IRM Corp. v. Carlson

Opinion

SABRAW, J.

In this matter we decide an issue which has already been considered with conflicting results by a number of the other Courts of Ap*100peal—does a good faith settlement between alleged joint tortfeasors and a plaintiff bar a cross-complaint by another alleged joint tortfeasor who seeks total equitable indemnity from the settling tortfeasors on a theory, inter alia, of active/passive negligence. We conclude that it does. We further conclude that claims for implied contractual indemnity are subject to the same rule. Finally, we address a related due process issue raised by cross-complainant IRM Corporation, find it is without merit, and affirm the judgment.

I. Statement of Facts

IRM appeals from a judgment of dismissal of its cross-complaint for indemnity against Western Shower Door, Inc., and Neis Carlson dba Merritt Construction Company (Merritt Construction). The facts which led to that dismissal are relatively simple.

A. The Genesis of IRM’s Cross-complaint

In 1974, IRM apparently assumed management of an apartment complex located in Moraga. In 1978, one of IRM’s tenants, George Becker, sustained serious injuries when he struck the glass shower door in the bathroom of his apartment, breaking the glass and cutting his hand. The glass in the shower door was untempered; the building code in effect in 1962 required that glass shower doors installed at that time be made of tempered glass. The shower door was installed in 1962 by Western Shower Door, acting as a subcontractor during construction of the apartment complex. The component parts of the door were obtained from Pioneer Shower Door, Inc. Merritt Construction was the general contractor on the apartment construction project.

B. The Litigation

After he was injured, Becker filed suit against his landlord IRM seeking personal injury damages based on theories of negligence and strict products liability. IRM, in turn, filed a cross-complaint against Merritt Construction and Western Shower Door. IRM alleged four different theories as the bases for its cross-claims: (1) total indemnity “by operation of law”; (2) total equitable indemnity arising out of the claim that the cross-defendants’ alleged negligence was “active” while the alleged negligence of IRM, if any, was “passive”; (3) total indemnity based on cross-defendants’ breach of express and implied warranties (contractual indemnity); and (4) comparative equitable contribution under the doctrine of comparative negligence. Thereafter, plaintiff Becker joined Merritt Construction, Western Shower Door and Pioneer Shower Door, Inc., as parties defendant.1

*101IRM was granted summary judgment against plaintiff Becker in 1981. Becker appealed the summary judgment.2 The remaining litigation between the parties continued during Becker’s appeal from the IRM summary judgment. In 1983, Western Shower Door and Merritt Construction, while denying any liability, entered into a sliding scale settlement agreement (a so-called Mary Carter agreement) with plaintiff Becker. In the agreement, Merritt Construction and Western Shower Door agreed to pay Becker $150,000 initially and an additional $50,000 if he recovered less than $200,000 against the remaining defendants IRM and Pioneer Shower Door. By the agreement, Merritt Construction and Western Shower Door hoped to limit their maximum liability to $200,000.

Code of Civil Procedure section 877.53 requires that a court in which litigation is pending be promptly notified by the parties of the existence and terms of any sliding scale settlement agreement. As required by section 877.5, Merritt Construction and Western Shower Door notified the trial court of the sliding scale settlement agreement through a motion in which they sought an order “approving sliding scale recovery agreement. ” In the notice of motion and supporting memorandum of points and authorities, the parties requested that the court find the settlement was entered into “in good *102faith” but nowhere referenced the provisions of section 8774 or section 877.65 which deal with the subject of “good faith” settlements, unlike section 877.5 which does not address “good faith.” In this instance, the notice of motion and supporting papers referenced only section 877.5. However, paragraph 12 of the settlement agreement, attached to the moving papers, did reference both section 877.5 and section 877.6. Neither the notice of motion nor the supporting memorandum of points and authorities and declaration requested dismissal of IRM’s cross-complaint.

A hearing on the motion was held on shortened notice of two days. No opposition to the motion was filed; all parties except Pioneer Shower Door were represented at the hearing. IRM’s counsel informed the court that IRM had not filed papers concerning the motion because the motion papers had been received less than two days before. However, IRM’s counsel expressed no significant opposition to the good faith nature of the settlement. During the hearing the subject of dismissing IRM’s complaint was not discussed.

The court found the settlement was made in good faith and ordered IRM’s cross-complaint dismissed with prejudice. IRM objected to the form of the order dismissing its cross-complaint. Conceding that its claim for equitable contribution based on comparative negligence was barred by the settlement, IRM asserted that its remaining three claims were not barred by section 877.6 because they were claims (1) for total equitable indemnity based on the distinction between the alleged active wrongdoing of cross-defendants and its own alleged passive liability, (2) for contractual indemnity and (3) for indemnity “by operation of law.” IRM informed the court that it was willing to appear for a hearing regarding the disputed form of order if the court “deem[ed] it necessary,” but did not specifically demand a hearing.

