMID] is requested or required by an upstream or
downstream party to balance receipts or deliveries of gas that are
attributable to [Rainbow], [AMID] may cease receiving gas from or
delivering gas to or for [Rainbow] until the upstream or downstream
party no longer requests or requires Transporter [AMID] to balance
receipts and deliveries of [Rainbow’s] gas.
The trial court adopted Rainbow’s interpretation of Section 9.1, making the
following conclusion of law regarding its construction:
It is unambiguous under Section 9.1 of the MAG-0005 that AMID
was excused from providing firm balancing service to Rainbow if and
only if Transco either (a) requested or required AMID to balance
scheduled quantities with physical deliveries of gas at the Magnolia-
Transco Interconnect where Rainbow’s use of the MAG-0005 created
an imbalance between scheduled quantities and physical deliveries at
that point; or (b) requested or required Rainbow or AMID to balance
Rainbow’s receipts and deliveries on Transco where use of the MAG-
0005 would create an imbalance between Rainbow’s scheduled
receipts and scheduled deliveries on Transco.
AMID argues that the trial court’s “many references to ‘scheduled receipts,’
‘scheduled deliveries’ and ‘physical deliveries’ do not appear in the plain text of
Section 9.1” and that the trial court erred “in adding its own extra-contractual,
narrow language to Section 9.1.”
The MAG-0005 allowed Rainbow to move up to 20,000 MMBtus of gas
into and out of the Magnolia pipeline through the Magnolia-Transco interconnect.
AMID agreed “to receive up to the MDQ [Aggregate Maximum Daily Quantity, or
20,000 MMBtus] of gas tendered at the Receipt Point [the Magnolia-Transco
Interconnect] and to transport and redeliver the Equivalent Quantity to the account
35
of [Rainbow] at the Delivery Point [also identified as the Magnolia-Transco
Interconnect] on a Firm basis.”
Section 9.1 provided that Rainbow was not obligated to balance the receipts
or deliveries, and it provided two exceptions to AMID’s performance of this term.
Section 9.1 stated that Rainbow did not need to balance receipts and deliveries on
the Magnolia pipeline on a daily basis unless an upstream party requested or
required balancing of “receipts and deliveries of gas attributable to [Rainbow].”
Section 9.1 further provided that AMID could “cease receiving gas from or
delivering gas to or for [Rainbow]” if AMID was requested or required by an
upstream party to “balance receipts or deliveries of gas that are attributable to
[Rainbow].”
AMID agrees that Section 9.1 is unambiguous, as the trial court found.
AMID argues, however, that the trial court erred in relying on extrinsic evidence to
insert “many nuanced distinctions into Section 9.1 regarding scheduling
imbalances and physical imbalances.” This argument, however, ignores the
entirety of the MAG-0005 and the language of Section 9.1.
In construing a contract, we strive to give effect to all the provisions of the
contract so that none will be rendered meaningless. El Paso Field Servs., L.P. v.
MasTec N. Am., Inc., 389 S.W.3d 802, 805, 808 (Tex. 2012). We construe phrases
and words “in conjunction with the specific rights and obligations contained in the
36
contract.” See id. at 808. Unless there is an indication that the parties intended to
give a word a technical or special meaning, we give the terms their “plain,
ordinary, and generally accepted meaning.” Id.
Section 9.1 sets out two clauses providing limitations on Rainbow’s right to
be out of balance on the Magnolia pipeline and AMID’s obligation to perform
under the MAG-0005. The first sentence of Section 9.1 provides that Rainbow was
not obligated to balance receipts and deliveries on a daily basis unless AMID or
Rainbow was requested or required by a party like Transco “to balance receipts
and deliveries of gas attributable to [Rainbow].” (Emphasis added.) The second
sentence further provides that if AMID is requested or required by a party like
Transco “to balance receipts or deliveries of gas that are attributable to
[Rainbow]”, then AMID can cease receiving or delivering gas from or to Rainbow.
(Emphasis added.)
We cannot read these two distinct clauses as excusing AMID from
performance under the MAG-0005 because a party like Transco had issued a
general OFO or general request. Rather, the requests or requirements from a party
like Transco were required to meet the express provisions in Section 9.1—that the
requests address the specific balancing concerns implicated by Section 9.1 and that
they be “attributable to” Rainbow.
37
Furthermore, the two sentences of Section 9.1 use different language to raise
two different balancing concerns. Sentence 1 of Section 9.1 references both AMID
and Rainbow and requires that the request from a party like Transco require
“balance[ing] receipts and deliveries of gas attributable to [Rainbow].” (Emphasis
added.) This necessarily implicates a point-to-point imbalance or scheduling
imbalance—an imbalance between receipts scheduled into the pipeline and
deliveries scheduled out of the pipeline. This comports with the trial court’s
construction that AMID was excused from performing if a party like Transco
“requested or required Rainbow or AMID to balance Rainbow’s receipts and
deliveries on Transco where use of the MAG-0005 would create an imbalance
between Rainbow’s scheduled receipts and scheduled deliveries on Transco.”
Sentence two of Section 9.1 sets out an additional provision. It states that
AMID could quit receiving gas from or delivering gas to or for Rainbow if a party
like Transco required it to balance “receipts or deliveries.” (Emphasis added.) This
implicates a single-point imbalance or operational imbalance—an imbalance
between the amount of gas scheduled to move through a point like the Transco-
Magnolia interconnect and the amount of gas actually measured at that point. This
comports with the trial court’s construction that AMID was excused from
performing if Transco “requested or required AMID to balance scheduled
quantities with physical deliveries of gas at the Magnolia-Transco Interconnect
38
where Rainbow’s use of the MAG-0005 created an imbalance between scheduled
quantities and physical deliveries at that point.”
American Midstream argues that the trial court erroneously considered
extrinsic evidence, such as the terms of the OBA and expert testimony, in
construing Section 9.1. We disagree. Based on the trial court’s findings, it does not
appear that the trial court improperly considered extrinsic evidence to construe
Section 9.1.
