Zion Missionary Baptist Church v. Pearson

HOWELL, Justice.

Appellee, Bobby G. Pearson, individually and doing business as P & M Air Conditioning and Heating (“Contractor”), sued Zion Missionary Baptist Church (“Owner”) and Oak Cliff Bank and Trust1 to recover the unpaid balance upon a written contract for the installation of air conditioning in Owner's building. In response to a single issue submission,2 the jury found that Contractor *611“did substantially perform.” Based thereon, the trial court entered judgment awarding Contractor his full remaining balance as pleaded,3 of $10,125. Owner’s first and second points (out of eight) are dispositive; therefore, we reverse and remand.

In November of 1978, Owner entered into an agreement for installation of an air conditioning system. Thereafter, Contractor furnished materials and labor, and testified that except for some “minor few things,” he completed the contract. Owner, however, withheld the final payment to Contractor, contending that the system did not work properly. Contractor filed suit and Owner counterclaimed for deceptive trade practices and breach of warranty. The following issue was answered in Contractor’s favor:

1. Do you find ... that the Plaintiff Pearson substantially performed the air conditioning contract in a good and workmanlike manner?

Owner tendered special issues as to the cost of remedying defects and omissions, but the trial court refused to submit them. It further overruled Owner’s objections to the charge, motion to correct the judgment, and motion for new trial.

The jury finding here is similar to the finding in the leading case of Atkinson v. Jackson Brothers, 270 S.W. 848, 850-851 (Tex.Comm’n App. 1925, holding approved), where it was held that the trial court erred in permitting recovery of the full contract price in a case where the jury did not find full performance by the contractor, but instead, only found substantial performance. According to Atkinson, the contractor’s measure of damages in cases where there is a finding of substantial performance, as opposed to full performance, is the contract price less the reasonable cost of remedying the defects and omissions so as to conform the performance to the contract. Atkinson further held that it is the contractor’s burden to provide evidence from which the trier of fact can properly measure the deductions necessary to remedy defects and omissions. 270 S.W.2d at 851; see also, Williams v. Meyer, 629 S.W.2d 257, 259 (Tex.App.—Waco 1982, writ dism’d); BPR Construction & Engineering, Inc. v. Rivers, 608 S.W.2d 248, 250 (Tex.Civ.App.—Dallas 1980, writ ref’d n.r.e.); Treiber v. Schaefer, 416 S.W.2d 576, 579 (Tex.Civ.App.—San Antonio 1967, no writ).

Although Contractor relied upon the theory of full performance in his pleadings and testimony, he did not object to submission of the case solely upon the theory of substantial performance.4 Applying the Atkinson rule, Contractor placed himself in the position of having to present evidence and obtain jury findings on (1) whether he substantially performed and, if so, (2) the cost of remedying defects or omissions necessary to reach complete performance. See also, Williams, 629 S.W.2d at 259. Contractor’s judgment must fail because there is no jury finding on the second part of the substantial performance theory of recovery.

Omission of the second part of the test was not harmless. There was conflicting evidence whether certain defects or omissions existed, to whom they were attributable, and their cost of repair. See Treiber, 416 S.W.2d at 579; see also, Turner, Collie & Braden, Inc. v. Brookhollow Inc., 642 S.W.2d 160, 165 (Tex.1982). Moreover, the trial court cannot be deemed to have made such a finding in light of Owner’s objection to the omission and its tendered issues.

To uphold the judgment, Contractor argues that since a finding of substantial performance entitles Contractor to sue under his contract, Contractor’s damages should be measured by the contract price, with Owner entitled to prove deficiencies *612by way of offset or counterclaim. See BPR, 608 S.W.2d at 251 (Robertson, J., concurring). Inasmuch as Owner only offered evidence that tended to show that defects and omissions existed, and offered no evidence as to the cost of remedying those defects, Contractor argues that it was proper for the trial court to award the full contract balance.

Contractor urges us to re-examine Atkinson, and argues that it imposes an inequitable burden on a contractor — placing him in a position of being required to negate his own claim of full performance by forcing him to offer evidence on the cost of curing deficiencies, the existence of which he denies, or to risk forfeiture of all compensation due. This contention was squarely rejected in Vance v. My Apartment Steak House of San Antonio, Inc., 677 S.W.2d 480, 482-483 (Tex.1984), wherein the Supreme Court reiterated the Atkinson rule:

By definition, this doctrine [of substantial performance] recognizes that the contractor has not totally fulfilled his bargain under the contract — he is in breach. Nonetheless, he is allowed to sue on the contract, but his recovery is decreased by the cost of remedying those defects for which he is responsible. “To allow full recovery without deductions for defects is to award compensation for something ... not done.”

677 S.W.2d at 482 (quoting Atkinson, 270 S.W. at 851). A minority of the Court urged the same contentions here presented by Contractor, but the Court nevertheless reaffirmed the proposition that the burden of proving the reasonable cost of remedying defects is on the contractor. See also, BPR, 608 S.W.2d at 250 (concurring opinions of Guittard, C.J., and Robertson, J.). The contractor’s only alternative is to plead, prove and secure jury findings of full performance.

The doctrine of substantial performance, taken in its present context, has caused recurrent problems. Since 1925, Atkinson has been cited almost 50 times. Many of those cases were suits brought by contractors to recover the unpaid balance under an express agreement for performing improvements to real property. Findings of substantial performance, rather than complete performance, were returned, but the contractor failed to present evidence and/or request findings as to the cost of remedying deficiencies. Citing Atkinson, the courts have reiterated that, in such instances, judgment may not go for the contractor.