*103 Without any further hearing, the trial court entered an order dismissing IRM’s cross-complaint. IRM appealed.6

H. The Issues Framed by IRM

Having determined that the settlement before it was entered into in good faith, the trial court apparently accepted the arguments of the settling cross-defendants and reasoned that dismissal of IRM’s cross-complaint was mandated by both section 877.6 and the analysis of the Supreme Court in American Motorcycle Assn. v. Superior Court (1978) 20 Cal.3d 578 [146 Cal.Rptr. 182, 578 P.2d 899]. On appeal, IRM contends that neither the Supreme Court’s AMA decision nor section 877.6 bars its three remaining claims for total indemnity against Merritt Construction and Western Shower Door because its theories of recovery on those claims are founded (1) on the active/passive negligence distinction (tort) and (2) the asserted breach by cross-defendants of express and implied warranties (contractual indemnity).

As a second argument, IRM contends that it was denied due process because it was never given notice that its cross-complaint might be dismissed and never received the hearing referenced in section 877.6 on the question of whether or not the Mary Carter settlement agreement was entered into in good faith.

*104HI. Analysis

A. The Good Faith Settlement Statute

Section 877.6 was enacted by the Legislature in 1980 to establish a statutory procedure for determining if a settlement by an alleged joint tortfeasor has been entered into in good faith and to provide a bar to claims of other alleged joint tortfeasors for equitable contribution or partial or comparative indemnity when good faith is shown. According to our Supreme Court, section 877.6 is a codification of one of the principles adopted by it in American Motorcycle Assn. v. Superior Court, supra, 20 Cal.3d 578, 604, where the court concluded that “from a realistic perspective the legislative policy underlying . . . [section 877] dictates that a tortfeasor who has entered into a ‘good faith’ settlement [citation] with the plaintiff must also be discharged from any claim for partial or comparative indemnity that may be pressed by a concurrent tortfeasor.” (Tech-Bilt, Inc. v. Woodward-Clyde & Associates (1985) 38 Cal.3d 488, 496, fn. 5 [213 Cal.Rptr. 256, 698 P.2d 159]; see also Turcon Construction, Inc. v. Norton-Villiers, Ltd. (1983) 139 Cal.App.3d 280, 283 [188 Cal.Rptr. 580].)

B. Previous Court of Appeal Decisions

In its 1978 AMA decision, our Supreme Court determined that the principles of comparative negligence adopted in Li v. Yellow Cab Co. (1975) 13 Cal.3d 804 [119 Cal.Rptr. 858, 532 P.2d 1226, 78 A.L.R.3d 393] should be used to apportion liability among multiple negligent tortfeasors under a comparative indemnity doctrine. Prior to the AMA decision, the doctrine of equitable indemnification had permitted passively negligent joint tortfeasors to obtain indemnity from joint tortfeasors whose active negligence was the primary cause of a plaintiff’s injury. (See, e.g., Alisal Sanitary Dist. v. Kennedy (1960) 180 Cal.App.2d 69, 74 [4 Cal.Rptr. 379]; Gardner v. Murphy (1975) 54 Cal.App.3d 164 [126 Cal.Rptr. 302].) As we noted at the outset, the implications of the principles set forth in the AMA decision as applied in the context of good faith settlements have already been considered by several of the Courts of Appeal with differing results. We, therefore, survey those decisions to assist us in reaching our own conclusion on the question.

1. The First Post-AMA Consideration of the Issue

The continuing viability of the active/passive negligence distinction after the Supreme Court’s AMA decision was first considered by the Third District Court of Appeal in City of Sacramento v. Gemsch Investment Co. (1981) 115 Cal.App.3d 869 [171 Cal.Rptr. 764], which arose before section *105877.6 became effective. In Gemsch, a pedestrian was injured when she slipped and fell on seeds which had dropped from city-owned palm trees onto a sidewalk that had not been cleaned for five years and over which the city held an easement. After suing the city (an adjacent landowner) and a lessee and a sublessee of the property where the accident occurred, the pedestrian settled with all parties except the city. The settling defendants then successfully moved for summary judgment on the city’s cross-complaint against them for indemnity on the ground that they had been alleged to be joint tortfeasors and had settled in good faith. The City of Sacramento argued that AMA did not eliminate the doctrine of total implied indemnity based on the active/passive negligence distinction as applied in cases such as Gardner v. Murphy, supra, 54 Cal.App.3d 164. The trial court and a majority of the Court of Appeal disagreed. Although it acknowledged that the Supreme Court had not expressly repudiated the concept of total equitable indemnity “where the alleged indemnitor’s negligence versus the indemnitee’s fault was passive/active, negative/positive, or secondary/primary,” the Gemsch majority concluded that the Supreme Court had “left little doubt where it stood,” citing the high court’s analysis in AMA at pages 594-597. (Id., at p. 876.)

