Tom Thomas Organization, Inc. v. Reliance Insurance

*591Levin, J.

Tom Thomas Organization, Inc., commenced this action to recover damages resulting from the loss of films and tapes which were insured under an inland marine policy issued by Reliance Insurance Co.1

Reliance asserts that the 12-month limitation on suit contained in the policy began running December 14, 1971, the date of loss, and bars Thomas’ action, which was commenced March 16, 1973. Thomas contends that the period of limitation did not begin to run until Reliance denied liability on June 22, 1972. Thomas alternatively contends that Reliance is estopped by its conduct from relying on the limitation.2

The circuit court denied Reliance’s motion for summary judgment on the ground of estoppel. The Court of Appeals reversed, holding that the period of limitation began to run on the date of loss and that Reliance was not estopped from asserting the limitation because it had denied liability six months before the period ran.

We reverse the Court of Appeals.

The running of the period of limitation was tolled from the date Tom Thomas gave notice of loss until liability was formally denied by Reliance.

The question whether Reliance has any liability under the policy for this loss has not been adjudicated and is not before this Court. The cause is remanded for trial.

I

The insurance policy provides that no action *592"shall be sustainable in any court of law or equity unless the same be commenced within twelve (12) months next after discovery by the insured of the occurrence which gives rise to the claim * * *

The general rule, absent statute, is that a provision in a policy of insurance limiting the time for bringing suit is valid if reasonable even though the period is less than that prescribed by otherwise applicable statutes of limitation.3

While a 12-month limitation on suit may represent a reasonable balance between the insurer’s interest in prompt commencement of action and the insured’s need for adequate time to bring an action,4 the insured usually does not have the full 12 months within which to commence an action.

Substantial delays are built into standard insurance policies. The insured is generally allowed 60 to 90 days to file proof of loss. The insurer is generally given another 60 days to pay or settle the claim.

Notwithstanding diligence by both parties at all stages of the claim procedure, considerable time often elapses before the insured learns whether the insurer will pay. Even if the insured promptly reports a loss to his insurance agent, discussions concerning resolution of the claim may take *593weeks. Additional time often passes before the insurance company provides a form for filing proof of loss. Even then the insured does not know whether it will be necessary to start an action; under the policy in this case, payment is not required until 60 days after "acceptance” by the insurer of the proof of loss. No time limit for acceptance is imposed.

While inclusion of such terms in a policy clarifies the claims procedure, the practical consequence is considerable shortening of the time within which suit may be commenced. Here the films and tapes were lost December 14, 1971. Thomas reported the loss January 20, 1972 and filed proof of loss March 7, 1972. Reliance denied the claim June 22, 1972 — more than 60 days after the proof of loss was filed. Over half of the 12-month period of limitation had elapsed between discovery of the occurrence giving rise to the claim and formal denial of the claim.

II

The New Jersey Supreme Court, in Peloso v Hartford Fire Insurance Co, 56 NJ 514; 267 A2d 498 (1970), reached what we regard to be a sound result reconciling policy provisions concerning proof of loss and payment of claims with the provision imposing a time limitation for commencement of an action. Suit on a fire insurance policy was instituted 18 months after the date of the fire and 9 months after liability was denied by the insurer. The Court noted that while the policy purported to give the insured 12 months to begin an action, operation of the proof of loss and payment of claim terms significantly shortened that period of time. The Court concluded that the period of limitation was tolled from the time an *594insured gives notice of loss until the insurer formally denies liability:

"In this manner, the literal language of the limitation provision is given effect; the insured is not penalized for the time consumed by the company while it pursues its contractual and statutory rights to have a proof of loss, call the insured in for examination, and consider what amount to pay; and the central idea of the limitation provision is preserved since an insured will have only 12 months to institute suit. We think this approach is more satisfactory, and more easily applied, than the pursuit of the concepts of waiver and estoppel in each of the many factual patterns which may arise.”