We think a principal reason for the recurrence of the problem is a continuing failure of the bench and bar to fully apprehend the established definition of “substantial performance” as applied to the situation in hand. It does not mean “complete for all practical purposes.” It does not refer to a situation where the contractor’s performance is fully complete and fully satisfactory; saving such trifling and insignificant aspects as to which no reasonable owner similarly situated would have ground to object. It is not a de minimus test.

If a contractor were to testify that the work was 90% completed when he was excluded from the job, the jury would have a basis to find substantial performance. However, it would be manifestly unfair to award 100% of the agreed amount because the unearned 10% of a construction contract would most often be a respectable sum of money.

Another problem is that, in cases similar to the one in bar, the owner usually pleads defects and omissions by way of counterclaim or offset. Under such circumstance, it would be natural for the participants to fall into the easy assumption that each party must prove what he pleads — the contractor that he did substantially perform, and the owner, the defects and omissions claimed, together with the cost of remedying the same. However, the Atkinson rule lays the burden elsewhere, causing the unwary to be repeatedly ensnared.

Arguing BPR, Owner urges that the case must be rendered in its favor. However, we believe that the subsequent Vance decision requires that we remand for a new trial. In that case, the trial court directed a verdict and the Court of Appeals affirmed. The Supreme Court reaffirmed *613the substantial performance doctrine and held that the burden of proving the cost of remedying deficiencies rests on the contractor. However, a remand was ordered on grounds that some evidence of the cost of remedying had been presented. Vance, 677 S.W.2d at 483.

Presently, the jury found substantial performance and the sufficiency of the evidence to support this finding is unchallenged. Obviously, the jury was supportive of Contractor’s case and most likely would have returned findings entitling Contractor to a significant recovery had the issue been properly placed before them. If we were to render judgment for Owner, we would be frustrating the clear intent of the jury that Contractor recover a sum of money from Owner and would be exacting a forfeiture of Contractor’s cause of action.

BPR is perhaps distinguishable in that the trial court effectually rendered judgment notwithstanding the verdict. Finding no error in the judgment below, that court was obligated to affirm. It is well established that where there is no error in the judgment below the appellate court has no power except to affirm. We have found error in the judgment and possess both the power and the obligation to remand when such recourse “will subserve better the ends of justice.” Massachusetts Mutual Life Ins. Co. v. Steves, 472 S.W.2d 332, 333 (Tex.Civ.App.—Fort Worth 1971, no writ).

In the seminal Atkinson case a remand was ordered. In this court’s previous opinion of Maizel v. Bush, 337 S.W.2d 337 (Tex.Civ.App.—Dallas 1960, writ ref’d n.r. e.), it agreed that the cost of remedying defects and omissions could not be determined from the evidence presented, but the owner’s plea for rendition was rejected: “[W]e point out that in the Atkinson appeal judgment was not rendered for appellant, as appellant in this case asks us to do.” 337 S.W.2d at 341.

In Treiber, 416 S.W.2d at 579, Atkinson was again interpreted as authority for remand: “Since the trial court had tried the case upon a wrong theory ..., the case was reversed and remanded.” The observation fully applies to the present case.

Other cases finding remand for new trial preferable to rendition are Williams v. Meyer, 629 S.W.2d 257, 260 (Tex.App.—Waco 1982, writ dism’d) (remanded “in the interests of justice”) and Turner, Collie & Braden v. Brookhollow, Inc., 642 S.W.2d 160, 165 (Tex.1982) (theory of damages placed in evidence not the theory submitted). Our review of the substantial performance cases indicates that in the majority of instances where the contractor has not carried his burden of proving the owner’s remedial cost, remand rather than rendition has been ordered and the same remedy will be applied here.5

Reversed and remanded.

. Oak Cliff Bank and Trust was nonsuited during trial.

. More precisely, the basic dispute was submitted in a single issue and a second issue inquired as to attorney’s fees.

. We do not reach Owner’s claim that it did not receive credit for all payments made.

. A pleading of full performance will support the submission of a substantial performance issue. Del Monte Corp. v. Martin, 574 S.W.2d 597, 599 (Tex.Civ.App.—San Antonio 1978, no writ).

. The dissent urges that Contractor is not entitled to "another ‘bite at the apple.’ ” The rhetoric employed is admittedly colorful but hardly analytical. The cases relied upon are distinguishable — either the reversing court found it highly unlikely that the plaintiff would recover at a re-trial or the plaintiff was held to have waived independent grounds of recovery by failing to request any issues whatever thereon. See TEX.R.CIV.P. 279. Neither situation is presently before us.

The dissent urges that Owner is being exposed to the "risk" of a second trial and condemns remand as “ ‘double jeopardy.’ ” It is urged that a new trial will "punish Owner" and that Contractor will be "rewarded” for failure to request proper issues. Remand is repeatedly labeled as inequitable. We do not believe that the dissenting view is supported by the particular facts of this case.

Our review of the record reflects that Owner defended upon the claim that Contractor’s extensive materials and labor were of no value to Owner, at least not beyond the partial payments admittedly made. A counterclaim against Contractor was filed seeking money damages, but no issues were requested thereon. By all appearances, Owner urged the jury to answer the substantial performance issue in the negative, confident that such answer would entitle Owner to a take nothing judgment.

The jury rejected Owner’s contentions. Had Contractor correctly submitted his case, a money judgment approaching the amount of judgment actually rendered below would have been affirmed on appeal. As a “reward” for being *614more perceiving than Contractor, or the trial court, of the issues necessary to support a judgment, and because it made timely objections, Owner will receive "another bite at the apple’ ” which the first jury did not intend Owner to have. As "punish[ment]” for his failure to request the proper issues, Contractor is being forced to endure the “risk” of another trial. Contractor’s cause is being placed in ‘“double jeopardy.’ ” Considering that Owner would have fared badly at the hands of the first jury had the case been correctly submitted, we cann-not agree that remand for a new trial is "inequitable.”