In reaching its decision, the Gemsch majority next looked to the later decision in Safeway Stores, Inc. v. Nest-Kart (1978) 21 Cal.3d 322 [146 Cal.Rptr. 550, 579 P.2d 441] where the Supreme Court held that “equitable indemnity as modified by the partial indemnity doctrine permits apportionment on a comparative fault basis between a strictly liable defendant and a negligent defendant.” (City of Sacramento v. Gemsch, supra, 115 Cal.App.3d 869, 876, italics in original.) In the view of the Gemsch majority, continuing validity of the passive/active distinction would have allowed full indemnity to a passive defendant who is strictly liable. However, in Safeway, the Supreme Court held otherwise, applying a comparative analysis to such a situation. Observing that the Supreme Court might not have completely abolished implied equitable indemnity in the traditional sense, the Court of Appeal majority concluded that in AMA the high court “severely modified one application of it, namely, the passive/active, primary/ secondary approach.” (Id., at p. 877.) The majority went on to say that “[t]he instant case shows why it should be absorbed into the new comparative indemnity of AMA. The City had a separate but concurrent duty to trim or remove trees and to prevent a dangerous condition of which it had notice. There is no evident equity in favor of the City to allow full indemnity.” (Ibid.) The Gemsch majority noted that the case before it was “a prime example of the dilemma facing counsel for alleged indemnitors. With the impetus of Code of Civil Procedure section 877 as broadened by AMA, when settlement is made without a recalcitrant codefendant, then settlors are faced with litigation to determine whether there is some trace of Card*106ner left. Where the transaction rests upon related facts, either concurrent or successive, joint or several, which legally create a detriment compensable against multiple actors, the right of indemnity should follow AMA guidelines, unless a contract or statute otherwise provides.” (Id., at pp. 876-877.)

In a short dissent, Justice Paras took the position that nothing in AMA abrogated the equitable indemnity doctrine. He concluded that the Supreme Court could have stated that that was its intent if it had so desired in AMA, but it had not said so. In his view, “[t]otal equitable indemnity should not be foreclosed by the ‘good faith’ settlement of an active wrongdoer and the injured party, leaving the latter free to pursue his claim further against factually innocent, yet remedyless, persons.” (Id., at p. 879, dis. opn. of Paras, J.)

2. The Gemsch Majority View Gains Momentum

The continuing viability of the passive/active theory of implied indemnity was next considered by Division Two of the Second District in Turcon Construction, Inc. v. Norton-Villiers, Ltd., supra, 139 Cal.App.2d 280. Citing AMA and the analysis of the Gemsch majority, the court unanimously rejected an attempt to rely upon the theory of active versus passive negligence in order to maintain a cross-complaint for indemnity after a good faith settlement by a joint tortfeasor had been made. (Id., at p. 284.) Consistent with the Gemsch majority opinion, the Turcon court appeared to leave the door open to cross-complaints based on contractual indemnity or those where liability of a cross-complainant to the plaintiff is imposed solely as a matter of law because of the relationship with the settling tortfeasor. (Ibid.)

In Kohn v. Superior Court (1983) 142 Cal.App.3d 323 [191 Cal.Rptr. 78], Division Three of our district unanimously followed the analysis of the Gemsch majority. In that case, several cross-complaining defendants brought petitions for writs of mandate after their claims for total implied indemnity were dismissed by the trial court when two cross-defendants and alleged joint tortfeasors entered into good faith settlements with the plaintiff. The Kohn court was careful to explain that it was addressing only the issue of implied equitable indemnity based on tort theories because the petitioning parties had failed to properly present the issue of contractual indemnity to the trial court. (Id., at p. 330.) The court noted that the petitioners had not asserted express contractual indemnity rights. It also noted that the court in Kramer v. Cedu Foundation, Inc. (1979) 93 Cal.App.3d 1, 12-13 [155 Cal.Rptr. 552], had already ruled that implied equitable indemnity had been *107replaced by the AMA principles of implied equitable comparative indemnity. (Ibid.)

