Philips Bros. Electrical Contractors, Inc. v. Pennsylvania Turnpike Commission

OPINION BY

Judge SIMPSON.

We are asked whether a prospective bidder may file a bid protest under the Commonwealth Procurement Code1 one year prior to the contracting agency’s anticipated solicitation of bids. The Pennsylvania Turnpike Commission (Contracting Agency) denied the bid protest of Philips Brothers Electrical Contractors, Inc. (Prospective Bidder), which challenged the Agency’s determination that a proposed new turnpike maintenance facility is not a public building subject to the Separations Act.2 Contracting Agency determined the *943bid protest was not ripe for review. It also concluded the facility is not a public building. On appeal, Prospective Bidder assigns error in Contracting Agency’s conclusion the facility is not a public building subject to the Separations Act. Notwithstanding Prospective Bidder’s interesting argument on the merits, we are compelled to dismiss the petition for review for lack of an actual controversy at this time.

The fully developed record in this matter reveals the following. On September 12, 2007, Prospective Bidder inquired with Contracting Agency whether its project bid for construction of the $20 million Plymouth Meeting Maintenance Facility (Facility)3 sought a single, general contractor bid or separate bids from prime contractors for electrical, mechanical and/or plumbing work. Reproduced Record (R.R.) at 27a. Contracting Agency responded the proposed bid sought a single contractor inasmuch as the Facility is not a public building. Id. at 28a. Importantly, the project description, below, indicates Contracting Agency anticipates soliciting bids in the fourth quarter of 2008.

The parties exchanged further correspondences which ultimately resulted in Prospective Bidder’s December 12, 2007, formal bid protest. The bid protest averred:

The proposed construction bidding process is in violation of the Separations Act. The proposed construction being bid includes the erection of public buildings and separate bids for primary contractors [are] mandated by statute.
Please review this protest in accordance with the procedure set forth in [the Commonwealth Procurement Code, 62 Pa.C.S. § 1711.1].

R.R. at 33a.

Contracting Agency denied Prospective Bidder’s bid protest as premature because Agency has not requested bids or established a bid opening time. See Contracting Agency Dec., 2/8/08. Nevertheless, Contracting Agency also addressed the merits of the bid protest. It rejected Prospective Bidder’s assertions the term “public building” should be interpreted to mean “publicly owned building” and ac*944cepted the more restrictive meaning of “a building open to the public.” Id. at 3. Consequently, Contracting Agency determined the Facility is not a public building subject to the Separations Act because it is not intended for public use.4

Prospective Bidder appeals.5 Relying on Supreme Court precedent,6 Prospective Bidder asserts error in Contracting Agency’s application of a narrow definition to the term. It urges any building constructed with public funds and for the public benefit is a public building for purposes of the Separations Act. Here, there is no dispute the public funds will be used for construction of the $20 million Facility, and the costs exceed the Separations Act’s $4,000 statutory threshold. Further, it is irrelevant whether the Facility will be open to the public; the proper inquiry is whether the building benefits the public. Prospective Bidder claims Contracting Agency has applied its narrow definition of public building to other proposed projects in order to thwart compliance with the Separations Act.

For its part, Contracting Agency maintains the Separations Act does not define “public building,” and the Court precedent upon which Prospective Bidder relies provides a circular definition of the term so as to leave its meaning unresolved. Contracting Agency therefore relies on the Statutory Construction Act of 19727 to adopt the following definition of public building: “A building that is accessible to the public; [especially] one owned by the government.” Black’s Law Dictionary, 1243 (7th ed. 1999). As further support, Contracting Agency contends use of the word public in the Separations Act would be redundant if the General Assembly intended the Act to apply to all Commonwealth-owned buildings. See Twp. of O’Hara v. Condemnation of Permanent Fee Simple Interest for Pub. Park & Recreation Area & Facilities of 4.65 Acres, more or less in O’Hara, 910 A.2d 166 (Pa.Cmwlth.2006), appeal denied, 592 Pa. 763, 923 A.2d 412 (2007) (court should not interpret statute so as to render statutory language as mere surplusage).

Despite our serious concerns with Contracting Agency’s interpretation of the term “public building,” we must first ad*945dress the threshold determination that the bid protest is not ripe. We conclude that we must forestall a full merits review because Prospective Bidder’s December 2007 bid protest is premature.

