MOORE, J., delivered the opinion of the court, in which MERRITT, J., joined. BOGGS, J. (pp. 649-52), delivered a separate dissenting opinion.
OPINION
MOORE, Circuit Judge.This action was brought under the False Claims Act (“FCA”), 31 U.S.C. §§ 3729-3733, to recover damages for the loss of a helicopter that Defendant-Appellant Boeing Co. (“Boeing”) had remanufactured or overhauled for military use. Boeing now raises the questions of law certified for interlocutory appeal by the district court, arguing that the district court erred in holding (1) that the High-Value Items Clause (“HVIC”), set forth in 48 C.F.R. (“FAR”) § 52.246-24, and incorporated into the helicopter contract between the United States (“Government”) and Boeing, does not operate as a defense to damages sought under the FCA and (2) that the Government may recover damages for the loss of the helicopter. We AFFIRM the judgment of the district court.
I. BACKGROUND
In 1985 and 1989, the United States Army (“Army”) awarded multiyear procurement contracts totaling approximately $2 billion to Boeing for the remanufacture of almost four hundred Boeing-manufactured CH-47A/B/C Chinook helicopters to the CH-47D configuration. As part of these contracts, Boeing was required to inspect and to ensure the quality of all of the parts used for the remanufacture, including those items purchased from its chosen subcontractors. The contracts provided warranty coverage for the helicopters from all defects in material and workmanship for the lesser of two-hundred flight hours or twenty-four months after acceptance.
On August 28, 1990, the Army accepted delivery of a remanufactured CH-47D helicopter (“Aircraft 89-0165”). The next day, Boeing submitted a claim for payment to the Government, in the form of a $4.1 *640million invoice for Aircraft 89-0165. On January 11, 1991, after fifty-six flight hours, Aircraft 89-0165 suffered the failure of a defective flight-critical transmission gear-1 and crashed during a low-level contour flight over the 'Saudi Arabian desert as part of Operation Desert Shield. Aircraft 89-0165 and its contents were totally destroyed at a loss of at least $10 million. The Army replaced Aircraft 89-0165 with a new CH-47D helicopter that cost almost $13 million.
On May 22, 1995, Relator Brett Roby (“Roby”) filed a qui tarn action under seal pursuant to 31 U.S.C. § 3730(b) on behalf of himself and the Government, alleging that Boeing and its supplier, Speco Corp. (“Speco”), had violated the FCA by making false statements about the manufacture and sale of defective transmission gears to the Army via Boeing’s remanufactured CH-47D helicopters. Speco manufactured the gears that Boeing installed into the CH-47D helicopters before their delivery to the Army. On April 30, 1997, the Government intervened and filed an Amended Complaint against Boeing, which was unsealed on May 1,1997.
In its Answer, Boeing denied the allegations of FCA violations and raised a total of twelve affirmative defenses. Specifically, Boeing claimed: (1) that the HVIC, included by regulation in the helicopter contract, barred the damages sought under the FCA and (2) that consequential damages were not available under the FCA.
On December 21, 1998, the Government filed a motion for partial summary judgment, challenging Boeing’s assertion of the 'HVIC as an affirmative defense. After hearing oral argument, the district court granted the motion. United States ex rel. Roby v. Boeing Co., 73 F.Supp.2d 897, 912 (S.D.Ohio 1999) (“Roby /”). On February 5, 1999, Boeing filed a cross-motion for partial summary judgment as to the measure of damages. After hearing oral argument, the district court granted Boeing’s motion in part, with respect to the general issue of consequential damages, but denied the motion as it related to the Government’s damages in this case. United States ex rel. Roby v. Boeing Co., 79 F.Supp.2d 877, 895-96 (S.D.Ohio 1999) (“Roby II”).