The parol evidence rule, which “applies to writings that evidence the
creation, modification, termination, or securing of a right or obligation under the
contract,” bars consideration of evidence that contradicts, varies, or adds to the
terms of an unambiguous written agreement. Barrow-Shaver Res., 590 S.W.3d at
483. Specifically, “[e]vidence of prior or contemporaneous agreements is
inadmissible as parol evidence when the contract is unambiguous.” Id. (citing ERI
Consulting Eng’rs, Inc. v. Swinnea, 318 S.W.3d 867, 875 (Tex. 2010)).
Nevertheless, “a court may still consider surrounding facts and
circumstances as an aid in the construction of the contract’s language.” Id. (quoting
First Bank v. Brumitt, 519 S.W.3d 95, 110 (Tex. 2017), internal quotation marks
omitted). While “evidence of circumstances can be used to ‘inform the contract
text and render it capable of only one meaning,’ extrinsic evidence can be
39
considered only to interpret an ambiguous writing, not to create ambiguity.” Id.;
see Kachina Pipeline Co. v. Lillis, 471 S.W.3d 445, 450 (Tex. 2015).
In Barrow-Shaver, the supreme court held that evidence of the parties’
substantive negotiations directly related to the creation of their unambiguous
contract and, thus, the parol evidence rule barred consideration of evidence of the
parties’ substantive negotiations. 590 S.W.3d at 483. The court went on to hold:
We can consider the surrounding circumstances, however, including
the fact that negotiations took place between sophisticated parties in
this commercial oil and gas context. See, e.g., [Kachina Pipeline, 471
S.W.3d at 450] (recognizing that a court may consider objective
factors of the facts and circumstances surrounding the context of the
parties’ contract, such as the setting in which the contract was
negotiated, commercial or otherwise (citation omitted)). In URI, Inc.
v. Kleberg County, we explained that:
the “facts and circumstances” extant at the time a contract is
executed may be consulted only to inform the meaning of the
language the parties chose to effectuate their accord. In construing
an unambiguous contract or in determining whether an ambiguity
exists, courts may not seek the parties’ intent beyond the meaning
the contract language reasonably yields when construed in
context.
543 S.W.3d at 763. “[S]urrounding facts and circumstances cannot be
employed to ‘make the language say what it unambiguously does not
say’ or ‘to show that the parties probably meant, or could have meant,
something other than what their agreement stated.’” Id. at 757
(citations omitted).
Id. at 483–84.
Given this precedent, we conclude that the trial court did not violate the
parol evidence rule in construing the MAG-0005. Nothing in the trial court’s
40
conclusion of law interpreting Section 9.1 indicated a reliance on anything beyond
the language used by the parties in Section 9.1 specifically and in the MAG-0005
generally. To the extent that the trial court used the surrounding facts and
circumstances—i.e., that the negotiation of the MAG-0005 occurred between
sophisticated parties knowledgeable in commercial natural gas transactions—to
inform its conclusions, there is no indication that those circumstance served to alter
the meaning of the words chosen by the parties in the MAG-0005. See id.
Rather, the two different clauses in Section 9.1 must be construed in a way
that gives effect to both without rendering any of the provisions meaningless. See
El Paso Field Servs., 389 S.W.3d at 808. The evidence that AMID complains of—
including AMID’s OBA with Transco, Transco’s FERC tariff, and expert
testimony regarding how these transactions actually occurred—does not alter the
meaning of the MAG-0005. The differences in meaning as construed above is
based on the language of the MAG-0005 itself.
C. Evidence Supporting the Finding of Breach of the MAG-0005
In light of the proper construction of the MAG-0005, we now consider the
sufficiency of the evidence supporting the trial court’s findings that AMID
breached the contract.
The trial court’s findings of fact identified seven specific days on which
AMID breached the MAG-0005. The trial court concluded that “AMID’s refusals
41
to provide service constituted a material breach of MAG-0005 and effectively
made the firm balancing service interruptible, destroying the benefit of the
bargain.” The trial court further concluded that “[t]here is no evidence of any
request or requirement meeting [the criteria set out in Section 9.1] that would
excuse AMID from performing or prevent Rainbow from using the MAG-0005.”
The trial court specified that “[n]o request or requirement from Transco was issued
excusing AMID from performing” and thus, “[t]here is no excuse for AMID’s
breach.”
AMID does not dispute that it limited or curtailed Rainbow’s nominations
under the MAG-0005 on the days identified by the trial court. It disagrees,
however, with the legal significance that the trial court ascribed to the curtailments.
AMID asserts that the breaches identified by the trial court in its findings “fall into
two overlapping categories: (1) days when there was an OFO or critical alert from
Transco, and (2) days when [AMID] advised Rainbow via instant message to
nominate less than 20,000 MMBtu of balancing services but did not curtail a
nomination.” AMID argues that the Transco’s OFOs and critical alerts “satisfied
the conditions in Section 9.1 of the MAG-0005 [excusing AMID from providing
balancing services] as a matter of law”:
[The OFOs] all were issued in Zone 4 where the Magnolia-Transco
interconnect is located. They all apply to every shipper on the Transco
pipeline, including Rainbow. And they all requested or required
shippers to limit imbalances. Therefore, as a matter of law, Rainbow
42
had no right to be out of balance under Section 9.1 of the MAG-0005
on any day an OFO or critical alert was in place.
Thus, AMID asserts that these incidents do not constitute breaches of the MAG-
0005 because AMID’s performance was excused under the contract’s terms.