Finally, we have found one decision that has at least partially addressed the circumstance of a claim for indemnity based not on a contractual relationship or on an implied equitable indemnity but where the liability of the nonsettling joint tortfeasor exists solely by operation of law. Lopez v. Blecher (1983) 143 Cal.App.3d 736 [192 Cal.Rptr. 190] arose out of a vehicular accident. Blecher was traveling on a freeway when he came upon an overturned van. Blecher’s vehicle struck the van and then struck a motorist who had stopped to give aid at the accident scene. The Good Samaritan sued Blecher, the driver of the van and both of the registered co-owners of the van, one of whom was Lopez. The plaintiff later settled with Blecher for $200,000. Blecher, in turn, successfully sought summary judgment against the cross-complaint of Lopez, asserting the settlement was made in good faith which discharged him from all further liability for total, partial or comparative indemnity or contribution. On appeal, Lopez argued that she was not a joint tortfeasor because her liability was limited and vicarious in nature as a registered co-owner of the van and thus only secondary while that of Blecher was “primary.” The Court of Appeal rejected the argument, relying on AMA and the Gemsch majority opinion. It should be noted that the Lopez decision references discharge from all forms of implied indemnity, total, partial or comparative, although much of the reasoning is limited to partial or comparative indemnity.

3. The Minority View

In Huizar v. Abex Corp. (1984) 156 Cal.App.3d 534 [203 Cal.Rptr. 47], Division Five of the Second District reached a conclusion contrary to that of the Gemsch, Turcon, Kohn and Lopez decisions but consistent with the dissent of Justice Paras in Gemsch and the position now asserted by IRM. Huizar was an injured worker who sued the manufacturer and the distributor of a defective punch press. The two defendants cross-complained against each other. Among other things, the distributor sought total implied indemnity from the manufacturer on the basis of alleged implied and express warranties and on the theory that any negligence on its part was passive as contrasted with the alleged active negligence of the manufacturer. When the plaintiff entered a good faith settlement with manufacturer Abex, the trial court dismissed the cross-complaint of distributor Advanced. Advanced later settled with the plaintiff in good faith and the trial court then dismissed the cross-complaint of Abex against Advanced. Both Abex and Advanced appealed from the dismissals of their respective cross-complaints. The Court of Appeal reversed the dismissal of the distributor’s cross-complaint against the manufacturer Abex, explaining:

*108“With reference to the suggestion by Abex that a cause of action seeking total indemnification is barred by a determination of good faith settlement under Code of Civil Code Procedure section 877.6, subdivision (c), supra, we are of the opinion that had the Legislature intended such a result, the appropriate language easily could have been incorporated in the subject statute. . . . [¶] As to the remaining contention of Abex, we opine that had the Supreme Court in American Motorcycle Assn. v. Superior Court, supra, 20 Cal.3d 578 intended or desired to abolish the doctrine of equitable or total indemnification, it easily could have so stated.” (Id., at p. 541.)

Somewhat surprisingly, the Huizar court did not cite or discuss the Gemsch, Turcon, Kohn or Lopez decisions. Like the Gemsch majority which reached the opposite conclusion, the Huizar court also looked to the Supreme Court’s decision in Safeway Stores, Inc. v. Nest-Cart, supra, 21 Cal.3d 322, 332, footnote 5, to support its conclusion. It next referenced E.L. White, Inc. v. City of Huntington Beach (1982) 138 Cal.App.3d 366 [187 Cal.Rptr. 879], in which Division Two of the Fourth District held that a vicariously liable tortfeasor may still obtain full equitable indemnity from the party actually causing the harm to the injured party, stating: “To conclude otherwise would counter basic ‘principles of common-law indemnification between vicariously liable tortfeasors and tortfeasors guilty of the acts and omissions causing the harm. In short, the apportionment rule applies to those who in fact share responsibility for causing the accident or harm, and does not extend further to those who are only vicariously liable. . . .’ [Citation.]” (Id., at p. 376.) In Huizar, the court’s ruling was based on two different theories: (1) the doctrine of total implied equitable indemnity, and (2) a claim for contractual indemnity based on breach of express and implied warranties, an issue which the Gemsch, Turcon and Kohn courts never reached on the merits.

More recently, Division Three of the Fourth District in Angelus Associates Corp. v. Neonex Leisure Products, Inc., supra, 167 Cal.App.3d 532 considered the same issue now before us. After reviewing all of the decisions we have considered, the court followed Huizar v. Abex Corp., supra, 156 Cal.App.3d 534 and held that a nonsettling defendant in a products liability action may pursue a cross-complaint for total equitable indemnity against a codefendant manufacturer despite the latter’s good faith settlement with the plaintiff.