On August 3, 2000, before trial, the parties reached a settlement under which Boeing made an immediate payment of $25 million. The settlement did not include the FCA claim arising from the Saudi crash; an additional payment of $15 million is contingent upon 'the outcome of this appeal. The district court accepted the settlement and certified for interlocutory appeal the following questions of law:
1. Whether the [Government] can recover damages under the [FCA] for loss of a helicopter resulting from the failure of a defective flight-critical component part; and
2. Whether the [HVIC] contained in [FAR] § 52.246-24 and incorporated in the Boeing CH-47D helicopter contract operates as a defense to damages sought under the [FCA] for the loss of or damage to a helicopter resulting from the failure of a defective component part.
J.A. at 214 (Order to Amend and Certify). On September 18, 2000, we granted Boeing’s petition for permission to appeal. We have no question before us concerning whether and to what extent Boeing’s conduct was fraudulent. Rather, the question is whether the HVIC precludes liability *641under the FCA, assuming that liability would otherwise exist.
II. ANALYSIS
In an interlocutory appeal, we review a district court’s legal conclusions de novo. Northwestern Ohio Adm’rs, Inc. v. Watcher & Fox, Inc., 270 F.3d 1018, 1023 (6th Cir.2001).
A. Mootness
We first consider sua sponte the jurisdictional question whether the parties’ settlement of August 3, 2000, renders this case moot. Under Article III of the Constitution, our exercise of judicial power is limited to “actual cases or controversies.” Affholder, Inc. v. Preston Carroll Co., 866 F.2d 881, 885 (6th Cir.1989) (quoting Allen v. Wright, 468 U.S. 737, 750, 104 S.Ct. 3315, 82 L.Ed.2d 556 (1984)) (internal quotation marks omitted). “Settlement of a claim before a final adjudication moots the claim and deprives the federal judiciary of jurisdiction over the claim.” Id. Agreements to limit recoverable damages, however, do not moot cases and therefore do not affect our jurisdiction. Id.
The parties’ settlement in this case is essentially the same as the agreement to liquidate damages that was reached in Nixon v. Fitzgerald, 457 U.S. 731, 102 S.Ct. 2690, 73 L.Ed.2d 349 (1982), where a discharged air force employee sought civil damages from the former president. Id. at 733, 102 S.Ct. 2690. Under the terms of the agreement, the employee accepted $142,000, with an additional amount of $28,000 contingent upon the Supreme Court’s ruling that the former president was not entitled to absolute immunity. Id. at 744, 102 S.Ct. 2690. Observing that “[t]he limited agreement between the parties left both petitioner and respondent with a considerable financial stake in the resolution of the question presented in this Court,” the Court concluded, “Given respondents’ continued active pursuit of monetary relief, this case remains definite and concrete, touching the legal relations of parties having adverse legal interests.” Id. (quotation omitted).
In this case, Boeing has already paid the Government $25 million; it has agreed to pay an additional amount of $15 million contingent upon our rulings with respect to the scope of the FCA and the HVIC. Therefore, because the parties have “a considerable financial stake,” the case is not moot, and we will proceed to the merits of this appeal.
B. The FCA and the HVIC
The history of the FCA dates back to 1863, when it was enacted “with the principal goal of stopping the massive frauds perpetrated by large [private] contractors during the Civil War.” Vt. Agency of Natural Res. v. United States ex rel. Stevens, 529 U.S. 765, 781, 120 S.Ct. 1858, 146 L.Ed.2d 836 (2000) (quotation omitted). The FCA has since become the primary means by which the Government combats and deters fraud. H.R.Rep. No. 99-660, at 18 (1986). As amended in 1986, the FCA provides for a civil penalty from $5,000 to $10,000 and treble damages when an individual knowingly acts to defraud the Government and does not “fully cooperate[] with any Government investigation of such violation.” 31 U.S.C. § 3729(a). The Supreme Court understands the current version of FCA damages to be “essentially punitive in nature.” Vt. Agency, 529 U.S. at 784, 120 S.Ct. 1858 (explaining that the Court had “suggested that damages under an earlier version of the FCA were remedial rather than punitive [because] that version of the statute imposed only double damages and a civil penalty of $2,000 per claim” (citations omitted)).