The Supreme Court of Alaska, in Fireman’s Fund Insurance Co v Sand Lake Lounge, Inc, 514 P2d 223, 226-227 (Alas, 1973), reached a like result by finding the policy limitation unconscionable. The Court noted that insurance companies use form policies and consumers have a take-it-or-leave-it option. The Court declined to interpret the policy phrase "inception of the loss” to mean the date of the fire. Analogizing to the Uniform Commercial Code,5 which permits reduction of the four-year statute of limitation by agreement of the parties but not to less than one year, the Court held that the insured must be allowed a full year from the accrual of a cause of action to sue and that a cause of action does not accrue until formal denial of a claim.6

*595The United States Court of Appeals for the Ninth Circuit, applying Nevada law,* *****7 extended the 12-month limitation period provided in a casualty policy by the 60-day payment of claim period. The Court quoted with approval Steel v Phoenix Insurance Co, 51 F 715, 721 (CA 9, 1892), aff'd 154 US 518; 14 S Ct 1153; 38 L Ed 1064 (1893):

" ' * * * A policy of insurance which contains conditions reducing the statutory time for the commencement of any suit thereon ought, in justice and equity, to be so construed — if reasonable under its terms — as to give the full period of time mentioned in the policy, freed from the provisions of all other clauses of the policy, or from the conduct of the insurance company, limiting, or attempting to limit, the time actually given in the limitation clause. This, it appears to us, is the consistent and logical view that ought to be taken of such policies of insurance. * * * It would prevent either party from taking, any undue or improper advantage of the other.’ ” Westchester Fire Insurance Co v Sperling, 421 F2d 141 (CA 9, 1970).

In this case the policy allowed the insured 90 days from discovery of loss to file proof of loss and gave the insurer 60 days from presentation and *596acceptance of proof of loss to pay the claim.8

The effect of these terms is to substantially shorten the 12-month limitation period for commencement of suit. The policy permits a delay of up to 150 days after discovery of loss for filing proof of loss and payment. An indefinite additional period of time — for "acceptance” after "presentation” of the proof of loss — is allowed the insurer before the 60-day period for payment begins to run.

We adopt the approach of the New Jersey Supreme Court.9 The appropriate resolution is not to allow the contractual period of limitation to run *597from the date of the casualty or, as provided in this policy, discovery of the loss, but to toll the running of the limitation from the time the insured gives notice until the insurer formally denies liability.10

It appears that Thomas gave notice of the loss on or about January 20, 1972 (although proof of loss was not filed until March 7, 1972) and Reliance denied liability June 22,1972. The running of the limitation was tolled for approximately five months and did not expire until mid-May, 1973. Thomas’ action was timely commenced on March 16, 1973 and is not barred by the limitation.

It is unnecessary to reach the alternative argument advanced by Tom Thomas — unconscionability and the reasonableness of a one-year limitation. We predicate our holding on reconciliation of the provisions of the policy.

Reversed and remanded for trial.

Kavanagh, C. J., and Williams and Fitzgerald, JJ., concurred with Levin, J. *598Ryan, J., took no part in the decision of this case.

Tom Thomas’ claim against Marsh .& McLennan is for breach of an asserted duty to provide insurance coverage.

Thomas also contends that a new claim arose March 23, 1972, when the lost films and tapes were returned. Thomas had already remade the films and tapes to meet a February contract obligation.

It is unnecessary to decide this question.

See Anno: Validity of Contractual Time Period, Shorter than Statute of Limitations, for Bringing Action, 6 ALR3d 1197 (1966).

The general statute of limitation on contract obligations in Michigan is six years. MCLA 600.5807(8); MSA 27A.5807(8). Policy limitations of less than six years have been enforced by this Court without discussion of reasonableness. See, e.g., Lombardi v Metropolitan Life Insurance Co, 271 Mich 265; 260 NW 160 (1935) (group disability plan; two-year limitation); Bashans v Metro Mutual Insurance Co, 369 Mich 141; 119 NW2d 622 (1963) (accidental injury and illness; two-year limitation); Dahrooge v Rochester German Insurance Co, 177 Mich 442; 143 NW 608 (1913) (standard fire insurance policy; one-year limitation); Betteys v Aetna Life Insurance Co, 222 Mich 626; 193 NW 197 (1923) (disability or death indemnity policy; one-year limitation); Harris v Phoenix Accident & Sick Benefit Ass’n, 149 Mich 285; 112 NW 935 (1907) (accident and sick benefit policy; six-month limitation).