C. We Follow the Majority View

1. IRM’s Second Cause of Action for Total Implied Equitable Indemnification

We are persuaded that the analysis of the implied equitable indemnity issue by the Gemsch majority is consistent with the principle of comparative *109negligence adopted in Li v. Yellow Cab Co., supra, 13 Cal.3d 804 and with the concept of comparative indemnity referenced in AMA and section 877.6. We conclude that the policy considerations involved in those two decisions require abandonment of the concept of total implied equitable indemnity and its accompanying passive/active analysis. We hold, therefore, that the trial court properly dismissed IRM’s cause of action for total implied equitable indemnity.

2. IRM’s Third Cause of Action Alleging Contractual Indemnity Based on Breach of Express and Implied Warranties

In its third cause of action, IRM sought contractual indemnity based on the theory that Merritt Construction and Western Shower Door breached implied and express warranties they gave in building the apartment complex and installing the defective shower door. We observe preliminarily that IRM’s theory involves at least a two-step analysis. First, IRM asserts that express and implied warranties of fitness for a particular use and of conformance with the applicable building code ran in its favor. Based on that assertion, IRM then jumps to the conclusion that breach of those warranties constituted grounds for invoking express and implied contractual indemnity. In so doing, IRM misconstrues the law of express and implied contractual indemnity.

Express contractual indemnity involves the agreement between two parties that one will indemnify the other in certain circumstances specified in the contract of indemnity. (See E. L. White, Inc. v. City of Huntington Beach (1978) 21 Cal.3d 497, 506-510 [146 Cal.Rptr. 614, 579 P.2d 505].) In the present case, IRM’s express contractual indemnity theory fails for two reasons. First, there was no express contract of any kind between IRM and codefendants Merritt Construction and Western Shower Door. Second, even assuming that there had been an express contract of warranty between the parties, there was no express agreement between them on the subject of indemnity. At most, IRM can argue that an agreement to indemnify should be implied in these circumstances.

The manner in which we deal with the issue of implied contractual indemnity has been predetermined by the way we decided the equitable indemnity issue as explained by the court in Kramer v. Cedu Foundation, Inc., supra, 93 Cal.App.3d 1. Kramer did not involve the good faith settlement issues before us. However, it was decided after AMA and involved the question of whether the doctrine of implied contractual indemnity was still viable after AMA. The Kramer court considered the impact of AMA and explained that: “[i]mplied contractual indemnity is a form of equitable indemnity; it implies a contractual obligation to indemnify despite the absence of an express in*110demnity agreement where equitable considerations make it just to shift the loss to the other party. ... la E. L. White, Inc. v. City of Huntington Beach, supra, 21 Cal.3d 497, 506-510, the court pointed out that parties were still free to formulate express contracts under which a ‘passive’ or even an ‘actively negligent’ party would be completely indemnified. However, the court reaffirmed that in the absence of express contract, the American Motorcycle principles of implied equitable indemnity requiring apportionment according to comparative fault must be applied.” (Id., at pp. 12-13.)

Thus, in Kramer we find additional support for our primary conclusion that the doctrine of implied equitable indemnification was abrogated by the AMA decision. It also instructs that the doctrine of implied contractual indemnity went the same route as did implied equitable indemnity. Applying Kramer to the present case leads to the inescapable conclusion that IRM’s cause of action seeking indemnity based on a theory of implied contractual indemnity was properly dismissed.

3. IRM’s First Cause of Action for Indemnity “By Operation of Law”

IRM’s first cause of action is asserted to be based, in part, on a “line of California cases which have determined the right to indemnity between successive tortfeasors.” The “line of California cases” referenced by IRM consists of two decisions, Herrero v. Atkinson (1964) 227 Cal.App.2d 69 [38 Cal.Rptr. 490, 8 A.L.R.3d 629] and Niles v. City of San Rafael (1974) 42 Cal.App.3d 230 [116 Cal.Rptr. 733]. Based on those two cases, IRM argues that when “(a) a plaintiff’s injury is caused by two negligent acts, (b) the first tortfeasor has no control over the second tortfeasor’s conduct and (c) the first tortfeasor’s liability arises out of a rule of positive law, the first tortfeasor is entitled to total indemnity from the second.”