Whereas the FCA allows the Government to recoup losses from fraud, the HVIC helps to manage the costs of liabili*642ty insurance. Since 1984, the Federal Acquisition Regulations (“FAR”) have prescribed the insertion of the HVIC in certain government contracts to limit the liability of contractors “for loss of or damage to property of the Government (including the supplies delivered under th[e] contract) that (1) occurs after Government acceptance of the supplies delivered under th[e] contract and (2) results from any defects or deficiencies in the supplies.” FAR § 52.246-24(a).2 The HVIC covers the loss of or damage to a high-value item, defined as “a contract end item that (a) has a high unit cost (normally exceeding $100,000 per unit) ... and (b) is designated by the contracting officer as a high-value item.” Id. § 46.802. Regarding such high-value items, the Government’s stated policy is to “act as a self-insurer” and to “relieve contractors of contractual liability for loss of or damage to those items.” Id. § 46.803. In short, the HVIC represents' the Government’s assumption of the risk that a high-value item such as Aircraft 89-0165 may be lost or damaged after acceptance as a result of a defect or deficiency in the item. It does not necessarily imply that the Government has self-insured for the damages that result from violations of federal law.
Boeing itself accepts the fact that, “[a]s-suming the government could prove a false claim, a contractor would remain liable for penalties and, if there be any, other appropriate FCA damages, notwithstanding the HVIC.” Appellant’s Br. at 31. However, relying on the text and history of the HVIC, Boeing argues that the HVIC prohibits the recovery of damages under any and all causes of action, when those damages result from the fraud of non-managerial personnel, meaning that there would be no appropriate FCA damages in this case. The issue before us is whether the HVIC’s limitation of contractor liability extends to cases brought under the FCA. Specifically, we must decide whether the Government has agreed to limit damages that would otherwise be recoverable under the FCA.
In holding that the HVIC provides no defense to claims of FCA violations, the district court first noted that the FAR limit the application of the HVIC “to contractual remedies and not to claims premised under the [FCA]”; indeed, the HVIC and the FCA are silent with respect to each other. Roby 7, 73 F.Supp.2d at 910. Therefore, the district court declined to find them inconsistent. Id. Because FCA claims arise from the submission of a false or fraudulent claim, the district court concluded that the HVIC’s limitation on contractual liability did not limit a contractor’s liability under .the FCA, finding no evidence in the record of any such intent on the Government’s part. Id. at 910-11. Finally, the district court distinguished United States v. United States Cartridge Co., 198 F.2d 456 (8th Cir.1952), cert. denied, 345 U.S. 910, 73 S.Ct. 645, 97 L.Ed. 1345 (1953), which held that a liability-limiting contract provision did limit the Government’s FCA claims, id. at 465, on the ground that the contract was made in the emergency situation preceding World War II, making the case unique. Roby I, 73 F.Supp.2d at 911-12.
We agree with the district court that the HVIC does not bar the Government from suing Boeing under the FCA to recover damages for Aircraft 89-0165. We look first to the language of the FCA, which holds a defendant liable for a civil penalty “plus 3 times the amount of dam*643ages which the Government sustains because of the act of that person.” 31 U.S.C. § 3729(a). The allegedly fraudulent act in this case is Boeing’s “false[ ] representation] that the helicopters conformed to contract requirements and fail[ure] to disclose their faulty manufacture to the United States Government.” J.A. at 87 (Am. Compl. at ¶ 3).3 Because of this false claim, the Government sustained the loss of Aircraft 89-0165. Therefore, the Government argues that Boeing is liable under the FCA for treble damages as well as a civil penalty.