The OFOs at issue here are imbalance OFOs that Transco issued to make
adjustments in daily receipts or deliveries on the Transco pipeline over the
specified period of time to maintain a current or cumulative balance between its
customer’s receipts and deliveries in accordance with the terms of Transco’s
transportation rate schedules. The OFOs directed shippers to limit imbalances on
the Transco pipeline between receipts and deliveries to specific levels. For
example, the OFO issued for January 10, 2016, provided for a “tolerance %
allowed” of 5%. The OFOs also identified the zone impacted, and they could
identify “affected shippers.”
Contrary to AMID’s argument, none of the OFOs reference gas attributable
to Rainbow as creating an imbalance on the Transco pipeline. Furthermore, the
OFOs at issue here stated that OBA parties, like AMID, were not subject to the
OFOs. Thus, AMID failed to present evidence that the OFOs excused its
performance under the MAG-0005. Rainbow presented evidence that it had a
pooling agreement with Transco that required Rainbow to always balance its
receipts and deliveries on the Transco pipeline and, as a result, its receipts and
deliveries on the pipeline were balanced. And AMID’s George Matthews testified
43
that, regardless of the OFOs, it was possible that AMID could have met its
obligations to Rainbow to allow it to be out of balance on the Magnolia pipeline
under the MAG-0005 through other means such as purchasing or selling gas from
other parties, but AMID did not consider doing so.
Thus, Rainbow presented evidence that these OFOs did not fall within
Section 9.1’s exceptions for AMID’s performance of the MAG-0005. The OFOs
and critical alerts identified by AMID did not apply to OBA parties, like AMID,
and Rainbow’s nominations would not have caused an imbalance on the Transco
pipeline. Rainbow established that AMID could have used “other available tools”
to fulfill the terms of the MAG-0005, such as purchasing gas from other shippers.
Instead, AMID limited Rainbow’s nominations. We conclude that the evidence
was, thus, legally sufficient to support the trial court’s breach findings. See
Emerald Oil & Gas, 348 S.W.3d at 215 (holding that appellant who attacks legal
sufficiency of finding on which it did not have burden of proof must demonstrate
that no evidence supports challenged finding).
AMID asserts that its “advice” that Rainbow limit nominations on
November 22, 2016, and during the summer of 2016 did not constitute a breach of
the MAG-0005 because it did not actually curtail any of Rainbow’s nominations
on those dates. AMID argues that, to demonstrate breach, Rainbow had to provide
44
evidence that it made a nomination that AMID curtailed.4 But this argument
disregards the contractual terms and the evidence of the parties’ conduct.
The communications from AMID to Rainbow informing Rainbow that there
was limited capacity and that Rainbow could not use its full 20,000 MMBtu in
services occurred while Rainbow was considering and preparing its nominations.
Evidence indicated that the communications could not be considered “advice” that
Rainbow could disregard. AMID’s scheduler in charge of the Magnolia pipeline
testified that shippers like Rainbow were expected to comply with his instructions.
And Rainbow’s president, Tschider, testified that Rainbow could not make
downstream deals to sell gas if it would not be able to obtain the supplies through
the MAG-0005. If Rainbow proceeded to make a nomination it had already been
told could not be confirmed, Rainbow would expose itself to additional loss and
difficulty in meeting its obligations to its own customers. Thus, Rainbow presented
evidence that when AMID told Rainbow that it could not make a full nomination
for a particular day, regardless of whether AMID limited its performance before or
4
Rainbow argues that submitting a nomination even after it was told via instant
message that the capacity was not available would have been “futile.” See, e.g.,
DiGiuseppe v. Lawler, 269 S.W.3d 588, 594–95 (Tex. 2008) (observing that Texas
law generally does not require performance of futile acts). AMID characterizes
this argument as “a theory of anticipatory breach,” and it argues that there is no
evidence of anticipatory breach because AMID’s statements to Rainbow did not
amount to a complete repudiation of the contract. As discussed above, the trial
court found that AMID’s conduct in this regard—telling Rainbow that it could not
make a nomination for the full 20,000 MMBtus on certain days—was itself a
breach of the contract’s terms.
45
after Rainbow made the official nomination, AMID breached the terms of the
MAG-0005.
Additionally, AMID’s argument that it did not breach the MAG-0005 when
in merely informed Rainbow that it could not use the full benefits (as opposed to
curtailing a nomination after Rainbow made it) does not comport with the
contractual obligations set out. AMID argues that there is no evidence that it
refused service on those days because Rainbow never made a nomination that was
actually refused by AMID. We observe, however, that the MAG-0005 obligated
Rainbow to pay the contractual demand charges, regardless of its actual usage of
the MAG-0005. In return, AMID agreed to firm—not interruptible—capacity of up
to 20,000 MMBtus per day for Rainbow to use at its discretion. Nothing in the
contract required Rainbow to make a full nomination for capacity that AMID had
already said was not available.
In breach of its obligations, AMID told Rainbow on multiple occasions that
it could not provide the full 20,000 MMBtu promised in the MAG-0005. As the
trial court concluded, there was no evidence of an OFO or other request that met
the criteria of Section 9.1 that would have excused AMID’s performance. These
repeated, unexcused failures to perform constituted a material breach of the MAG-
0005 by AMID and, as the trial court held, “effectively made the firm balancing
service interruptible.”
46
We conclude, after considering all the evidence in a neutral light, that the
trial court’s findings are not so contrary to the overwhelming weight of the
evidence as to be clearly wrong and unjust. See Cain, 709 S.W.2d at 176.
Accordingly, we conclude that the evidence is factually sufficient to support the
trial court’s findings of breach.
D. AMID’s Repudiation of the MAG-0005
Rainbow argues that, in addition to the specific refusals of service discussed
above indicating that AMID treated the MAG-0005 as an interruptible rather than
firm, AMID expressly repudiated the MAG-0005 in December 2016. The trial
court found that De La Rosa’s statements on AMID’s behalf during the December
7, 2016 call constituted a repudiation of the MAG-0005. AMID argues, however,
that the evidence is legally and factually insufficient to support the trial court’s
repudiation finding.