We find IRM’s reading of these two cases unpersuasive. We believe that cross-defendants accurately explain these decisions as attempts to apply the concept of comparative equitable indemnity to particular fact situations before AMA was decided, although the cases do not use such precise terminology. Furthermore, unlike the situation in Herrero and Niles, the negligent act of the party seeking total indemnity must be separate and distinct from the negligent act or omission of the second party. For instance, in the first cited case Herrero’s negligence resulted in injury to Alice Lorenzo. When Lorenzo underwent surgery for that injury many months later, she died due to the alleged negligence of the medical professionals. The alleged negligence of the medical professionals was separate and distinct from that of Herrero in causing the original accident. By contrast, in the present case, the injuries to plaintiff Becker were allegedly caused by the joint failures of *111IRM, Merritt Construction and Western Shower Door to see that the shower door was made of tempered, glass. Thus, the alleged acts or omissions of IRM in this case are not separate and distinct from those of cross-defendants in the same sense as those in Herrero.

IRM also asserts that it is entitled to total equitable indemnity by operation of law based on its analysis of section 1021.6 which provides for an award of attorney’s fees in certain actions for indemnity.7 In IRM’s view, this statute is further support that its claim for total equitable indemnity by operation of law should survive the good faith settlement by the other alleged joint tortfeasors. It reasons that barring its cross-claim for indemnity by operation of law would be unjust because in the event it is held liable to plaintiff Becker on his strict liability claim it would be in the position of a retailer of goods and would be entitled to reimbursement through indemnity from those higher up in the chain of distribution.

Although we agree that IRM might theoretically be entitled to indemnity for its attorney’s fees from those higher up in the chain of distribution pursuant to section 1021.6 in the event that plaintiff Becker prevails against IRM on his strict liability theory, that circumstance does not automatically lead to the conclusion that it would be unjust to bar IRM’s cross-complaints for indemnity “by operation of law.” If one were to follow that logic, then it is unjust to bar cross-complaints for partial equitable indemnity or comparative indemnity in light of good faith settlements as section 877.6 now authorizes. The fact that IRM loses its ability to seek attorney’s fees from other alleged joint tortfeasors pursuant to section 1021.6 is simply one additional factor to be considered in the overall analysis. Weighing all relevant factors, we conclude that IRM’s theory of indemnity “by operation of law” must suffer the same fate as its claim for total implied equitable indemnity. The trial court properly dismissed this cause of action in light of the good faith settlement.

4. General Considerations

In view of the salutory purpose of encouraging settlements on which section 877.6 is based and the current backlog in the trial courts which settlements can help to eliminate, we have concluded that the good faith settle*112ment between plaintiff Becker and cross-defendants Merritt Construction and Western Shower Door served to bar the cross-complaint of IRM. The sliding scale settlement in this case was conditioned on the settling cross-defendants receiving freedom from further exposure to liability above that specified in the settlement agreement. Settlements such as this in multiple party litigation are becoming more and more common. While some commentators and even some courts still express reservations about the wisdom and equity of permitting sliding scale settlement agreements, the Legislature expressly indicated its approval of such settlement procedures when it enacted section 877.5.

IV. The Due Process Issue

IRM contends that it was denied due process because it was never permitted a hearing on the good faith settlement issue. As we have explained Western Shower Door and Merritt Construction failed to give notice in their motion that they intended to request the court (1) to first make a good faith settlement determination pursuant to section 877.6 and (2) to then order IRM’s cross-complaint dismissed.8 Instead, the notice of motion and supporting papers referenced only section 877.5. It was not until after the hearing when the proposed form of order was prepared that IRM was notified of cross-defendants’ intentions to obtain dismissal of IRM’s cross-complaint.

Were the foregoing circumstances the only ones before us, the argument would be more persuasive and we might well conclude that there had been a denial of due process which would require remand for a properly noticed hearing. However, in this instance, IRM has conceded in its opening brief that the settlement was entered into in good faith. That being the situation there would have been absolutely no purpose served in this case by the court holding a hearing pursuant to section 877.6.9 *113In reality, what concerns IRM is not the opportunity to contest the good faith determination. Instead, IRM is really objecting to the lack of an opportunity to contest the dismissal of cross-complaint because it was never given notice that dismissal was being requested. In other words, IRM was never given proper notice that cross-defendants were, in effect, moving for judgment on the pleadings based on the expected good faith settlement determination.

In theory, IRM is undoubtedly correct. However, the suggestion by IRM in its papers challenging the form of the proposed order that it would appear at a hearing to have the issue of dismissal heard by the trial court, “if the court deem[ed] it necessary,” can arguably be construed as a waiver of any objection to lack of notice and lack of a hearing on that issue. Obviously the trial court did not deem a hearing necessary; it apparently concluded that it was important to enter its order so that plaintiff Becker could receive some measure of immediate compensation for his injuries. In any event, on the particular facts of this issue, we find no error.

