Barnard & Son, Inc. v. Akins

SHEPARD, Justice.

This is an appeal from a judgment and from denial of certain post-trial motions. These holdings by the trial judge in effect decreed a forfeiture of plaintiffs-purchasers’ interest in a land sale contract. We affirm in part, reverse in part, and remand.

Plaintiff-appellant Barnard & Son, Inc., contracted to purchase over 100 acres of real property from defendants-respondents Akins’. The total purchase price was approximately $200,000, as to which Barnard paid $30,000 down, assumed a mortgage of approximately $26,000, and promised to make annual payments of $16,000 on June 1 of each succeeding year on the principal and interest owing. That agreement was entered into on May 11, 1978.

Significantly, the contract allowed the purchasers Barnard to prepay any sums due under the contract. Since the Akins’ were concerned about the tax consequences of the sale of the property, they desired any such prepayment moneys to be paid into a trust, which the contract required the Akins’ to establish not later than January 15, 1979. The contract further required the Akins’ to execute a separate warranty deed to a ten-acre tract of land, together with an easement providing access to that tract of land. Lastly, the contract required the Akins’, within a reasonable time, to provide title insurance showing marketable title.

*468It was not until May 11, 1979 that the Akins’ furnished to Barnard a commitment for a title insurance policy. That commitment indicated certain clouds upon the title to the property. Barnard informed the Akins’ that a clouded title would be unacceptable, and Barnard, on May 17, 1979, demanded that the Akins’ clear the title to the property.

Meanwhile, on April 13, 1979, Barnard served a notice of default upon the Akins’, specifying the Akins’ failure to establish the trust by January 15, 1979, and the Akins’ failure to deed to Barnard the ten acres of real property together with the easement. Akins’ were given 30 days to cure the defaults. The warranty deed to the ten acres was signed by the Akins’ on or about June 10, but the trust was not established. By this time, a dispute had apparently arisen between the parties regarding the location of the easement to furnish access to the ten-acre tract. That dispute continued and was never resolved.

As of June 1, 1979, Barnard had not received the title insurance policy, the Akins’ had failed to establish the trust for the deposit of any prepayment moneys, and the dispute concerning the location of the easement continued. Thus, Barnard did not make the June 1, 1979 annual payment as specified by the contract. On June 4, 1979, the Akins’ served upon Barnard a notice of default, specifying Barnard’s failure to make the June 1, 1979 annual payment and giving Barnard 30 days to cure said default. On June 15, 1979, Barnard deposited with the escrow holder all sums then due, but that payment was conditional upon the Akins’ curing the default specified in the default notice served upon Akins’ on April 13, 1979. In July 1979, Akins’ refused to accept the conditional annual payment which had been deposited in escrow, and rather took possession of all the documents from the escrow holder, declaring the contract forfeited.

On August 3, 1979, Barnard instituted this action, seeking specific performance and damages from the Akins’. The cause was tried before the court, with an advisory jury. Following trial and an advisory verdict, the court denied specific performance of the contract, awarded Barnard damages against Akins’ for $283.73, and awarded Akins’ their costs and attorney’s fees.

Thereafter, Barnard made motions for judgment notwithstanding the verdict, for a new trial, and for rescission of the contract. All those motions were denied, and judgment was entered. This appeal resulted.

It is clear that the trial court in the instant case deemed itself to be sitting as a court of equity. For example, the court stated:

“A review of the evidence in this case leads the court to the conclusion that, weighing the equities, specific performance should not be granted. It is a rule of long standing in Idaho that where the entire facts are presented in an action for specific performance of a contract, the rights of the parties should not be adjudged on technical questions so as to do injustice, but rather the court should give such judgment as will be just and equitable...
******
“Here a balancing of the equities between the parties weighs more heavily in favor of the defendants.”

At a later point, the court commented upon the motion of the Akins’ to expunge certain documents from the public records, stating:

“While this cloud could be removed in a separate legal action, the removal of that cloud would be an equitable matter, which this court, given all of the evidence already submitted herein, should address at this time without causing further litigation between the parties.
“In the interest of justice and equity, the recording should be removed from the title to the defendant’s property.”