At this point, Boeing would direct us to the HVIC, which limits contractor liability for high-value items in fairly broad terms:
Except as provided in paragraphs (b) through (e) below, and notwithstanding any other provision of this contract, the Contractor shall not be liable for loss of or damage to property of the Government (including the supplies delivered under this contract) that (1) occurs after Government acceptance of the supplies delivered under this contract and (2) results from any defects or deficiencies in the supplies.
FAR § 52.246-24(a). The HVIC does not reference the FCA, but it does expressly refuse to limit a contractor’s liability when “the Government’s acceptance of [a high-value item] results from willful misconduct or lack of good faith on the part of any of the Contractor’s managerial personnel.” FAR § 52.246-24(b).4 The parties have stipulated that this exception is not at issue in this ease. Therefore, according to Boeing, the HVIC’s limitation of liability for loss or damage is absolute, precluding the Government from recovering any damages (as opposed to a civil penalty) under the FCA.
We cannot dispose of the FCA claim so easily. Although the loss of Aircraft 89-0165 occurred after Government acceptance and resulted from the defective Spe-co gear, it was actually caused by Boeing’s initial misrepresentation that the helicopter conformed to contract requirements.5 *644This misrepresentation, which triggered FCA liability, is the key to this case. Boeing argues from the “willful misconduct or lack of good faith” language in the managerial personnel provision, FAR § 52.246-24(b), that damages for FCA violations must be covered by the general limitation of liability. We do not agree. Were the HVIC a typical insurance policy, we would consider resolving the ambiguity in Boeing’s favor. Cf. North Bank v. Cincinnati Ins. Cos., 125 F.3d 983, 986-87 (6th Cir. 1997) (stating that Michigan law requires courts to construe ambiguous provisions and exclusionary clauses in insurance policies against the insurer). The aim of the HVIC, however, is to “reduc[e] Government procurement costs by limiting the contractor’s risk.” J.A. at 434 (DPC 86 at 1). The HVIC insures contractors only indirectly; it is, by its own terms, a self-insurance policy, which means that the Government is both insurer and insured. Because nothing in the HVIC suggests that its limitation of contractor liability covers statutory violations, we hold that the district court did not err in concluding that the HVIC does not provide a defense to damages sought under the FCA.
On one level, the dispute in this case is essentially the same as the one in United States Cartridge Co., where the defendant operated a Government-owned ammunition plant during World War II. United States Cartridge Co., 198 F.2d at 458. The Government alleged that the defendant had presented claims for payment that were false because it “fail[ed] to maintain a proper system of inspection and to produce the quality of ammunition called for by the contract.” Id. In its answer, the defendant denied any wrongdoing and argued that its liability was limited by contractual terms similar to the HVIC. Id. at 459-60. After a bench trial, the district court dismissed the case, noting that the limitation of liability was stated in “broad terms” and did not violate public policy. Id. at 460-63. The Eighth Circuit affirmed the dismissal. Id. at 465.
Not surprisingly, the parties disagree as to whether and how the United States Cartridge Co. decision should affect our disposition of this case. We think that the district court correctly distinguished the two cases. See Roby I, 73 F.Supp.2d at 911-12 (emphasizing “the emergency situation” of war in United States Cartridge Co. and contrasting the “extensive governmental control of a prime contractor” in that case with the “limited governmental monitoring” in the case at bar). Moreover, we believe that the Government’s public policy argument in this case is stronger than it was in United States Cartridge Co., where the Eighth Circuit concluded:
If this contract were to be regarded as one creating the conventional relationship between the Government and a commercial corporate contractor not subject to Government supervision and control, for the supplying of goods or services, and if the provisions limiting liability were to be viewed merely as an attempt to relieve such a contractor from liability for its own fraud, the Government’s argument [that the limitation of liability was void] might perhaps be unanswerable.
But this was not a conventional Government contract made under normal conditions; it was an unusual arrangement made to meet a crisis.... “The industrial units thus created are unique. * * * These plants embody a new and tripartite relationship among Government, labor, and management.”