The judgment is affirmed. Each party shall bear its own costs on appeal.

Anderson, P. J., concurred.

The record contains no indication of how or when Pioneer Shower Door was added as a party, but it had become a party defendant by the time of the events which concern us. Pioneer is not a party to this appeal.

Our Supreme Court in Becker v. IRM Corporation (1985) 38 Cal.3d 454 [213 Cal.Rptr. 213, 698 P.2d 116] expanded the existing law of landlord-tenant holding that IRM, as a supplier of rental housing, could be held strictly liable for placing a dangerous and defective product, the untempered glass shower door, and hence an unsafe apartment, in the marketplace. At the same time, the court noted that in cases where such liability is asserted, “[t]he landlord will also often be able to seek equitable indemnity for losses.” (Id., at p. 467.)

Section 877.5 provides: “(a) Where an agreement or covenant is made which provides for a sliding scale recovery agreement between one or more, but not at all, alleged defendant tortfeasors and the plaintiff or plaintiffs:

“(1) The parties entering into any such agreement or covenant shall promptly inform the court in which the action is pending of the existence of the agreement or covenant and its terms and provisions; and
“(2) If the action is tried before a jury, and a defendant party to the agreement is a witness, the court shall, upon motion of a party, disclose to the jury the existence and content of the agreement or covenant, unless the court finds that such disclosure will create substantial danger of undue prejudice, of confusing the issues, or of misleading the jury.
“The jury disclosure herein required shall be no more than necessary to be sure that the jury understands (1) the essential nature of the agreement, but not including the amount paid, or any contingency, and (2) the possibility that the agreement may bias the testimony of the alleged tortfeasor or tortfeasors who entered into the agreement.
“(b) As used in this section a ‘sliding scale recovery agreement’ means an agreement or covenant between a plaintiff or plaintiffs and one or more, but not all, alleged tortfeasor defendants, where the agreement limits the liability of the agreeing tortfeasor defendants to an amount which is dependent upon the amount of recovery which the plaintiff is able to recover from the nonagreeing defendant or defendants. This includes, but is not limited to, agreements within the scope of Section 877, and agreements in the form of a loan from the agreeing tortfeasor defendant to the plaintiff or plaintiffs which is repayable in whole or in part from the recovery against the nonagreeing tortfeasor defendant. ”

All statutory references are to the Code of Civil Procedure.

Section 877 provides: “Where a release, dismissal with or without prejudice, or a covenant not to sue or not to enforce judgment is given in good faith before verdict or judgment to one or more of a number of tortfeasors claimed to be liable for the same tort—[¶] (a) It shall not discharge any other such tortfeasor from liability unless its terms so provide, but it shall reduce the claims against the others in the amount stipulated by the release, the dismissal or the covenant, or in the amount of the consideration paid for it whichever is the greater; and [1[] (b) It shall discharge the tortfeasor to whom it is given from all liability for any contribution to any other tortfeasors.”

Section 877.6 provides in pertinent part: “(a) Any party to an action wherein it is alleged that two or more parties are joint tortfeasors shall be entitled to a hearing on the issue of the good faith of a settlement entered into by the plaintiff or other claimant and one or more alleged tortfeasors .... [¶] (c) A determination by the court that the settlement was made in good faith shall bar any other joint tortfeasor from any further claims against the settling tortfeasor for equitable comparative contribution, or partial or comparative indemnity, based on comparative negligence or comparative fault. [¶] (d) The party asserting the lack of good faith shall have the burden of proof on that issue.”

The order dismissing the complaint was not fashioned as a judgment, but rather as an order of dismissal. An appeal from such an order is not specifically designated as an appealable order in section 904.1. Trial courts are not technically empowered by section 877.6 to dismiss cross-complaints such as that before us. They are simply empowered to determine if the settlement has been made in good faith which has the effect of barring the types of claims specified in section 877.6. Courts are only empowered to dismiss complaints and cross-complaints in the circumstances specifically provided by statute or case law such 9s those specified in section 581, subdivisions (c)-(g); dismissal of a claim against a settling alleged joint feasor in the circumstance of a good faith settlement is not mentioned o'r authorized by sections 877, 877.5 or 877.6.

