Utah Power & Light Co. v. Idaho Public Utilities Commission

BISTLINE, Justice,

concurring and dissenting.

I concur in those portions of the Court’s opinion which upholds the Commission’s use of an average year as opposed to an end-of-year rate base; which upholds the Commission’s coal inventory adjustment; and which upholds the Commission’s establishment of a 13.5 percent return on equity.

I dissent from the remainder of the Court’s opinion which usurps the Commission’s ratemaking function for that of its own. This Court’s scope of review on appeal in cases such as this is limited to determining whether the Commission regularly •pursued its authority and whether the constitutional rights of the utility have been violated by the fixing of rates which are unjust or unreasonable and thus confiscatory. Utah Power & Light Co. v. Idaho Public Utilities Commission, 102 Idaho 282, 284, 629 P.2d 678 (1981) (UP & L I) (Bistline, J., dissenting, p. 285, 629 P.2d 678).

CONSTRUCTION WORK IN PROGRESS

The Court today sets aside the Commission determination to not include construction work in progress (CWIP) in UP & L’s test year data. The Court cites Citizens Utility Co. v. Idaho Public Utilities Commission, 99 Idaho at 170, 579 P.2d 110 (1978), for the proposition that test year data should be adjusted for anticipated and known changes where the changes are shown to be reliable and certain, thus holding that the Commission erred in not including CWIP in the 1977 rate base. See UP & L I, supra. The Court today thus follows its recent trend of re-examining each component of a Commission ratemaking decision and determining for itself what it, if it were the Commission (which perhaps it is), would have included in a utility’s rate base. As I stated in UP & L I, the Court’s function is to determine if the overall rate allowed by the Commission is reasonable and just, not whether or when a plant or any given item is to be included in the rate base:

“ ‘The standard to be applied in appellate review of utility cases was articulated in Intermountain Gas Co. v. Idaho Public Utilities Commission, 97 Idaho 113, 540 P.2d 775 (1975):
“Our purpose is not to analyze each step of the rate-setting process to determine whether the regulatory agency was correct in its decision, but to look at the overall effect of the rate fixed to determine whether the return to the utility is reasonable and just. As the Supreme Court of the United States stated in Federal Power Commission v. Hope Natural Gas Co., 320 U.S. 591, 64 S.Ct. 281, 88 L.Ed. 333 (1944): ‘It is not theory but the impact of the rate order which counts. If the total effect of the rate order cannot be said to be unjust and unreasonable, judicial inquiry under the Act is at an end. The fact that the method employed to reach that result may contain infirmities is not then important. * * * ’” 540 P.2d 775, 782.’ ”
UP & L I, supra, at 286, 629 P.2d 678 (Bistline, J., dissenting) (emphasis added).

In the present case, it is clear that the Commission’s decision to not allow UP & L to include CWIP in its rate base was reasonable. Inclusion of CWIP in rate base results in an uneven matching between those consumers who will pay for a construction cost and those (if any) who will ultimately benefit from the construction, by requiring consumers to pay for plants not presently serving them and which will not provide service until sometime in the future.

Additionally, it is a matter of common knowledge that utilities often construct generating capacity exceeding their retail *829customers’ needs. During 1980, in fact, UP & L sold 6.25 percent of its Hunter No. 1 plant to Provo City and 39.69 percent of its Hunter No. 2 plant to the Desert Generation and Transmission Co-Op realizing a net gain of over eleven million dollars. Pursuant to this Court’s decision in Boise Water Corp. v. Idaho Public Utilities Commission, 99 Idaho 158, 578 P.2d 1089 (1978), the Commission is required to allocate to shareholders the gain on property to the extent it is undepreciated,1 whether or not the property was included in the rate base and was paid for by shareholders. Today’s decision can lead to the inequitable result of having ratepayers pay for plants not yet on line, with the utility thereafter selling all or a portion of the generating capacity of the plant before it comes on line, and thereby pocketing the gain from the sale returned to the shareholders per our decision in Boise Water, supra.

Requiring the Commission to include CWIP in rate base also leads to inequitable allocations between customer classes. UP & L, which sells energy to several jurisdictions, changes its plant allocations among the jurisdictions every year. Idaho accounted for 16 percent of UP & L’s sales in 1976; 19 percent in 1977; 15.3 percent in 1978; 15.9 percent in 1979; and 14.7 percent in 1980. Thus, allocating CWIP before a plant comes on line can and often will result in inequitable misallocation of the plant between jurisdictions. An examination of the above figures demonstrates that if CWIP was included in the rate base in 1977, Idaho customers would have paid a disproportionate amount of the service that later would have been received by other regulatory jurisdictions.