United States Cartridge Co., 198 F.2d at 464-65 (internal citation omitted). The contract in this case was a conventional one for the remanufacture of helicopters almost entirely during peacetime, and Boeing was not subject to Government supervision or control. These differences *645suggest that the limitation of liability in United States Cartridge Co. allocated risks in a way much more favorable to the defendant than does the HVIC. In short, we do not read the HVIC as an agreement by the Government to assume the risk of damages to high-value items that it sustains because of FCA violations.
Boeing implores us to hold the Government to its contractual responsibilities and points us to the Fourth Circuit’s recent decision in United States v. Bankers Insurance Co., 245 F.3d 315 (4th Cir.2001), where the question on appeal was “whether the existence of an FCA claim precludes arbitration of a contract dispute involving the Government.” Id. at 318. The contract dispute concerned a federal agency and a private insurance company that had agreed to arbitrate any misunderstandings or disputes. Id. at 317-18. The Government contended that the Attorney General was not bound by the arbitration agreement because (1) he had not been a party to the agreement, id. at 319, and (2) arbitration would impair his exclusive authority to enforce the FCA. Id. at 324. Unpersuaded by these arguments, the Fourth Circuit ultimately required the Government to submit to nonbinding arbitration before litigating the FCA claim. Id. at 324-25.
According to Boeing, the holding in Bankers Insurance that the Government must satisfy its contractual obligations supports the proposition in this case that the Government may comply with the HVIC only by refraining from seeking damages under the FCA. That the Government is bound by the contracts that its authorized officials sign is incontrovertible. However, we cannot as readily agree with the inference that Boeing draws from Bankers Insurance for the resolution of this case. The Fourth Circuit recognized that FCA claims are “premised on a unique statutory right” and explicitly noted that “the statutory authority of the Attorney General [to enforce the FCA would] not [be] compromised by” making the Government honor its previous agreement to arbitrate. Bankers Ins., 245 F.3d at 325. In other words, the contract in Bankers Insurance merely deferred the litigation of the FCA claim until the nonbinding arbitration process had been completed.
In this case, however, Boeing’s interpretation of the HVIC would absolutely foreclose the Government from recouping anything more than a $10,000 civil penalty for damages sustained because of a false claim for a high-value item, when the damages sustained could be far greater than the general $100,000 threshold for such items. Given Congress’s explicit recognition while amending the FCA “that a large number of fraud cases and many of the larger-dollar cases arise out of Department of Defense contracts,” H.R.Rep. No. 99-660, at 20,6 it strikes us as incongruous that the HVIC would relieve contractors for high-value items from the FCA’s damages provision. After all, the motivating purpose of the FCA is to combat and to deter fraud, which would not be served in the context of defense contracts by the civil penalty alone.
In its brief, Boeing expounds at length on the negative implications, both fiscal *646and otherwise, of holding military contractors liable under the FCA for damages to high-value items. We agree with the Government and Roby that we should leave any revision of the FCA or the HVIC to Congress. In the case before us, Boeing was contractually required to ensure the quality of the parts used for the remanu-facture of the Army’s helicopters; its failure to do so resulted in the Government’s acceptance and use of a helicopter that was not flight-ready and the subsequent loss of the helicopter. The HVIC does not foreclose the FCA as a means for the Government to recover damages for the loss of Aircraft 89-0165.
C. FCA Damages
The crux of this case is the appropriate measure of damages under the FCA, which simply provides for “3 times the amount of damages which the Government sustains because of the act of th[e] person” who submitted the false or fraudulent claim. 31 U.S.C. § 3729(a). We have previously observed that FCA damages “typically are liberally calculated to ensure that they ‘afford the government complete indemnity for the injuries done it.’ ” United States ex rel. Compton v. Midwest Specialties, Inc., 142 F.3d 296, 304 (6th Cir. 1998) (quoting United States ex rel. Marcus v. Hess, 317 U.S. 537, 549, 63 S.Ct. 379, 87 L.Ed. 443 (1943)). “[T]he government is entitled to full damages where it proves it received no value at all.” Id.
