United States Fidelity & Guaranty Co. v. United States Ex Rel. Struthers Wells Co.

209 U.S. 306 (1908)

UNITED STATES FIDELITY AND GUARANTY COMPANY
v.
UNITED STATES FOR THE USE AND BENEFIT OF STRUTHERS WELLS COMPANY.

No. 154.

Supreme Court of United States.

Argued March 5, 1908. Decided April 6, 1908. ERROR TO THE CIRCUIT COURT OF APPEALS FOR THE SECOND CIRCUIT.

*308 *309 Mr. Leonidas Dennis for plaintiff in error.

Mr. Herbert A. Heyn for defendant in error.

*311 MR. JUSTICE PECKHAM, after making the foregoing statement, delivered the opinion of the court.

The demurrer put in by the plaintiff in error is founded upon an amendment of the above mentioned act, which, it is contended, applies to the case before us. The amendment is set forth in the margin.[1]

*312 The record shows that the contract between Flaherty and the United States was entered into December 10, 1903, and the material was furnished to Flaherty by the Struthers Wells Company in March, 1904. It thus appears that the bond was executed under the provisions of the original act of Congress, and the materials were furnished Flaherty while that act was in force and before its amendment. The legal rights of the Struthers Wells Company had become vested before the enactment of the amendment. It is contended on the part of the plaintiff in error that the passage of the amendment (February 24, 1905) made it necessary for the defendant in error to follow its provisions when it commenced this action on the twelfth of April, 1905. It is argued that the amendment prescribes the procedure to be followed by material-men in enforcing claims against a surety on a bond of the nature of the one in suit; that, as amended, the law prohibited a material-man from commencing any action in any district other than that in which the contract was to be performed (in this case *313 the Maryland District of the Fourth Circuit), and also not until after the complete performance of the contract, for the performance of which the bond was given, and until the expiration of six months after such completion, during which time the United States alone has the right to commence an action. The plaintiff in error insists that, although the cause of action herein arose before the passage of the amendment, the action itself not having been commenced until after that time, all the provisions of the amendment regulating the enforcement of such cause of action apply to the action before us, as they do not affect the cause of action itself, but only the method of enforcing the same. In other words, it is contended that the amendment is to have retroactive effect in all matters relative to procedure, and that, as so construed, this action was improperly brought in the Circuit Court of the United States for the Eastern District of New York, and that it was prematurely brought because it does not appear that at the time of the commencement of this action the contract had *314 been completed or that six months had expired since its completion, or that the United States had not itself sued on the bond.

The act which is amended consists of but one material section, the second section providing only for the comparatively unimportant matter of security for costs. The act amending the section also consists of but one section. The question is whether the amended act applies to this case.

There are certain principles which have been adhered to with great strictness by the courts in relation to the construction of statutes as to whether they are or are not retroactive in their effect. The presumption is very strong that a statute was not meant to act retrospectively, and it ought never to receive such a construction if it is susceptible of any other. It ought not to receive such a construction unless the words used are so clear, strong and imperative that no other meaning can be annexed to them or unless the intention of the legislature cannot be otherwise satisfied. Dash v. Van Kleeck, 7 Johns. 499; Jackson v. Van Zandt, 12 Johns. 168; United States v. Heth, 3 Cranch, 399, 414; Southwestern Coal Co. v. McBride, 185 U.S. 499, 503; United States v. American Sugar Co., 202 U.S. 563, 577.

The language of the amended act is prospective, as it provides "that hereafter any person or persons entering into a formal contract with the United States," etc. That language standing alone would leave little doubt as to the intention of Congress in the matter of the taking effect of the amendment.

It is urged, however, that as the amendment in this respect but reiterates the language of the original act, the use of the word "hereafter" in the commencement of the amendment ought not to have the significance which would otherwise attach to it, because it is simply in this particular reenacting the law as it already stood.

There is considerable force in the suggestion that the word "hereafter" is not to receive the weight which in other circumstances it ought to have. The question is, however, one *315 as to the intention of Congress, and when we come to look at the provisions of the statute, as amended, we are convinced that Congress did not intend that the amendment should apply to cases where the bond had already been executed, the work done, the respective rights of the parties settled, and the cause of action already in existence. If Congress had intended otherwise, we think it would have still further amended the original act by providing in plain language that the amendment should apply to all cases, and not be confined to the future.

The plaintiff in error contends that where an amendment to an act relates only to procedure, it takes effect upon causes of action existing when the amendment was passed, and hence that part of the amendment in question applies and prevents the taking of jurisdiction by the Circuit Court for the Eastern District of New York. It is admitted by the plaintiff in error that the act is not confined to procedure but deals with substantive rights in some instances, one of which is the provision granting a preference to the United States over all other creditors. In such case counsel admits that the provision must be construed and held to apply to bonds executed subsequent to the enactment of the statute, and to such bonds alone. Under the statute of 1894 no such preference could be obtained. American Surety Co. of New York v. Lawrenceville Cement Co., 96 Fed. Rep. 25; United States v. Heaton, 128 Fed. Rep. 414.