We agree with these comments of the trial judge regarding the equitable jurisdiction of the court, but deem a further maxim of equity to be applicable in the *469instant action, that being that once the equitable jurisdiction of the court has attached, the court should retain jurisdiction to resolve all portions of the dispute between the parties and render equity to all parties without regard to the technical niceties of pleading and procedure. Watkins v. Watkins, 76 Idaho 316, 281 P.2d 1057 (1955); Finlayson v. Waller, 64 Idaho 618, 134 P.2d 1069 (1943). See I.R.C.P. 15(b), 54(c); Cady v. Pitts, 102 Idaho 86, 625 P.2d 1089 (1981). In the instant action, although plaintiff Barnard sought specific performance of the contract, the trial court in denying such relief implicitly decreed a forfeiture of Barnard’s interest in the contract. Such forfeitures are disfavored in Idaho law. We deem that the trial court erred in failing to apply the equitable remedy which was available to it and which the evidence discloses was applicable to the circumstances, that remedy being rescission.

While it is correct that rescission was neither specifically pleaded nor sought as a remedy, nevertheless, as aptly stated by the trial court:

“The pleadings, exhibits and affidavits-filed to date inferentially reveal that neither of the parties have been completely culpable nor totally blameless during the post execution period. For example, both parties found it necessary to serve good faith notices of default upon the other in order to obtain the performances promised in the written contract.”

The case at hand is somewhat similar to Huggins v. Green Top Dairy Farms, 75 Idaho 436, 273 P.2d 399 (1954), wherein the trial court had, as here, essentially declared the forfeiture of a purchaser’s interest in a contract. On appeal, this Court did not hesitate to reverse that judgment by requiring return of the sums paid by the sellers and remanding for a new trial to determine the reasonable rental value of the property for the time during which it had been held by the purchaser.

In the instant case, the trial court denied Barnard the remedy of specific performance. Although he did not expressly so state, the trial court apparently concluded that Barnard & Son, Inc. was not entitled to specific performance because it had breached the contract by placing conditions upon its payment into escrow of the June 1, 1979 annual installment. Again, though not expressly stated, the trial court apparently concluded that the conditions stated by Barnard were improper. The court held that Akins’ failure to establish the trust on or before January 15 was irrelevant, because Barnard had not previously tendered any funds for deposit into the unestablished trust. Insofar as the Akins’ failed to grant an easement for access to the ten-acre tract, the trial court found that the location of the easement sought by Barnard was not specifically agreed upon between the parties to the contract. We do not disagree with the decision of the trial court in denying specific performance and we will not disturb that exercise of his discretion. See, however, Associated Developers Co. v. Infanger, 85 Idaho 158, 376 P.2d 496 (1962).

We do, however, disagree with that portion of the trial court’s decision holding that the failure to provide title insurance was not a breach of the contract by the Akins’. The trial court stated:

“From the evidence presented, this court is convinced that the defendants were not in default in providing the title insurance policy within a reasonable period of time as required by the contract, considering the conduct of the parties in respect to the contract and the condition of the title to the property disclosed by the preliminary commitments for title insurance.”

It is undisputed and is indeed stipulated by the parties, and the trial court found:

“15. That under the terms of the agreement of sale entered into between the parties on May 11, 1978, the defendants were to provide to the Plaintiff clear title to the property that was the subject matter of the sale.
“16. That the title commitment given to the Plaintiff by the Defendants showed clouded title.
*470“17. That upon receipt of the title commitment Plaintiff demanded that the title to the property be cleared by the Defendants.”

Likewise, it is undisputed from the record that the final policy of title insurance did not issue until after the Akins’ had terminated the contract, removed all of the deeds and other documents from the escrow holder, and forfeited the contract, and until after this lawsuit had been initiated.