In Marcus, the Supreme Court indicated that “restitution to the government of money taken from it by fraud” was the motivating purpose of the FCA; therefore, “the device of [then-] double damages plus a specific sum was chosen to make sure that the government would be made completely whole.” Marcus, 317 U.S. at 551— 52, 63 S.Ct. 379. Three decades later, in United States v. Bornstein, 423 U.S. 303, 96 S.Ct. 523, 46 L.Ed.2d 514 (1976), the Supreme Court understood the baseline to be “the Government’s actual damages,” measured as “equal to the difference between the market value of the [goods] it received and retained and the market value that the [goods] would have had if they had been of the specified quality.” Id. at 316 & n. 13., 96 S.Ct. 523 The Bomstein Court favored this formula because it “maximizes the deterrent impact of the [then-] double-damages provision and fixes the relative rights and liabilities of the respective parties with maximum precision.” Id. at 317, 96 S.Ct. 523.
In this case, the district court held that the Government could recover damages under the FCA that were “the direct, proximate, and foreseeable result of the claims submitted by” Boeing for Aircraft 89-0165; Boeing had argued that its liability at most was limited to “the price of a fully-conforming transmission gear.” Roby II, 79 F.Supp.2d at 895. On appeal, Boeing continues to maintain that “the proper measure of direct FCA damages is the amount wrongfully paid on the claim,” Reply Br. at 23, or the value of the defective Speco gear. However, Boeing now concedes that damages under the FCA could equal — but never exceed — the amount of the claim, which in this case would be the approximately $4.1 million value of Boeing’s contract to remanufac-ture Aircraft 89-0165.
Negotiation strategy aside, we are at a complete loss as to how Boeing can understand “the amount wrongfully paid” to be limited to “the portion of the contract price allocated to the defective gear.” Reply Br. at 21. According to our reading of the contract and the subsequent invoice, Boeing billed the Government for the remanu-factured helicopters as units, not as assemblages of assorted parts. Cf. Bornstein, 423 U.S. at 307, 96 S.Ct. 523 (invoices for radio kits that contained falsely marked electron tubes “included claims for pay*647ment for the falsely marked tubes”). The fact that every component but one conformed to contract requirements is not legally significant when the defective gear was “flight critical” and thus necessary for flight. Because the Speco gear was defective, Aircraft 89-0165 was defective, making Boeing’s entire claim for payment false for the purposes of the FCA.
This understanding of Boeing’s FCA violation informs our analysis of how to calculate damages under the FCA. Under the “diminished value” or “benefit of the bargain” test, which Boeing cites as controlling, we subtract the market value of what the Government received from what it was promised.7 That the contract in this case was for the remanufaeture rather than the sale of a helicopter gives us some pause, but ultimately does not affect the issue before us.8 We will therefore frame the following discussion in terms of the market value of remanufac-tured helicopters.
Under Compton, the market value of Aircraft 89-0165 as delivered was zero. Boeing, of course, would disagree, and we are aware of the fact that the Army did get fifty-six hours of flight time from the helicopter, when the warranty was good for two-hundred flight hours. However, as we concluded in Compton:
[A] setoff based on value purportedly received would create a perverse incentive system in which government con*648tractors could endanger the lives of American soldiers by providing substandard materiel, and the‘Army would be deterred from correcting the danger because it would be forced to bear the cost of any use it received from the substandard goods before their defects were discovered.
Compton, 142 F.3d at 305 n. 8. We believe that this policy argument, which was compelling with respect to untested jeep brake-shoe kits, id. at 297-98, has even more force in the context of this case.