To constitute a repudiation, a party to a contract must have absolutely and
unconditionally refused to perform the contract without just excuse. El Paso Prod.
Co. v. Valence Operating Co., 112 S.W.3d 616, 621 (Tex. App.—Houston [1st
Dist.] 2003, pet. denied). Repudiation of a contract is a “positive and unconditional
refusal to perform the contract in the future,” evidenced by “conduct that shows a
fixed intention to abandon, renounce, and refuse to perform the contract.” CMA-
47
CGM (Am.), Inc. v. Empire Truck Lines, Inc., 416 S.W.3d 495, 519 (Tex. App.—
Houston [1st Dist.] 2013, pet. denied).
Prior to the December 7, 2016 phone call, Rainbow had expressed its
concerns that AMID was not performing as required by the MAG-0005 because
Rainbow had not been able to utilize the entire 20,000 MMBtu of capacity as
needed. During the phone call, De La Rosa and other representatives from AMID
expressly stated that AMID could not maintain the promised volume of 20,000
MMbtu because, realistically, AMID could only provide 10,000 MMBtu. De La
Rosa stated that Rainbow needed to understand that the MAG-0005 was
interruptible rather than firm, and AMID made it clear that these changes limiting
service to Rainbow under MAG-0005 were made so that AMID could “stay under
the radar” with Transco.
AMID argues, essentially, that these statements were not a repudiation of the
MAG-0005, but rather that the parties were discussing changes in the industry and
in Transco’s policies that had impacted the parties’ performance under the MAG-
0005. AMID asserts that the statements of De La Rosa and its other representatives
on the December 7 phone call were not an unequivocal, absolute refusal to perform
under the MAG-0005. It argues: “Neither De La Rosa, nor anyone else on the
December 7 call, stated that [AMID] would refuse to allow Rainbow to be out of
balance absent a request or requirement from Transco to stay in balance. And both
48
parties agreed to ‘huddle up’ to address Transco’s restrictions moving forward.”
But the transcript of the call itself supports the trial court’s determination that
AMID expressed that it was no longer able to perform the MAG-0005 as agreed.5
AMID also argues that Rainbow “elected to continue performance under the
MAG-0005 after each alleged breach and repudiation.” It asserts that Rainbow, as
the non-breaching party, could “choose either to treat the contract as terminated or
as continuing; it cannot do both,” citing Man Industry (India), Ltd. v. Midcontinent
Express Pipeline, LLC, 407 S.W.3d 342 (Tex. App.—Houston [14th Dist.] 2013,
pet. denied) (breach), and El Paso Production Co., 112 S.W.3d 616 (repudiation)
to support its contentions. AMID points to the fact that the parties did not cease
performance until January 13, 2017, “nearly six weeks after the alleged repudiation
and one month after the last alleged breach.” However, AMID’s cases supporting
its arguments about “seeking to benefit from the contract or insisting on continued
performance ‘operates as a conclusive choice,’ depriving the non-breaching party
of an excuse to terminate its own performance” are distinguishable. Both
Smithdale Court Inc. v. Keely, No. 01-92-00018-CV, 1993 WL 282922 (Tex.
5
AMID argues, “Even if there were some evidence of breach or repudiation, . . . [it]
was excused as a matter of law from performing after Rainbow wrongfully
terminated the MAG-0005 on February 1, 2017.” As we held above, the evidence
supported the trial court’s conclusion that AMID breached and ultimately
repudiated the MAG-0005. Thus, Rainbow’s termination of the contract was not
“wrongful.” And, as we discuss further below with regard to damages, AMID’s
breach and subsequent repudiation caused Rainbow lost profits for the term of the
MAG-0005 contract.
49
App.—Houston [1st Dist.] Jul. 29, 1993, no pet.) (not designated for publication)
and Levco Construction, Inc. v. Whole Foods Market Rocky Mountain/Southwest
L.P., 549 S.W.3d 618 (Tex. App.—Houston [1st Dist.] 2017, no pet.) involved
finite performance—a contract for sale of a home and a construction contract,
respectively. See Smithdale Ct. Inc., 1993 WL 282922, at *3; Levco Constr., 549
S.W.3d at 643, 645. They are not contracts, like the MAG-0005, that would be
performed as discrete transactions conducted on an on-going basis. The fact that
Rainbow continued to negotiate to see if it could retain the benefit of the MAG-
0005 agreement does not constitute an election to continue the contract. See Man
Indus., 407 S.W.3d at 368.
We conclude that the evidence is legally and factually sufficient to support
the trial court’s repudiation findings. See Emerald Oil & Gas, 348 S.W.3d at 215;
Cain, 709 S.W.2d at 176.
We overrule AMID’s second issue.
Damages
In its third issue, AMID argues that, even if we conclude that the trial court’s
liability findings stand, Rainbow Energy’s damages are nevertheless
unrecoverable.
50
A. Relevant Law
“The goal in measuring damages for a breach-of-contract claim is to provide
just compensation for any loss or damage actually sustained as a result of the
breach.” Parkway Dental Assocs., P.A. v. Ho & Huang Props., L.P., 391 S.W.3d
596, 607 (Tex. App.—Houston [14th Dist.] 2012, no pet.). Damages for breach of
contract may include both direct and consequential damages. Signature Indus.
Servs., LLC v. Int’l Paper Co., 638 S.W.3d 179, 186 (Tex. 2022). Direct damages
include restoring “the benefit of a plaintiff’s bargain.” Id. Consequential damages
“compensate the plaintiff for foreseeable losses that were caused by the breach but
were not a necessary consequence of it.” Id.