The Commission should not be required to include CWIP in the utilities’ rate base for the final reason that the proposed plant may never come on line. An example quite close to home is the WPPSS fiasco. Plants 4 and 5 will probably never come on line, but had they been included in the rate base, that fruitless burden would have been paid for by ratepayers who would have received no power whatever from the plants. Traditionally, it is the investors which have been required to provide the capital required to finance new construction. Along with providing the capital, investors also have assumed the risks of new construction, such as delays in placing the plant into service and cost overruns. Requiring the CWIP to be included in the rate base nicely relieves investors of all normal risks of plant construction, but requires the hapless ratepayers to pay return on the plant before receiving any benefit. Requiring the Commission to include CWIP in the rate base shifts the risk of investment from the shareholders, where it properly belongs, to unsuspecting, and now, courtesy of the Court, unprotected ratepayers.

It is clear that the Commission, until today, was entitled to an exercise of discretion in determining whether to include CWIP in a utility’s rate base. Equally clear is it that the Commission did not abuse its discretion in not allowing such a factor to go into that rate base.

PROPERTY HELD FOR FUTURE USE

The Court today holds that property held for future use (PHFU) must be included in the rate base when known and measurable. The authority and reasoning the Court summons for this conclusion is untenable and leave me, admittedly no more of an expert in the field of public utilities regulation than my fellow brethren, at a loss.

First, the Court states that “In UP & LI, supra, we dealt with the question of plant held for future use (PHFU) and there ruled that PHFU, when known and measurable, must be reflected in the rate base.” Unfortunately, the Court cites no page for this proposition and I have not yet located the statement therein — which may be inadequacy on my part. The Court did there hold that the Commission erred in failing to include in the rate base certain adjustments *830to the 1976 test year data for “known and measurable” changes, the exact language being:

“Test year data should be adjusted for known and measurable changes where the changes are shown to be reliable and certain. (Citations omitted.) The Com- . mission should include in the rate base all items which are proven with reasonable certainty to be justifiably used by the utility in providing services to its customers.”
UP & L I, supra, at 284, 629 P.2d at 680 (emphasis added).

The Court then ruled that the Commission erred in refusing to include in the rate base the Huntington and Coal Creek plants. In UP & L I the Court, rather than holding that PHFU must be included in the rate base, stated that “We have examined Utah Power’s other assertions of error [one of which was that PHFU should be included in the rate base] and find them to be without merit.” Id. at 285, 629 P.2d at 681.

The Court, in UP & L I, reiterated the doctrine that customers should only have to pay for items “justifiably used by the utility in providing services,” applying the doctrine that customers need only pay for those items used and useful. The Commission in the present case denied UP & L’s request for seven million dollars in PFHU expenditures finding that:

“Staff witness Holbert proposed elimination of this entire item from rate base on the grounds that it does not represent any plant which is now used and useful. This it is not properly charged to current ratepayers. In addition, Holbert testified that the breakdown of numbers in this category reveals that approximately $4 million is for mineral rights, $2 million for unit # 4 in the Company’s Naughton complex, and $1 million for future substation rights.”
R., p. 69.

The Commission found, as a matter of fact, that the PFHU expenditures requested by UP & L to be included in the rate base were not for used and useful expenditures. This finding is not controverted by the Court and more than adequately supports the Commission’s decision to not allow this item in UP & L’s rate base. Such a result is mandated by our decision in UP & L I, not the contrary as is posited by the Court today.

Secondly, as a purported foundation for its conclusion it is said that:

“Similarly, in Citizens Utilities Co. v. Idaho Public Utilities Commission, supra, 99 Idaho at 171, 579 P.2d at 117, the Court reiterated the company’s right to collect a return on necessary and prudent investments. No reason is pointed out why the same rule should not obtain in the instant case.”

The Court errs on both points. In Citizens, this Court did not reiterate the company’s right to collect return on necessary and prudent investments but held that the Commission erred in not including $8,000 in minimum checking account balances required in order for the utility to obtain low interest loans and in excluding from the rate base the cost of a billing machine which the Court held to be an anticipated and known change which was both reliable and certain. The Court stated only that: “The Commission should include in the rate base all items which are proven with reasonable certainty to be justifiably used in providing services.”

Id. at 171, 579 P.2d 110.