Compton is not as helpful in determining the market value of Aircraft 89-0165 as promised. In Compton, we held that the Government could recover the contract price because damages were the same whether we applied the diminished-value test, as the defendant urged, or the Uniform Commercial Code’s rejection provision. Id. at 305. However, contrary to Boeing’s reading of the case, Compton does not necessarily signify that the recovery of damages in FCA cases is “limited to the contract price originally paid.” Reply Br. at 26. Although the Government apparently did not claim that its full or actual damages were more than the contract price in Compton, it does so in this case.
Boeing characterizes the Government’s claim as one for replacement costs, which it argues are consequential damages and thus unrecoverable under the FCA. We think that this charaeterization confuses the issue. Under the diminished-value test that Boeing itself favors, actual damages depend on “market value.” Bornstein, 423 U.S. at 317 n. 13, 96 S.Ct. 523. Boeing conflates market value and contract price, but the concepts are clearly distinct. Cf. U.C.C. § 2-713 (2001) (“[T]he measure of damages for non-delivery or repudiation by the seller is the difference between the market price at the time when the buyer learned of the breach and the contract price ...”). In this case, the Government contracted for Aircraft 89-0165 to be remanufactured to specific standards. The helicopter as received by the Government did not meet those specifications. Therefore, the Government’s damages equal the difference between the market value of Aircraft 89-0165 as received (zero) and as promised. We do not presume to estimate the market value of a remanufactured helicopter. For our present purposes, we answer the question certified for interlocutory appeal in the affirmative — that is, the Government may recover damages under the FCA for the loss of a helicopter that results from the failure of a defective flight-critical component part. We note that these damages do not represent replacement costs.9 Because the Government did not contract for a new helicopter, it may not recover the roughly $13 million value of the helicopter bought to replace the destroyed Aircraft 89-0165. However, it *649may recover the benefit of its bargain with Boeing, which would be the value that Aircraft 89-0165 would have had if it had been of the specified quality.
III. CONCLUSION
For the foregoing reasons, we AFFIRM the judgment of the district court.
. A "flight critical part” is necessary for flight; its failure could cause the loss of the aircraft. J.A. at 1451 (Gray Dep.).
. From 1971 to 1984, when the FAR became effective, Armed Services Procurement Regulation ("ASPR”) 7-104.45 relieved contractors of such liability. See J.A. at 437 (Defense Procurement Circular 86 (“DPC 86”) at 4), 485-86.
. We note that Boeing “vigorously denies” any knowing submission of a false claim in this case. Reply Br. at 4. However, we must assume such a submission to address whether the HVIC precludes FCA damages when incorporated as a contract provision.
. This exception originally included "fraud or gross negligence as amounts to fraud[ ] on the part of any personnel of the Contractor.” J.A. at 437 (ASPR 7-104.45(b)(ii) (1971)). The defense industry objected to this provision on the following grounds:
Today's exposure to possible infiltration by any number of dissident factions in our society serves to highlight the impossibility of any management to reasonably accept as an uninsured risk the results of any individual’s actions regardless of the extreme nature of such acts.
Therefore, the introduction of this exception goes a long way toward negating the main purpose of DPC 86; that is, to remove from the Contractor the risk of potential liability for damage to Government property and eliminate from Government procurement the cost of Contractors' liability insurance against such liability for damage to Government property.
Unless the insurance exception is substantially modified and the exception regarding fraud of any personnel is removed, there is serious question whether DPC 86 implementation will have any real effect upon the cost of Contractor insurance included in the overall cost of the Government procurement program.
J.A. at 464-65 (Letter from Council of Defense and Space Industry Associations, to Captain E.C. Chapman, Chairman, ASPR Committee 4-5 (Aug. 12, 1971)). The Department of Defense eventually accepted the recommendation to delete the provision.
.In other words, the loss would not have occurred as it did if Boeing had not warranted conformance, because the Government would have required the correction, repair, or replacement of the gear, which was under warranty. The HVIC itself emphasizes this obligation. FAR§ 52.246-24(d)(l).
