Minor v. Rush

RONALD R. HOLLIGER, Presiding Judge.

Robin and Delann Rush (“Sellers”) appeal from a judgment ordering them to specifically perform a contract to sell their 230 acre farm to Gary Minor and Gina Carter (“Buyers”). Sellers refused to close and deliver a warranty deed to Buyers when Sellers determined that hens on the property exceeded their proceeds of the sale. Because they did not obtain a full Deed of Release from their bank, they claim that their refusal to deliver a deed to Buyers should be excused on the basis of *212impossibility of performance. The judgment is affirmed.

Factual and Procedural Background

Sellers operated a farm on 230 acres in Dekalb County. Experiencing financial difficulties, Sellers listed their land for sale with a realtor at a sale price of $1,325 per acre. The land was encumbered by seven liens. Six of those liens were held by Horizon State Bank (the “Bank”) either jointly with or guaranteed by the Farmer’s Home Administration (“FHA”). A seventh hen (the “McQuinn hen”) was privately held.

Gary Minor and Gina Carter originally offered $1,000 per acre for Sellers’ land. Under a twenty-four hour deadline to accept the offer, Sellers asked the Bank whether the sale would be sufficient to clear enough debt to enable the Bank to release the property. Bank informed Sellers that a sale at that price “looked like” it would clear the hens held by the Bank. Sellers accepted Buyers’ offer and entered into a contract for the sale of the land. The contract between the parties stated that Sellers would provide title in fee simple, but did not provide for any contingencies if Sellers’ proceeds were not sufficient to release the liens.1

In preparing the paperwork for the closing, the Bank requested a final payoff amount from FHA. FHA informed the Bank that there was an additional $25,000 in deferred payment outstanding. Although the Bank had annuahy contacted FHA to provide information of the outstanding loan balance to permit the Bank to determine the amount of operating loans for Sellers’ following growing season, information about the outstanding deferred payment balance had not been in-eluded in the information provided by FHA. The Bank also became aware of the McQuinn lien at this time. Over $50,000 would be required to retire the debt secured by that lien.

Given the amount of money necessary to cover the deferred payments to FHA and obtain a release of the McQuinn lien, the Bank determined that the sale price would be insufficient to clear the debt and refused to release its liens on the property. Because the Bank was unwilling to provide a Deed of Release, Sellers were unable to tender title in fee simple at closing. Buyers brought suit for breach of contract seeking specific performance of the contract. Sellers defended that because the Bank would not release the liens, performance was impossible. The trial court held that Sellers had breached the contract of sale and ordered specific performance of the contract. This appeal follows.

Standard of Review

Appellate review of court-tried cases is governed by the standard articulated in Murphy v. Carron, 536 S.W.2d 30 (Mo. banc 1976). Under that standard, a trial court’s judgment will be affirmed unless no substantial evidence supports it, it is against the weight of the evidence, or it erroneously declares or applies the law. Id. at 32.

Discussion

In their sole point on appeal, Sellers claim that the trial court erred in ordering specific performance for the reason that the Bank’s refusal to release its deed of trust rendered their performance *213under the contract impossible.2 Sellers do not question the sufficiency or weight of the evidence. Their only claim is that the trial court erred in its declaration and application of the law. As a general rule, when a party contracts to do “a thing possible to be performed, he will not be excused ... because unforeseen difficulties are encountered.” Webb-Boone Paving Co. v. State Highway Comm’n, 351 Mo. 922, 178 S.W.2d 580, 584 (1943) (quoting United States v. Spearin, 248 U.S. 132, 136, 54 Ct.Cl. 187, 39 S.Ct. 59, 63 L.Ed. 166 (1918)). Thus, a party to a contract must perform thereunder “unless performance is rendered impossible by an Act of God, the law, or the other party.” Farmers’ Elec. Coop., Inc. v. Mo. Dep’t of Corr., 977 S.W.2d 266, 271 (Mo. banc 1998). In order for a contingency not resulting in impossibility to excuse performance, the party wishing to be excused must provide for that contingency in the contract. Stein v. Bruce, 366 S.W.2d 732, 734 (Mo.App.1963).