The Procurement Code establishes a system of competitive bidding under which construction contracts are to be awarded. 62 Pa.C.S. §§ 901-907. The statutory mandate of competitive bidding is grounded in sound public policy; in addition to securing work at the lowest responsible price, competitive bidding invites competition and guards against favoritism, improvidence, extravagance, fraud and corruption in the award of municipal contracts. Premier Comp Solutions, LLC v. Dep’t of Gen. Servs., 949 A.2d 381 (Pa. Cmwlth.2008).

To that end, the Procurement Code sets forth procedures to challenge the solicitation or award of a contract allegedly in violation its provisions. See 62 Pa.C.S. § 1711.1; MSG Group, Inc. v. Dep’t of Pub. Welfare, 902 A.2d 613 (Pa.Cmwlth. 2006). In pertinent part and with added emphasis, the Procurement Code provides:

(a) Right to protest. — A ... prospective bidder ... that is aggrieved in connection with the solicitation or award of a contract, except as provided in section 521 (relating to cancellation of invitations for bids or requests for proposals), may protest to the head of the purchasing agency in writing.
(b) Filing of protest. — If the protestant is a ... prospective bidder or offeror, a protest shall be filed with the head of the purchasing agency prior to the bid opening time or the proposal receipt date. If the ... prospective bidder ... fails to file a protest or files an untimely protest, ... the prospective bidder ... shall be deemed to have waived its right to protest the solicitation or award of the contract in any forum. Untimely filed protests shall be disregarded by the purchasing agency.

62 Pa.C.S. § 1711.1(a) and (b).

Here, Prospective Bidder argues Contracting Agency does not contest it is creating single bid specifications for construction of the Facility or that it intends on soliciting single contract bids. Further, it asserts hardship due to its inability to bid on the Facility and to plan future work and bonding allocations. For these reasons, Prospective Bidder urges the matter is ripe for review.

The doctrine of ripeness arises out of a judicial concern not to become involved in abstract disagreements of administrative policies. Texas Keystone, Inc. v. Pa. Dep’t of Conservation & Natural Res., 851 A.2d 228 (Pa.Cmwlth.2004). The doctrine insists on a concrete contest, where there is a final agency action so that the courts can properly exercise their function. Id. Court rulings applying the ripeness doctrine are premised on policies of sound jurisprudence; courts should not give answers to academic questions, render advisory opinions, or make decisions based on assertions of hypothetical events that might occur in the future. Phila. Entm’t & Dev. Partners, L.P. v. City of Phila., 594 Pa. 468, 937 A.2d 385 (2007).

Our Supreme Court recently addressed the ripeness doctrine in Township of Derry v. Pa. Dep’t of Labor & Industry, 593 Pa. 480, 482, 932 A.2d 56, 57-58 (2007):

In deciding whether the doctrine of ripeness bars our consideration of a declaratory judgment action, we consider “whether the issues are adequately developed for judicial review and what hardships the parties will suffer if review is delayed.” Alaica v. Ridge, 784 A.2d 837, 842 (Pa.Cmwlth.2001) (quoting Treski v. Kemper Nat’l Ins. Co., [449 Pa.Super. 620, 674 A.2d 1106, 1113 *946(1996)]). The factors we consider under our “adequately developed” inquiry include: whether the claim involves uncertain and contingent events that may not occur as anticipated or at all; the amount of fact finding required to resolve the issue; and whether the parties to the action are sufficiently adverse. Id. Under the “hardship” analysis, we may address the merits even if the case is not as fully developed as we would like, if refusal to do so would place a demonstrable hardship on the party. Id.

Assuming this discussion of ripeness in a declaratory judgment action applies here to overcome an express statutory time frame for bid protests, we must consider whether the matter is adequately developed for review and what hardships the parties will suffer if review is delayed.

This Court agrees with Prospective Bidder that the current matter is adequately developed for judicial review. The record contains Prospective Bidders’ protest, its brief in support of protest, which includes a proposed advertisement for solicitation of bids, and Contracting Agency’s rationale for denial of the bid protest. The parties’ positions are further developed in their appellate briefs.