Under a similar set of circumstances, this court said in Fajen v. Powlus, 98 Idaho 246, 248-249, 561 P.2d 388, 390-391 (1977):

“Powluses cannot be required to perform their obligations under the contract and yet be compelled to take something less than that for which they bargained. A purchaser of real property who bargained for marketable title thereto cannot be required to accept property with an admitted cloud on the title...
******
“On the other hand, as stated in Giffin v. Faulkner, 50 Idaho 190, 195, 294 P. 521, 522 (1930):
‘Forfeitures are not favored by the court, [citations] One may not declare a forfeiture while he himself is in default, [citations] The duty of respondents, under the contract, to pay the $900 on or before November 1, 1928, was an obligation concurrent with the duty on the part of appellants to “furnish an abstract of title showing said lands to be free and clear of any and all incumbrances,” and justifies the conclusions of the trial court that the Faulkners could not require performance by the Giffins until they (the Faulkners) had tendered the abstract of title as provided in the contract.’
“In the case at bar, Fajen was himself in default of the contract and not entitled to forfeiture and the trial court’s granting of forfeiture was error.” (Bracketed and parenthetical material in original.)

See also Bob Daniels and Sons v. Weaver, 106 Idaho 535, 681 P.2d 1010 (Idaho App.1984); Bell v. Stadler, 31 Idaho 568, 174 P. 129 (1918); Boyd v. Boley, 25 Idaho 584, 139 P. 139 (1914); Restatement (Second) of Contracts § 237 (1981).

It is asserted by Akins’ that the result sought by Barnard in the instant case is contrary to Blinzler v. Andrews, 94 Idaho 215, 485 P.2d 957 (1971). To the extent that Blinzler is contrary to the holding in the instant action and that of Fajen v. Powlus, Blinzler is overruled.

There can be no argument but that one cannot declare a forfeiture of a contract where he himself is materially in default. Associated Developers v. Infanger, supra; Fajen v. Powlus, supra; Huggins v. Green Top Dairy Farms, supra. Thus, in the instant case, the Akins’ were unable to declare a forfeiture while they themselves were in material default. The Akins’ contracted to deliver a title insurance policy showing marketable title free and clear from all liens and encumbrances. Upon that contract provision Barnard had a right to rely, and having paid $30,000 down and paid the mortgage payment for 1978, he could not be required to invest further moneys into a pig in a poke. At the time that the Akins’ served notice of default and sought to forfeit the contract rights of Barnard, and some eleven months after the execution of the contract, the Akins’ still had not furnished a title insurance policy. Rather, they had provided only a commitment for such policy, which commitment admittedly indicated clouds on the title. Barnard demanded that the title be cleared. The trial court held that the title clouds were of no significance, and that, in any event, a title insurance policy had issued some time after the litigation started. A purchaser of real property will not be forced to accept something less than that for which he bargained. In this case, Barnard rightfully expected a marketable title free and clear of encumbrances. Further, we deem the issuance of a title policy at a later date to be irrelevant here. Prior to such issuance, the Akins’ had seized all deeds and documents from the escrow holder, making the contract totally inoperable. One could hardly expect Barnard to go on *471paying money into an escrow holder who no longer held any deeds or documents of title to which Barnard would be entitled upon completion of the contract payments.

It is argued that the trial court did not err in denying relief under the doctrine of rescission. We disagree. Although rescission was not specifically pleaded as a remedy sought by plaintiff Barnard, nevertheless we deem it to have been implicitly tried, and the trial court erred in failing to grant the remedy of rescission, which would have restored both parties to the status quo ante. The trial court also erred in failing to grant a new trial on the issues of unjust enrichment resulting to the Akins’ from their forfeiture of the contract and the retention of the sums paid by Barnard. The trial court’s orders denying Barnard’s motion for a new trial and for rescission are reversed with instructions that Barnard be granted rescission of the contract. The court is directed to take further evidence regarding the fair rental value of the property or of any other appropriate measurement of the setoff to be awarded Akins’ against the return to Barnard of the sums paid under the contract.

Costs to appellants. No attorney’s fees on appeal.

BAKES and HUNTLEY, JJ., concur.