“The normal measure of damages in a breach-of-contract case is the
expectancy or benefit-of-the-bargain measure.” Parkway Dental, 391 S.W.3d at
607. The purpose of this measure of damages is to restore the injured party to the
economic position it would have occupied had the contract been performed. Id. at
607. “To restore an injured party to the position he would have been in had the
contract been performed, it must be determined what additions to the injured
party’s wealth have been prevented by the breach and what subtractions from his
wealth have been caused by it.” Sharifi v. Steen Auto., LLC, 370 S.W.3d 126, 148
(Tex. App.—Dallas 2012, no pet.) (citing Lafarge Corp. v. Wolff, Inc., 977 S.W.2d
181, 187 (Tex. App.—Austin 1998, pet. denied)). Benefit-of-the-bargain damages
51
include lost profits that are proved with reasonable certainty. See Phillips v.
Carlton Energy Grp., LLC, 475 S.W.3d 265, 278 (Tex. 2015); see also USPLS, LC
v. Gaas, No. 01-20-00604-CV, 2022 WL 3722135, at *8 (Tex. App.—Houston
[1st Dist.] Aug. 30, 2022, pet. filed) (mem. op.) (“Lost profits may be either direct
damages—profits lost on the contract itself—or consequential damages—profits
lost on other contracts resulting from the breach.”).
The Supreme Court of Texas has set out the rules concerning the sufficiency
of evidence of lost-profits damages:
Recovery for lost profits does not require that the loss be susceptible
of exact calculation. However, the injured party must do more than
show that [it] suffered some lost profits. The amount of the loss must
be shown by competent evidence with reasonable certainty. What
constitutes reasonably certain evidence of lost profits is a fact
intensive determination. As a minimum, opinions or estimates of lost
profits must be based on objective facts, figures, or data from which
the amount of lost profits can be ascertained. Although supporting
documentation may affect the weight of the evidence, it is not
necessary to produce in court the documents supporting the opinions
or estimates.
Horizon Health Corp. v. Acadia Healthcare Co., Inc., 520 S.W.3d 848, 859–60
(Tex. 2017) (quoting ERI Consulting Eng’rs, Inc. v. Swinnea, 318 S.W.3d 867, 876
(Tex. 2010)).
“Thus, lost profits damages can be recovered only when both the fact and
amount of damages is proved with reasonable certainty.” Id.; see Cash Am. Pawn,
LP v. Alonzo, No. 01-19-00801-CV, 2021 WL 4155795, at *8 (Tex. App.—
52
Houston [1st Dist.] Sept. 14, 2021, no pet.) (“Lost profits are damages for the loss
of net income to a business measured by reasonable certainty.”). The “general
rule” for obtaining recovery of lost profits as damages requires the party to
demonstrate that “a loss of profits is the natural and probable consequence of the
act or omission complained of” and establish the amount of lost profits “with
sufficient certainty.” Horizon Health Corp., 520 S.W.3d at 860 (quoting Tex.
Instruments, Inc. v. Teletron Energy Mgmt., Inc., 877 S.W.2d 276, 279 (Tex.
1994)); see Bowen v. Robinson, 227 S.W.3d 86, 96 (Tex. App.—Houston [1st
Dist.] 2006, pet. denied).
“Opinions or estimates are competent evidence of lost profits if based on
objective facts, figures, or data from which the amount of lost profits can be
ascertained.” Cash Pawn Am., 2021 WL 4155795, at *8; see Phillips, 475 S.W.3d
at 279; ERI Consulting Eng’rs, 318 S.W.3d at 876. However, “anticipated profits
cannot be recovered where they are dependent upon uncertain and changing
conditions, such as market fluctuations, or the chances of business, or where there
is no evidence from which they may be intelligently estimated.” Horizon Health
Corp., 520 S.W.3d at 860 (quoting Tex. Instruments, Inc., 877 S.W.2d at 279).
“The law is wisely skeptical of claims of lost profits from untested ventures or in
unpredictable circumstances, which in reality are little more than wishful
thinking.” Id. (quoting Phillips, 475 S.W.3d at 280). “When the evidence
53
supporting a claim for lost profits damages is largely speculative or a mere hope
for success, lost profits have not been established with reasonable certainty.” Id.
(citing Tex. Instruments, Inc., 877 S.W.2d at 279).
While the proper measure of damages is a question of law that we review de
novo, Signature Indus. Servs., 638 S.W.3d at 187, the question of what constitutes
reasonably certain evidence of lost profits is a fact intensive determination.
Phillips, 475 S.W.3d at 279. The fact finder generally has discretion to award
damages within the range of evidence presented at trial. Gulf States Utils. Co. v.
Low, 79 S.W.3d 561, 566 (Tex. 2002).
B. The Trial Court’s Damages Findings
The trial court found damages against AMID as follows: (1) $6,145,215.89
for lost profits as the benefit-of-the-bargain damages supported by breach of
contract and fraud findings; (2) $3,215,923.72 for benefit-of-the-bargain damages
related to AMID’s repudiation, measured by the alleged lost profits from forward
sales beginning in January 2017; or (3) $991,550.61 for out-of-pocket damages,
supported by breach of contract, fraud, repudiation, and negligent
misrepresentation findings, measured by the demand charges Rainbow paid under
the contract minus its net revenue. Rainbow Energy elected to recover its
$6,145,215.89 benefit-of-the-bargain damages, as measured by its lost profits, on
the breach of contract finding.
54
The trial court found that it “was foreseeable to AMID that Rainbow would
use the MAG-0005 to supply forward contracts with its customers after Rainbow
was able to confirm the reliability of the MAG-0005” and that “Rainbow would
not be able to use the MAG-0005 to supply forward contracts if it was not reliable
on days that Rainbow tested the MAG-0005.”