We cannot agree, however, the requisite harm occasioned by delay in review is present. Prospective Bidder complains it cannot bid on the Facility because it is not a general contractor and it cannot properly project future work and allocate its bonding limits. While the alleged harms may be true, they pertain to the merits and not to delayed review.8

Remedies in the Procurement Code support the conclusion that Prospective Bidder suffers no demonstrable hardship if review is delayed until the time frame set forth in the statute. As soon as Contracting Agency solicits bids, and before the time set for opening bids or the proposal receipt date, Prospective Bidder may file a second bid protest. It may reassert its claims before this Court if Contracting Agency again denies its bid protest. 62 Pa.C.S. § 1711.1(g). On appellate review, this Court may cancel the solicitation or award, or declare any resulting contract void. Id. at § 1711.1(j). Thus, the Procurement Code provides a complete remedy upon timely review; therefore, we discern no demonstrable harm to the parties if review is delayed.

We are reluctant to disturb the express statutory time frame for bid protests under these conditions. Accordingly, the petition for review is dismissed.

SMITH-RIBNER, J., dissents and files opinion.

ORDER

AND NOW, this 24th day of November, 2008, the petition for review is DISMISSED as premature.

. 62 Pa.C.S. §§ 101-4604.

. Act of May 1, 1913, P.L. 155, as amended, 71 P.S. § 1618. The Separations Act provides:

*943[I]n the preparation of specifications for the erection, construction, and alteration of any public building, when the entire cost of such work shall exceed four thousand dollars, it shall be the duty of the architect, engineer, or other person preparing such specifications, to prepare separate specifications for the plumbing, heating, ventilation, and electrical work; and it shall be the duty of the person or persons authorized to enter into contracts for the erection, construction, or alteration of such public buildings to receive separate bids upon each of the said branches of work, and to award the contract for the same to the lowest responsible bidder for each of said branches.

. Relevantly, the project description is as follows:

Location: Plymouth Twp. PA (Montgomery Co.) PA Tpke
Value: $20,000,000
Bid Type: Competitive Public Bids
Update: Construction Documents Under Way. Bidding Possible Fourth Quarter 2008
Owner: PA Turnpike Commission
Use: Office Space, Storage Spaces, Vehicle Repair Space, Industrial Drive-Through Vehicle Wash, Lunchroom, Locker Rooms, Server/ Communications Room, Mechanical and Electrical Spaces, Salt Storage, Anti-Skid Storage, and Mixing Facility, Calcium Chloride Storage and Dispensing, Gas, Diesel, and Propane Fleet Fueling Stations, Unheated Vehicle Storage Building, Open Storage Yard, Vehicle Impound Lot, District Maintenance/Stores, Electrical, Carpentry, Plumbing, and Welding Trade Shops, Garage Space, Conference Space, Parking Lot, Restrooms

Reproduced Record (R.R.) at 11 (second emphasis added).

.In its decision, Contracting Agency reviews the purpose of the Separations Act and states the protection of the public is not needed here because the public will not be invited to the Facility. Contracting Agency Dec., 2/8/08, at 6. Actual physical harm, however, is not the type of public harm envisioned by case law. As observed in Mechanical Contractors Association of Eastern Pennsylvania, Inc. v. Southeastern Pennsylvania Transportation Authority, 654 A.2d 119 (Pa.Cmwlth.1995), the legislature intended to keep the expenditure of public funds a process open and clear of possible manipulations. "To remove that process outside the hands of the appointed public officials charged with the duty of expending such funds, would be to infringe the rights of the public.” Id. at 121 (citation omitted). “It is clear ... that by implementing a procedure whereby the general contractor decides which subcontractor is to receive work, denies the public their right to be assured that work is awarded free of personal interest, bias, and prejudice.” Id. The public protection is therefore integrity in the distribution of public monies.

. We must affirm a determination of the purchasing agency unless the Court finds from the record that the determination is arbitrary and capricious, an abuse of discretion or is contrary to law. 62 Pa.C.S. § 1711.l(i).

. See Tragesser v. Cooper, 313 Pa. 10, 16, 169 A. 376, 378 (1933), where the Supreme Court defined the term public building for purposes of the Separations Act as "any building owned or to be owned by [a government entity] and used or to be used for public purposes."

. See 1 Pa.C.S. § 1903 (words and phrases should be construed according to their common and approved usage).

. Prospective Bidder also asserts harm to Commonwealth taxpayers if review is delayed in the form of increased construction and material costs, and expenses incurred in another bid protest. However, all citizens have an interest in Contracting Agency’s compliance with the law.