The Uniform Commercial Code, art 2, 8 2-725(1) provides that the four-year limitation period contained in the Code for breach of contract actions arising out of the sale of goods may be reduced by agreement of the parties, but may not be reduced to less than one year from the date of accrual of the cause of action. The Alaska Court expressed its agreement with Professor Corbin that this was a sound provision and should apply to contracts other than contracts for sale of goods.

“Our holding in this case is supported by an important practical *595consideration. In insurance loss cases, adequate preparation of a proof of loss requires a substantial amount of time. Even after submitting his proof, a claimant typically must wait for 60 days before filing suit. The standard policy provision affords insurance companies that 60-day period within which to accept the proof of loss. Were we to read 'inception of the loss’ as meaning the date of the fire, the operational effect of that decision would he to reduce the limitation period to considerably less than one year from the date the cause of action accrued.” Fireman’s Fund Insurance Co v Sand Lake Lounge, Inc, supra, 227.

The Court noted that under Erie R Co v Tompkins, 304 US 64; 58 S Ct 817; 82 L Ed 1188 (1938), it was bound to follow Nevada law. Since the Nevada courts had not decided the question, the Federal court anticipated how a Nevada court would have decided it. Westchester Fire Insurance Co v Sperling, 421 F2d 141, 142 (CA 9, 1970).

"3. Notice of Loss: The Insured shall as soon as practicable report in writing to the Company or its agent every loss, damage or occurrence which may give rise to a claim under this policy and shall also file with the Company or its agent within ninety (90) days from date of discovery of such loss, damage or occurrence, a detailed sworn proof of loss.

"16. Settlement of Loss: All adjusted claims shall be paid or made good to the Insured within sixty (60) days after presentation and acceptance of satisfactory proof of interest and loss at the office of the Company.”

The policy in the Peloso case was a standard fire insurance policy prescribed by New Jersey statute. (The terms of the standard fire insurance policy in Michigan are likewise prescribed by statute, MCLA 500.2832; MSA 24.12832.)

Whether construing statutes or contracts, courts look to the language used and the context for the purpose sought to be achieved. In interpreting a statute, a court is guided by legislative intent; in construing a contract, it looks for the intent of the parties. Courts are not less constrained in construing statutory terms than they are in construing terms agreed to by contracting parties.

While Thomas, unlike the plaintiff in Peloso, was not expressly precluded from bringing suit before expiration of the 60-day "settlement of loss” period, the contract of insurance between Thomas and Reliance provides: "This policy is made and accepted subject to all the conditions which are hereby specifically referred to and made a part of this policy * * * .” Although by its terms the policy did not make the "proof of loss” and "settlement of loss” terms conditions precedent to bringing suit, it would have been violative of the policy to commence suit before complying with these conditions. Reliance cannot be heard to say that Thomas had a full 12 months because he might have ignored the provisions of the policy and commenced an action immediately after the loss without trying to settle his claim.

We appreciate that this Court has previously rejected the contention that a limitation "12 months next after the fire” does not begin to run until after the insured has completed all the steps in the claim procedure (Dahrooge v Rochester German Insurance Co, supra, p 448) and that policyholder efforts to enlarge a limitation period prescribed in an insurance policy have been analyzed in terms of waiver and estoppel (see 14 Callaghan’s Michigan Civil' Jurisprudence, § 473). Waiver and estoppel analysis results in considerable uncertainty concerning the "resaonableness” of the time remaining for suit. Tierney, Contracts, 1971 Annual Survey of Michigan Law, 18 Wayne L R 265, 297-299 (1972). Arguably, if the insurer is estopped from asserting the limitation or is found to have waived it, there is no set time other than the general statutes of limitations within which an action may be commenced.

We find no Michigan case considering the analysis we adopt, reconciling the contractual terms to find that the limitation specified in the policy begins running at the date of loss or its discovery but is tolled until denial of liability by the insurer. A point "neither considered by the Court nor discussed” is not decided. Bostrom v Jennings, 326 Mich 146, 156-157; 40 NW2d 97 (1949).