The trial court considered AMID’s refusal of services on January 8 and
January 22, 2016, and held, “Had AMID performed as promised in January 2016,
it is reasonably certain Rainbow would have entered into forward sales contracts
with its customers for February 2016 at a price of $4.069/MMBtu and for March
2016 at a price of $1.911/MMBtu (the NYMEX LDS for the month plus the
average basis reported by the Intercontinental Exchange).” The trial court further
found that Rainbow “suffered immediate damages” when AMID curtailed its
February 11, 2016 nomination and it was required to purchase more expensive gas
to satisfy its obligations to its customers. The trial court further found that AMID’s
“ongoing non-performance” caused Rainbow to determine that it “could not
reliably enter into any forward sales contracts for the 2016-2017 winter season
using the MAG-0005 without incurring substantial risks,” so it “used the MAG-
0005 to support daily trades only.” This was followed by AMID’s additional
failure to perform and the December 7 phone call in which De La Rosa stated that
the MAG-0005 would have to be viewed as interruptible going forward.
55
The trial court concluded that AMID’s conduct “effectively made the firm
balancing service interruptible, destroying the benefit of the bargain for Rainbow.”
This material breach “proximately and foreseeably damaged Rainbow by making it
impossible for Rainbow to reliably enter into forward sales with customers—under
which Rainbow would have earned profits.”
Looking at Rainbow’s damages model, the trial court concluded that it was
“reasonably certain that Rainbow would have realized lost profits had AMID
performed its obligations under the MAG-0005 Agreement” and that “Rainbow
would have realized the revenue reflected in the Damages Model with forward
sales contract with customers (for February-March 2016, November 2016-March
2017, and November 2017-March 2018) and increased daily trading in January
2018.” The trial court determined that the Damages Model accurately reflected
Rainbow’s actual net profits using the MAG-0005 and Rainbow’s expected net
profits that it would have realized had AMID performed according to the contract’s
terms.
Thus, the trial court determined that, to restore Rainbow to the economic
position that it would have occupied had AMID performed, the damages had to
account for the profits that Rainbow lost because it could not rely on the MAG-
0005 as a firm balancing agreement. These lost profits were calculated based on
the established demand of existing customers and revenue and costs based on
56
Rainbow’s own transactions under other agreements or index prices. The damages
model accounted for mitigated damages, considering that Rainbow used the MAG-
0005 to the extent that it could for daily trades.
AMID now argues that (1) there is insufficient evidence of the proper
measure of damages; (2) Rainbow’s lost-profits model rests on unfounded
assumptions; and (3) Rainbow failed to prove lost profits with reasonable certainty.
C. The Proper Measure of Rainbow’s Damages
AMID first argues that “there is legally and factually insufficient evidence of
the proper measure of damages.” AMID asserts that the “award of damages failed
to account for the value of the MAG-0005 as a transportation contract,” noting that
“[t]ransportation services are different than balancing services” and “the MAG-
0005 offered both.” AMID argues that by its plain language, the MAG-0005
provided transportation services and that the trial court could not rely on parol
testimony or Rainbow’s own performance to change the terms as written.
We observe, however, that Rainbow’s damages model is based on AMID’s
breach of its obligation to provide balancing services under the MAG-0005.
Establishing damages flowing from that breach is not a matter of contract
interpretation. In presenting evidence of its lost profits, Rainbow is not attempting
to change the terms of the contract in a way that would implicate the parol
evidence rule. See Barrow-Shaver Res., 590 S.W.3d at 483 (holding that parol
57
evidence rule “applies to writings that evidence the creation, modification,
termination, or securing of a right or obligation under the contract,” and bars
consideration of evidence that contradicts, varies, or adds to terms of unambiguous
written agreements). Rather, Rainbow proved that AMID’s breach of its obligation
to provide the balancing services bargained for in the MAG-0005 caused damages,
as required to establish its breach of contract claim. See, e.g., Davis v. Nat’l Lloyds
Ins. Co., 484 S.W.3d 459, 468 (Tex. App.—Houston [1st Dist.] 2015, pet. denied)
(providing that plaintiff’s damages resulting from breach is essential element of
breach of contract claim). Rainbow was not obligated to assert or establish a
breach of AMID’s obligation to provide transportation services under the MAG-
0005 to prove that Rainbow sustained damages because of AMID’s breach of the
balancing provision.
AMID further argues that, because Rainbow failed to present any evidence
of the value of the MAG-0005 as a transportation contract, there is legally
insufficient evidence to support the award of benefit-of-the-bargain or out-of-
pocket damages, citing Highland Capital Management L.P. v. Ryder Scott Co. See
402 S.W.3d 719, 726–30 (Tex. App.—Houston [1st Dist.] 2012, no pet.). The
contract and damages in Highland Capital are distinguishable from the damages
here. In that case, this Court reviewed a trial court’s grant of summary judgment
dismissing appellant Highland Capital’s claims for negligence and negligent
58
misrepresentation in part on the ground that the appellant presented no evidence as
to the fair market value of the defective bonds at the time of their purchase. Id. at
727–28. The Court in Highland Capital concluded that, because there was no
evidence of the value of what appellant received when it purchased the bonds,
there was no way to calculate the difference between what it bargained for and
what it actually received. Thus, there was no evidence to support its claim for
damages. Id. Here, the MAG-0005 is a different kind of contract. It was not a
contract for a one-time sale, but a contract to provide ongoing services and
evidence of the value received at the time the parties entered the MAG-0005 is not
an essential component of damages.
Rainbow’s damages model demonstrated the essential components of its
damages claim. Rainbow presented evidence of the difference between what it
bargained for—a firm balancing contract that it could rely on to enter into forward
sales contracts—and what it received—interruptible, unreliable performance that
would not support forward sales contracts. The damages model used facts and data
from Rainbow’s ongoing operations to account for the revenue and costs
surrounding the forward sales that it had anticipated in entering into the MAG-
0005, and it accounted for the mitigation of those lost-profit damages by including
the profit that Rainbow was able to realize under the MAG-0005 despite AMID’s
non-performance.