Here, Sellers argue they cannot provide fee simple title because the Bank’s refusal to provide a Deed of Release renders their performance impossible. In this regard, Sellers direct this court’s attention to Werner v. Ashcraft Bloomquist, Inc., 10 S.W.3d 575 (Mo.App. E.D.2000), in which it was noted that “if the fulfillment of the contract depends on the act or consent of a third party, the contract is unenforceable until the third party so acts or consents.” Id. at 578.

Sellers’ reliance on Werner is misplaced. In that case, a contractor entered into a remodeling contract with the owners of a shopping center. Id. at 576. The contractor then subcontracted the removal and reinstallation of signage in front of the shopping center. After the subcontractor had removed the signage, the owners of the shopping center decided to purchase new signage instead of reinstalling the old signage. Id. The contractor then paid the subcontractor for the work already done and discontinued the subcontract. Id. The subcontractor sued for breach of contract, and the contractor took an appeal from an adverse judgment, claiming that the owner’s decision to replace the signage rendered their contractual duties impossible of performance. Id. at 576-77.

On appeal, the Eastern District of this court noted that the doctrines of commercial frustration and impossibility would, in appropriate cases, excuse performance of contractual duties. Id. at 578. Nonetheless:

if a party to a contract unconditionally undertakes to perform an act that is not impossible, but merely requires a third party to acquiesce or perform a preceding act, the party’s performance is not deemed to be conditioned on the third party’s acquiescence or performance. In the latter situation, the inability to secure the necessary permission or acts of the third party does not excuse performance of the contract.

Id. (internal citations omitted). Of particular relevance to the case at bar, the Wer-ner court held that a change order by a customer is reasonably foreseeable in remodeling contracts. Id. at 577. Such a change order is, therefore, not the “type of *214unexpected event warranting consideration of the application of the impossibility of performance doctrine.” Id. Thus, before a party may be “excused from performance in the event of contingencies arising after the formation of a contract, it is that party’s duty to provide therefor[ ] in the contract.” Id.

In the instant case, Sellers did not condition the contract on the Bank releasing its liens on the property. The Bank’s first informal opinion that the sale proceeds would be sufficient to clear the liens was based on the information it had on hand at the time that opinion was rendered. Although both the Bank and Sellers knew that the liens were either guaranteed by or held jointly with FHA, neither the Bank nor Sellers contacted FHA prior to acceptance of the offer.

The Werner court further noted that, as between the contractor and subcontractor, the contractor was in a better position to anticipate the contingency that actually occurred. Id. Similarly, in the present case, both the Bank and Sellers, but not Buyers, had access to information concerning both Sellers’ financial condition and the relevant loans. Under these conditions, it cannot be said that the Bank’s withholding of consent falls within the stringent limits of the impossibility defense under Missouri law.

By accepting Buyers’ offer, Sellers ran the unstated — but not unprecedented— risk that there would be more debt outstanding than originally contemplated by the Bank’s informal approval. As in Wer-ner, Sellers assumed the risk associated with that contingency when they contracted with Buyers and cannot now claim that by withholding the Deed of Release, the Bank has rendered Sellers’ performance under that contract impossible.

Conclusion

Because the contingency that led to Sellers’ refusal to perform was not the result of an act of God, the law, or the other party, and was not otherwise unforeseeable, Sellers have failed to establish impossibility of performance in this specific performance action. The judgment of the trial court is affirmed.

ROBERT G. ULRICH, Judge, concurs in majority. HAROLD L. LOWENSTEIN, dissents in separate opinion.

. Of course, in order for Sellers to deliver a fee simple title they were required to convey the property free of liens.

. Sellers also argue in passing that specific performance is an inappropriate remedy because legal damages would provide adequate compensation and specific performance of the contract would work an undue hardship against the Sellers. Similarly, Sellers suggest that the contract "terminated under its own terms” when Sellers failed to tender clear title and Buyers failed to object thereto in writing. None of these arguments, however, are raised in Sellers’ Point Relied On, and are therefore not preserved for our review. Rule 84.04(e); see also Thummel v. King, 570 S.W.2d 679, 686 (Mo. banc 1978).