. See also S.Rep No. 99-345, at 2-3 (1986), reprinted in 1986 U.S.C.C.A.N. 5266, 5267 ("In 1985, the Department of Defense Inspector General, Joseph Sherick, testified that 45 of the 100 largest defense contractors, including 9 of the top 10, were under investigation for multiple fraud offenses. Additionally, the Justice Department has reported that in the last year, four of the largest defense contractors, General Electric, GTE, Rockwell and Gould, have been convicted of criminal offenses while another, General Dynamics, has been indicted and awaits trial.” (citations omitted)).
. See generally John T. Boese, Civil False Claims And Qui Tam Actions § 3.01[D][1], at 3-34 to 3-35 (2d ed. Supp.2002). The facts of Bomstein, where the Supreme Court articulated this rule, are similar to those of this case and deserve some attention. Bomstein involved a Government contract for radio kits, which were to contain electron tubes of a certain quality. Bomstein, 423 U.S. at 307, 96 S.Ct. 523. The subcontractor who supplied these tubes sent tubes that were falsely marked as meeting the Government’s specifications. Id. The contractor then incorporated the falsely marked tubes into the radio kits and shipped them to the Government. Id. The contractor's invoices were thus false because they "included claims for payment for the falsely marked tubes that had been supplied” by the subcontractor. Id. After recovering damages for the tubes from the contractor, presumably by settlement, the Government brought an FCA action against the subcontractor. Id. at 307-08, 96 S.Ct. 523. In holding "that the Government’s damages should be doubled [as the FCA then provided] before any compensatory payments are deducted,” id. at 314, 96 S.Ct. 523, the Bornstein Court stated that those damages were "equal to the difference between the market value of the tubes it received and retained and the market value that the tubes would have had if they had been of the specified quality.” Id. at 317 n. 13, 96 S.Ct. 523.
We recount these facts in detail because the similarity between Bomstein and this case might prompt the all-too-easy substitution of "gear” for "tubes” in the equation quoted above. In both cases, the claim for payment was false because of a defective part that a subcontractor had supplied. However, as the district court correctly noted, “Bomstein was concerned only with the issue of damages and penalties against a subcontractor who causes the prime contractor to submit false claims.” Roby II, 79 F.Supp.2d at 893 n. 47. The defendant in this FCA action, of course, is Boeing, not Speco. We cannot know why the Government settled with the contractor in Bomstein for only the cost of the falsely marked tubes when it had contracted and paid for radio kits — perhaps the tubes did not affect the reliability of the radios. See Bornstein, 423 U.S. at 318-20, 96 S.Ct. 523 (Rehnquist, J., concurring in part and dissenting in part) (describing the subcontractor’s scheme). In this case, however, the Speco gear was not simply of lesser quality than specified; it was a defective flight-critical part, which made the loss of Aircraft 89-0165 inevitable.
. Again, we note that the question certified for appeal is ”[w]hether the [Government] can recover damages under the [FCA] for loss of a helicopter resulting from the failure of a defective flight-critical component part.” J.A. at 214. The answer to this question docs not depend on whether the underlying contract was for remanufacture or sale.
. The Federal Circuit has observed that the diminished-value test is "the normal measure of damages” in FCA cases but held that "[i]n the unusual case in which actual loss in value cannot be ascertained, the injured party may recover the replacement cost, but only if that cost is not clearly disproportionate to the probable loss in value caused by the defects in question.” Commercial Contractors, Inc. v. United States, 154 F.3d 1357, 1372-73 (Fed. Cir.1998). "The cost of remedying defects is not regarded as disproportionate if the defects significantly affect the integrity of a structure being built. In that setting, the injured party is entitled to recover the cost of remedying the defects despite the fact that the cost may be very high.” Id. at 1372.
So instructed, we observe that if the actual loss in Aircraft 89-0165's value could not be ascertained, then the Government would be entitled under Commercial Contractors to recover the very high cost of replacing the downed helicopter, because the defect concerned a flight-critical gear and significantly affected the structural integrity of the helicopter.