59
Furthermore, AMID’s argument that Rainbow was required to present
evidence of the value of the MAG-0005 solely as a transportation contract
disregards the nature of the parties’ ongoing business relationship. The parties had
already negotiated and continued to perform under the MAG-0001 as a
transportation contract. Rainbow’s president Stacey Tschider asserted that the
MAG-0005’s benefit to Rainbow was as a balancing contract. The emails and other
communications between the parties during negotiation of the MAG-0005, in
which it was clear that Rainbow was seeking the balancing services that it
negotiated for as a tool to expand its forward sales, likewise support the trial
court’s findings that the value of the MAG-0005 was a firm balancing agreement.
We conclude that the trial court did not err in determining damages based on
the breach of the balancing services bargained for in the MAG-0005. See Signature
Indus. Servs., 638 S.W.3d at 187 (holding that proper measure of damages is
question of law).
D. Assumptions Underlying Damages Model
AMID further argues that the award of lost profits as benefit-of-the-bargain
damages fails as a matter of law because the lost profits model relied on
assumptions that vary from the facts and that do not fill the “reasonable certainty”
the law requires. We disagree.
60
As Rainbow points out in its briefing, AMID does not attack the revenue or
costs identified in the damages model. AMID asserts in its reply brief that “[t]his
Court may assume that data is correct,” but it argues that the model itself was
flawed. AMID and Rainbow thus take two different views of how to determine the
proper damages resulting from the breach here. AMID contends that damages were
only available for days that Rainbow attempted to use the MAG-0005 but was
unable to do so. AMID argues that the damages model is flawed because it
assumes that AMID refused balancing services on days when there are no findings
of breach and no evidence of any refusal of service by AMID.
Under Rainbow’s model, however, the damages flowed from the breach of
the term making performance “firm,” not from any one denial of service. Rainbow
asserted, and the trial court found, that by failing to treat the contract as firm,
AMID destroyed the benefit of the bargain. AMID’s treatment of the MAG-0005
contract as interruptible made AMID’s performance unreliable. Thus, Rainbow
could not rely on the MAG-0005 as a tool to fulfill forward sales to its own
customers. The loss of this business resulted in millions of dollars of lost profits.
AMID argues that Rainbow’s lost-profits model was based on assumptions
that were not supported by the facts, including assumptions that Rainbow would
have entered into forward sales contracts to sell gas at locked-in prices in Zone 5,
based at least in part on using the balancing services under the MAG-0005 to buy
61
the gas in Zone 4. AMID also argues that Rainbow’s damages model theorizes that
Rainbow “would have used the MAG-0005 on many days in which Rainbow did
not in fact use the MAG-0005.” Thus, AMID argues that Rainbow’s estimate of its
lost profits “falls far afield of the ‘reasonable certainty’ the law requires.”
These arguments disregard the evidence that the value of the MAG-0005 to
Rainbow was in its reliability to use it as needed to supply gas for forward sales.
Rainbow presented evidence, in the form of testimony from Tschider and Coorsh,
among others, that the benefit of the MAG-0005 was to be used on days of high
pricing in Transco’s Zone 5 and that made the MAG-0005’s reliability necessary
even if it was not used daily or even monthly. Tschider and Phelan testified for
Rainbow regarding the demand it received from established customers. Rainbow
presented evidence of requests for service from companies like Duke Energy and
others, seeking more gas than Rainbow was able to provide. Tshcider and Phelan
testified that, if Rainbow could have relied upon AMID’s performance under the
MAG-0005, Rainbow would have entered into larger or additional forward sales
contracts to meet this demand.
Thus, Rainbow’s damages model was supported by evidence that it had
customers willing to enter into forward sales contracts for the months identified
and at the prices reflected in their model, based on the average publicly-available
pricing index. But Rainbow was unable to enter into these contracts because AMID
62
failed to perform its obligations under the MAG-0005. Rainbow acknowledges that
it did not actually attempt to use the MAG-0005 on all the days that it would have
used it had AMID performed reliably. Tschider testified that Rainbow did not enter
into the anticipated forward sales contracts because AMID breached the MAG-
0005 by treating it as interruptible. Because Rainbow did not have the forward
sales contract in place, it used the MAG-0005 for daily trades only. This accounted
for the difference between the days that Rainbow actually used the MAG-0005 and
the usage as reflected in the damages model. We conclude that this evidence
supports the trial court’s determination that these discrepancies do not render the
damages model unreliable.
AMID also argues that Rainbow’s trading strategy was “hypothetical” and
constituted a “new and unproven” trading strategy that was a “risk” and “at odds
with Rainbow’s 25-year trading history.” This misrepresents the evidence
presented at trial. Tschider testified that Rainbow had entered into hundreds of
forward sales contracts over its years of operation and that it was a commonly-used
trading strategy. Coorsh testified that using forward contracts was the most
conservative way to do business because it created certainty regarding costs and
profit. And according to Coorsh, Rainbow’s damages model determined the lost
revenue components using “actual forward transactions that were executed by
Rainbow” in conjunction with the MAG-0001 contract.
63
Coorsh also testified that Rainbow’s anticipated use of the MAG-0005 as a
tool to support additional forward sales to its customer base was “a reasonable
strategy” that was based on “what they have done in the past” and “the way that
they conduct their business”:
There is no reason to expect from an experienced gas trading and
marketing perspective that they would do something totally different
than what they have done in the past. Their entire business is serving
customers with reliable supply. This [the MAG-0005] is just one more
way to do that. I would not anticipate to see written documentation
explicit to one contract saying that this is what we are going to do,
especially when the plan is to do what they have always done and
expect to do in the future.
Thus, Coorsh’s testimony supports the trial court’s findings that the purpose
behind Rainbow’s “testing” of the MAG-0005 was to establish the reliability of
AMID’s performance, not the feasibility of entering into forward sales as a general
strategy.