Thus, if there is a court determination that a settlement has been entered in good faith and a cross-complainant such as IRM does not thereafter dismiss its cross-complaint, a motion for summary judgment or a motion for judgment on the pleadings is an appropriate means to enforce the bar to the action. (Cf., e.g., Angelus Associates Corp. v. Neonex Leisure Products, Inc. (1985) 167 Cal.App.3d 532, 534 [213 Cal.Rptr. 403]; Torres v. Union Pacific R.R. Co. (1984) 157 Cal.App.3d 499, 509 [203 Cal.Rptr. 825].) However, we do not believe that it is necessary for parties to appear on two separate occasions in order to obtain such a dismissal, the first to obtain a good faith settlement determination and the second on a motion for summary judgment or judgment on the pleadings. If properly noticed, we see no reason why the entire matter cannot be handled at one appearance.

We construe the order of dismissal in this case as a judgment on the pleadings for purposes of this appeal, as that appears to have been the intent of the trial court which took no evidence on the matter other than implicitly taking judicial notice of its own good faith settlement determination.

Section 1021.6 provides in relevant part: “Upon motion, a court after reviewing the evidence in the principal case may award attorney’s fees to a person who prevails on a claim for implied indemnity if the court finds (a) that the indemnitee through the tort of the indemnitor has been required to act in the protection of the indemnitee’s interest by . . . defending an action by a third person and (b) if that indemnitor was properly notified of the demand to . . . provide the defense and did not avail itself of the opportunity to do so, and (c) that the trier of fact determined that the indemnitee was without fault in the principal case which is the basis for the action in indemnity. ...”

This omission may be attributable to respondents’ erroneous contention on appeal that section 877.6 is inapplicable to “Mary Carter” settlements. Section 877.5 contains no bar to claims by nonsettling parties or joint tortfeasors; section 877.5 is, in effect, a rule of evidence which provides an exception to the general rule that offers to compromise and settlements are generally inadmissible evidence. (Evid. Code, §§ 1152, 1154.) In order to obtain a bar to a claim by a nonsettling party, in such cases, including those involving “Mary Carter” agreements, someone must first obtain a good faith determination from the court pursuant to section 877.6.

Notwithstanding previous concessions in the trial court and before us that the settlements were entered into in good faith when tested against section 877.6, after the recent decision of the Supreme Court in Tech-Bilt, Inc. v. Woodward-Clyde & Associates, supra, 38 Cal.3d 488, IRM suggested that it would be appropriate for us to remand in order to permit the trial court to hold a good faith settlement hearing in light of the Tech-Bilt holding. In that case, the Supreme Court held that for purposes of determining good faith pursuant to section 877.6, a court must not limit its analysis to the issue of whether a settling alleged joint *113tortfeasor has engaged in tortious conduct toward nonsettling parties. Instead, the court indicated that a wide variety of factors must be considered, including the amount paid in settlement. (Id., at pp. 499-500.) Although the Tech-Bilt decision will undoubtedly affect future good faith settlement determinations in other cases, we find it of little help to IRM. Here, IRM chose not to challenge the good faith nature of this settlement in the trial court. IRM’s counsel made a passing reference to the well-known, 11-year-old decision in River Garden Farms, Inc. v. Superior Court (1972) 26 Cal.App.3d 986, 998 [103 Cal.Rptr. 498] [dictum to the effect that “a low settlement violates the good faith clause”] and the Ninth Circuit’s more recent decision in Owen v. United States (9th Cir. 1983) 713 F.2d 1461, 1465 [predicting the California Supreme Court would adopt a good faith settlement rule involving assessment of relative liabilities] but never specifically asserted that the settlement failed to meet the good faith standard of section 877.6. IRM requested and apparently received the opportunity to review and to object to the form of the order later presented to the court but chose not to renew any arguable bad faith settlement objection. Finally, in its opening brief on appeal, IRM stated: “IRM concedes that the sliding scale recovery agreement was made in good faith. ” (Italics added.) It is significant to note in this regard that our Supreme Court granted review in Tech-Bilt on November 10, 1983, which was 25 days before the trial court’s hearing in this case and over 7 months before IRM explicitly waived any even arguable assertion that it wished to raise the good faith settlement issue on appeal. By contrast, the decisions upon which Tech-Bilt based its appeal and which the Supreme Court approved in its decision were available to IRM if it had really desired to challenge the good faith claim below and on appeal. Accordingly, IRM cannot now rely upon the fortuitous circumstance of the Tech-Bilt decision in attempting to litigate an issue it chose not to assert on appeal. In any event, remanding on this ground would be pointless. At a Bench and Bar settlement conference the participants valued this case in a range of $200,000-$250,000. Here the settlement amount was $200,000 without any contribution from Pioneer Shower Door or IRM. To send this case back to the trial court for a good faith review on whether a $200,000 Mary Carter settlement was somehow disparate from a settlement conference top end value of $250,000 would be an obvious idle act and a waste of valuable trial court time.