It would follow necessarily that if the full amount of the liability of the surety on the bond were insufficient to pay all the claims and demands, the provision that, after paying the full amount due the United States, the remainder only should be distributed pro rata among the intervenors, would also be a substantive amendment and not one of procedure. Hence counsel admits that the full amount which may be due the United States depends upon whether the bond was executed prior or subsequent to the amendment of the statute; that if the bond were executed prior thereto, the Government is only entitled *316 to its pro rata share, while if executed subsequently the full amount of its claim, regardless of the claims of the other creditors, would be the amount due. In other words, these provisions, contained in the single section of the act, are to be considered as prospective only and as applicable to bonds executed subsequently to the passage of the amendment.

There is another most important amendment, by which the material-man's right to sue is suspended until after the completion of the work and final settlement and for six months thereafter, during which the United States can alone sue upon the bond. Instead of a right to sue at once upon the non-payment of his claim, he is precluded from doing so, perhaps for years.

Although the time in which to commence action may be shortened and made applicable to causes of action already accrued, provided a reasonable time is left in which such actions may be commenced (Terry v. Anderson, 95 U.S. 628; Wilson v. Iseminger, 185 U.S. 55), yet that is a different principle from taking away absolutely a present right to sue until a period of time, measured possibly by years, shall have elapsed.

These various provisions are all contained in the same section of the statute, and there is not much of it left to be made retrospective, as matter of procedure, after these other provisions have been held to be prospective only. If the limitation as to the district in which the suit upon the bond could be brought were to be regarded as simply matter of procedure (which we do not assert), we still think it is not to be construed as applying retrospectively. As it is only a question of intention we are not prepared to hold that the section is prospective in its operation in regard to all its other provisions, but retrospective in the one instance, as to the district in which the suit is to be commenced. Even matters of procedure are not necessarily retrospective in their operation in a statute, and we see no reason for holding that this statute, of but one section, should be split up in its construction, and one portion *317 of it made applicable to cases already existing and other portions applicable only to the future. We are convinced Congress did not intend such separation. Viewing the whole section, we think Congress meant that only in future cases should the provisions of the amendment apply, although some trifling portion of those provisions might be regarded, technically, as in the nature of procedure. It is therefore wiser to hold the entire section governed by the usual rule and as applying only to the future.

The judgment of the Circuit Court of Appeals was right, and is

Affirmed.

NOTES

[1] Chapter 778, 33 Stat., p. 811:

"Be it enacted, etc., That the act entitled `An Act for the protection of persons furnishing materials and labor for the construction of public works,' approved August thirteenth, eighteen hundred and ninety-four, is hereby amended so as to read as follows:

"`That hereafter any person or persons entering into a formal contract with the United States for the construction of any public building, or the prosecution and completion of any public work, or for repairs upon any public building, or public work, shall be required, before commencing such work, to execute the usual penal bond, with good and sufficient sureties, with the additional obligation that such contractor or contractors shall promptly make payments to all persons supplying him or them with labor and materials in the prosecution of the work provided for in such contract; and any person, company or corporation who has furnished labor or materials used in the construction or repair of any public building or public work and payment for which has not been made, shall have the right to intervene and be made a party to any action instituted by the United States on the bond of the contractor, and to have their rights and claims adjudicated in such action and judgment rendered thereon, subject, however, to the priority of the claim and judgment of the United States. If the full amount of the liability of the surety on said bond is insufficient to pay the full amount of said claims and demands, then, after paying the full amount due to the United States, the remainder shall be distributed pro rata among said intervenors. If no suit should be brought by the United States within six months from the completion and final settlement of said contract, then the person or persons supplying the contractor with labor and materials . .. shall, upon application therefor, and furnishing affidavit to the Department under the direction of which said work has been prosecuted, that labor or materials for the prosecution of such work has been supplied by him or them, and payment for which has not been made, be furnished with a certified copy of said contract and bond, upon which he or they shall have a right of action, and shall be and are hereby authorized to bring suit in the name of the United States in the Circuit Court of the United States in the district in which said contract was to be performed and executed, irrespective of the amount in controversy in such suit, and not elsewhere, for his or their use and benefit, against said contractor and his sureties, and to prosecute the same to final judgment and execution: Provided, That where suit is instituted by any of such creditors on the bond of the contractor it shall not be commenced until after the complete performance of said contract and final settlement thereof; and shall be commenced within one year after the performance and final settlement of said contract and not later: And provided further, That where suit is so instituted by a creditor or by creditors, only one action shall be brought, and any creditor may file his claim in such action and be made party thereto within one year from the completion of the work under said contract, and not later. If the recovery on the bond should be inadequate to pay the amounts found due to all of said creditors, judgment shall be given to Each creditor pro rata of the amount of the recovery. The surety on said bond may pay into court, for distribution among said claimants and creditors, the full amount of the sureties' liability, to wit, the penalty named in the bond, less any amount said surety may have had to pay to the United States by reason of the execution of said bond, and upon so doing the surety will be relieved from further liability: Provided further, That in all suits instituted under the provisions of this act such personal notice of the pendency of such suits, informing them of their right to intervene as the court may order, shall be given to all known creditors, and in addition thereto notice of publication in some newspaper of general circulation, published in the State or town where the contract is being performed, for at least three successive weeks, the last publication to be at least three months before the time limited therefor.'"