This is the same statement made by the Court in UP & L I, supra, which, as discussed supra, prohibits the Commission from including in the rate base any items not used and useful. Second, the Commission did point out why the same “rule” should not apply in this case:

“[UP & L] submits ‘that this case presents the identical issue which was considered by this court in Citizens Utilities Company v. Idaho Public Utilities Commission, 99 Idaho 164, 579 P.2d 110 (1978),'id. at 47. Citizens did not consider property held for future use. But the Company argues that it is identical for ratemaking purposes to minimum checking account balances that Citizens was required to maintain. The Company *831cites no testimony in the record or legal authority for its equation of property held for future use with minimum checking account balances. The Court found in Gtizens that checking account balances were an integral part of the capital structure because they allowed it to take advanatage of low interest rates when needed, i.e., the Court found that these balances had been and would be-used and useful to the ratepayers. By contrast, none of the land interests included in the Company’s property held for future use had then been dedicated to construction work in progress, let alone dedicated to service to the Company’s customers.
“The Company’s property held for future use was not at the time of the hearing and had never before been of service to the ratepayers. It may be in the future. On the other hand, it may be sold before it is placed in service, and the Company’s shareholders would then be entitled to all gain from the sale under the Court’s holding in Boise Water.[2] Until these properties are dedicated to service of the ratepayers, the Commission may exclude them from the rate base.” Respondent’s Brief, p. 53.

Lastly, the Court premises its conclusion that PHFU must be included in UP & L’s rate base on the fact that it “deem[s] that the company’s expenditures for PHFU are necessary and desirable from an economic standpoint, since they allow the company to take advantage of land opportunities that might otherwise be unavailable, allow the company to escape purchasing property at inflationary prices, and are conducive to lower customer rates in the long run.” It is in this statement that is found the basic error in the Court’s logic — that it is for this Court to make policy and to deem what is best for the utilities — a function heretofore firmly vested in the Commission. It is not this Court’s province to be a super-Commission but merely to determine whether the Commission has abused its discretion in setting confiscatory and unconstitutional rates. Commentators might well perceive that it is this Court which oversteps its bounds and acts outside its jurisdiction and thus unconstitutionally in the setting of rates.

COAL STOCKPILE

Based on my dissent from those portions of the Court’s opinion which holds that CWIP and PHFU are required to be included in the utility’s rate base, I also dissent from that portion of the Court’s opinion which holds that a coal stockpile for the Emery plant is includable in the rate base, “under the same theory that allows CWIP and PHFU in the rate base.”

ATTRITION ALLOWANCE

In setting aside the Commission’s order respecting attrition or regulatory lag, the Court states that “Albeit the commission stated certain conclusions regarding the attrition problem, we discern that the commission likely was unwilling to consider such an allowance for attrition or regulatory lag in any event. We do not state that an attrition allowance will be mandatory in every public utility rate order, but we hold that the order at issue here is unclear as to the reason for the denial.” I confess to being at a loss to see how the Commission could have made its decision any clearer or from what evidence the Court is able to discern that the Commission “likely was unwilling to consider such an allowance for attrition or regulatory lag.” For the benefit of those interested, the Commission’s findings and conclusions are here set out in full:

“V. ATTRITION ALLOWANCE

“Utah Power & Light has requested additional rate relief in the form of what.it labels an ‘attrition allowance.’ Assuming that the final Order in this case had been released on August 1, 1978, the Company alleged a need for an additional $9,791,000 in rate relief. Assuming a release date of *832October 1, 1978, the attrition allowance jumps to an additional $32,001,000. Presumably, the actual release date would warrant still further relief. Throughout this case UP & L has had some difficulty in defining precisely what it means by ‘attrition.’ As the Company’s post hearing brief candidly admits, the record at times defines the problem in terms of erosion of earnings due to rapid expansion in an inflationary era, while at other times it focuses on ‘regulatory lag.’ For example, Company witness Mr. Colby seemed to place exclusive emphasis on the so-called problem of regulatory lag: ‘There is no thought of it compensating for future inflation. Only regulatory lag, as I understand it.’ The Company brief, by contrast, states that ‘the problem is one of a utility’s inability to earn the allowed or determined just and reasonable rate of return due to economic causes or lapse of time in realizing effective relief.’ (Emphasis added.) In yet a third formulation, the brief separates out the problem of ‘attrition’ from that of ‘regulatory lag’ and says that the latter only ‘accentuates’ the former.

“The bottom line appears to be that Utah Power & Light feels ‘attrition’ has occurred whenever the Company fails to earn the rate of return which the Commission has determined to be just and reasonable. As ■the prime example of this, Company witnesses Colby and Hoskins both stressed what they, alleged to be the fact that, during 1977, the Commission allowed a 13.5 percent return on equity whereas, in Idaho, the Company earned only 6.72 percent.

“There are numerous problems with this approach. First, the Company’s rate of return figure is no better than the calculations upon which it is based. The Company calculates its Idaho rate of return based,, among other things, upon (1) the use of an inflated year-end rate base without pro-forming the year’s revenues to match; (2) the inclusion of CWIP in rate base; (3) the inclusion of Plant Held for Future Use in rate base; (4) the exclusion of pre-1971 investment tax credits from its capital structure; and (5) an overstatement of workings capital by nearly 50 percent. As the above discussion of each of these items makes clear, this Commission does not accept the Company’s method of making these calculations. Consequently, the allegedly ‘disastrous’ 6.72 percent rate of return in Idaho is meaningless.