E. Damages Established with Reasonable Certainty
AMID argues that, even if Rainbow established the fact of its lost-profits
damages, it failed to prove the amount of damages with the reasonable certainty
required by Texas law. However, the strategies and related lost profits here were
supported by expert testimony and Rainbow’s own extensive business conducted
under other contracts. Rainbow’s experts acknowledged that natural gas trading
involves some risk and uncertainty, but it nevertheless presented sufficient
evidence based on how the market unfolded for the relevant periods to support its
64
damages model. And as Coorsh and Phelan testified, the figures used in AMID’s
damages model were conservative.
Coorsh addressed AMID’s contention that the damages model “used the
market with 20/20 hindsight.” He disagreed, stating, “There is no hindsight. The
model is a reflection of what they would have done in the real world.” He pointed
out, for example, that the model for January 2018 showed projected sales using the
MAG-0005 that would have resulted in Rainbow losing approximately $1 million
dollars. Coorsh testified that this loss demonstrates that Rainbow did not use
hindsight to create the model, because the use of hindsight would have prevented a
model containing projected losses. He also pointed to December 2017 as another
example. In that month, Rainbow had only minimal lost profits. He stated, “If they
had hindsight, they would have changed the dates in which they put gas to
Magnolia so that they would have made money. But they didn’t do that. Okay?
They showed what decisions they would have made on a day-to-day basis.”
Rainbow used objective facts and data regarding market performance,
including its own performance on other contracts like the MAG-0001 to existing
customers and the average prices of gas during the period for which it missed the
identified opportunities to supply additional gas to its customers. AMID’s briefing
does not identify any particular revenue or cost figures as being unsound. We
conclude that the evidence presented by Rainbow was sufficient for the trial court
65
to determine the amount of lost-profit damages with reasonable certainty. See
Horizon Health Corp., 520 S.W.3d at 859–60.
We overrule AMID’s third issue.
AMID’s Remaining Issues
In its first issue, AMID argues that Rainbow Energy’s fraud and negligent
misrepresentation claims fail because there is no evidence of a false representation
and there is no evidence of justifiable reliance. However, the trial court’s judgment
is supported by the trial court’s breach of contract findings, which we have
affirmed. The tort findings would not afford any greater relief or damages, and so
we need not address AMID’s first issue. See TEX. R. APP. P. 47.1.
In its fourth issue AMID argues that it is entitled to recover on its own
counterclaim for breach of contract. However, when one party to a contract
commits a material breach of the contract, the other party is discharged or excused
from further performance. Mustang Pipeline Co., Inc. v. Driver Pipeline Co., Inc.,
134 S.W.3d 195, 196 (Tex. 2004) (per curiam).
We have determined that the trial court properly concluded that AMID
committed a material breach of the MAG-0005 and repudiated it by treating it as
interruptible rather than firm. Thus, Rainbow was discharged or excused from
further performance under the MAG-0005. See id. Because AMID cannot show
that it tendered performance in connection with the MAG-0005, the trial court
66
properly concluded that it was not entitled to the demand charges it sought under
the MAG-0005.6
We overrule AMID’s fourth issue.
In its fifth issue, AMID argues, in the alternative, that we should remand the
case for a new trial. It bases this assertion on its argument that the trial court
misconstrued the MAG-0005. See, e.g., Best v. Falcon Rock Cmty. Ass’n, 2018
WL 4139092, at *1, *4–5 (Tex. App.—Houston [14th Dist.] Aug. 30, 2018, no
pet.) (remanding for new bench trial because trial court misconstrued unambiguous
contract term). Because we have concluded that the trial court did not misconstrue
the MAG-0005, we overrule AMID’s fifth issue.
We overrule AMID’s fifth issue.
Rainbow’s Request for Attorney’s Fees
Rainbow sought attorney’s fees from AMID, but the trial court ruled that
Rainbow could not recover attorney’s fees from AMID under Civil Practice and
Remedies Code section 38.001 because AMID is a limited liability company.
This Court has previously held that Civil Practice and Remedies Code
section 38.001 as it existed when this suit was filed does not authorize the recovery
of attorney’s fees in a breach-of-contract action against a limited liability
6
We note that Rainbow’s damages model incorporates the demand charges due
under the MAG-0005 as a cost in calculating its lost profits.
67
company.7 TEC Olmos, LLC v. ConocoPhillips Co., 555 S.W.3d 176, 188 (Tex.
App.—Houston [1st Dist.] 2018, pet. denied) (“Under the plain language of section
38.001, a trial court cannot order limited liability partnerships (L.L.P.), limited
liability companies (L.L.C.), or limited partnerships (L.P.) to pay attorneys’
fees.”); Alta Mesa Holdings, L.P. v. Ives, 488 S.W.3d 438, 455 (Tex. App.—
Houston [14th Dist.] 2016, pet. denied). We decline Rainbow’s request that we
overrule this precedent.
We overrule Rainbow’s request for attorney’s fees.
7
The legislature amended Civil Practice and Remedies Code section 38.001
effective September 1, 2021, to permit recovery of attorney’s fees from an
individual or “organization,” as defined by Business Organizations Code section
1.002. See Act of May 28, 2021, 87th Leg., R.S., ch. 665, § 1, 2021 Tex. Sess.
Law Serv. (West) (to be codified at TEX. CIV. PRAC. & REM. CODE § 38.001). This
suit was filed prior to that amendment taking effect, and so we apply the version
that was in effect when this action was commenced. See id. § 2 (amendment
applies to award of attorney’s fees in action commenced on or after effective date
of September 1, 2021).
68
Conclusion
We conclude that the trial court’s findings that AMID breached and
repudiated the MAG-0005 and the findings of $6,145,215.89 in lost profit, benefit-
of-the-bargain damages (plus $449,097.42 in prejudgment interest) were supported
by sufficient evidence. We likewise conclude that the trial court correctly
determined that AMID take nothing on its own breach of contract claim, and it
properly denied Rainbow’s claim for attorney’s fees. Accordingly, we affirm the
trial court’s judgment.
Richard Hightower
Justice
Panel consists of Justices Kelly, Hightower, and Farris.
Farris, J., dissenting.
69