“Secondly, the Company fails to separate out the various causes which may contribute to erosion of earnings. In 1977, for example, the Company experienced a severe plant outage due to an explosion in one of its Huntington Units. By its own admission, this event which was exacerbated by drought conditions prevailing at the time, caused the Company to lose more than $7 million in gross revenue. In addition, the Company experienced severe and abnormal losses due to a major coal strike of unusually long duration. The point is, as Dr. Fitzpatrick observed, that not every failure to earn the rate which is authorized is due to attrition.

“Yet a third difficulty arises from the Company’s expansive definition of ‘attrition.’ The Company, in its brief, would go so far as to include in this definition a factor such as ‘the time it takes for a company to recognize the need for a rate increase’ and ‘delays in filing for rate increases.’ These items, which are purely within management control, are then deemed not to be ‘a question of fault or responsibility’ but rather to be ‘an inherent problem in an expanding economy and an area of construction and growth of the utility.’ This simply will not do. The Company cannot label as ‘attrition,’ everything from management error to acts of God. At no time has the Company attempted to separate out the various factors which cause its alleged failure to earn its allowed rate of return, to quantify these factors, and to pinpoint those which, in any sophisticated economic sense, might truly be attributed to ‘attrition.’1 Absent such a demonstration, the Company has failed to shoulder and to carry its burden of proof in alleging the need for an ‘attrition allowance.’ The Company has demonstrated a revenue deficiency, nothing more.

“We take this opportunity to note that this Commission is not insensitive to the *833economic hardship confronting the utilities subject to our jurisdiction in these inflationary times. We have, when the ■ occasion warranted it, granted interim relief to companies facing emergency situations. See Application of Idaho Power Co., Case No. U-1006-117, IPUC Order No. 13158; Application of Utah Power & Light Co., Case No. U-1009-73, IPUC Order No. 12275.

“In addition, the Idaho legislature, by its amendment of Idaho Code § 61-622, set an outside limit of nine months for Commission deliberation on requests for rate relief, thereby manifesting its concern for the prompt disposition of rate cases. This statutory protection, combined with the right to petition for interim rate relief, provides a Company with adequate safeguards against the problem of regulatory lag.

“Within this framework, we encourage timely filing by a Company when rate relief is necessary. We note, for example, that Utah Power & Light has filed its next rate case — Case No. U-1009-100 — during the very week this Order is being released. This is in marked contrast to the present case which was filed almost seven months after the Commission’s first determination of the Company’s need for rate relief. [Footnote omitted.]

“Moreover, we have tolerated the use of partial test years in the submission of rate cases. For example, in Case No. U-1009-100, just recently filed with this Commission, Utah Power & Light has submitted seven months actual data and, as the case progresses, will replace the forecasted data for the other five months of its test year with actual numbers.

“A final word. Whatever problem of ‘regulatory lag’ may be said to exist is largely of the Company’s own making. These proceedings were extended to and prolonged beyond the normal seven month period because the Company continues to relitigate, in each and every case, issues on which this Commission has adopted firm policy positions. These issues include the rejection of a year-end rate base without proformed revenues and the exclusion from rate base of CWIP and of Plant Held for Future use. By continually filing applications in this format, the company forces numerous production requests and prolongs these proceedings beyond what would otherwise be necessary.

“The above approaches, repeatedly endorsed by witnesses at these hearings, are already being implemented in cases before this Commission. We find them adequate to cope with the problems of attrition and regulatory lag when such problems can be shown to be significant. We find, in the present case, that Utah Power & Light has borne its burden of proving the existence of a revenue deficiency, but has not demonstrated the existence of a significant problem as regards either attrition or regulatory lag. The Company’s request for an ‘attrition allowance’ of between $9,000,000 and $32,000,000 is therefore denied.

. Because generating plants depreciate slowly, the gain attributable to depreciation in the case of the sale of the two Hunter plants was very small, the shareholders retaining all but 800,-000 of the gain.

. See the discussion supra regarding the requirement that the gains on property to the extent they are not depreciated must be credited to shareholders rather than to ratepayers, who under today’s opinion will be paying for PHFU.

A generally acceptable definition of attrition as applied to the utility industry is as follows:

It is the decline in the per cent earned on the rate base due to the replacement of plant items at price levels higher than those experienced when the original plant items were installed; it also comes about by additions to plant at a unit cost higher than the average cost of existing units.

The 1958 National Association of Railroad and Utilities Commissioners report of annual proceedings, pp. 148, 156.”

R., pp. 80-83.